34-153-23007

Well Details

Well ID: 34-153-23007
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2007-08-01
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 41.0473778177
Longitude: -81.6401257255

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1158939113 2007-08-09 Interden Well Service was on site to complete the well. The pits will be used to flow back the well.
-1602528921 2007-08-21 The pits were pumped down as requested on 8/20. There is sufficient capacity to contain any rainfall.
-1712927633 2008-06-10 Preliminary restoration is approved.
1097858290 2007-08-08 The drilling rig has moved off. The pits are fenced and lined and in good condition. The pits must be solidified and closed by August 22.
1188439678 2007-08-23 Chemtech provided material to solidify the drilling pits. Schreiner plans to cover the pits on 8/24 to allow time for the pits to firm.
1200158419 2007-08-06 The drilling rig is moving off. The drilling location and pits are fenced, lined and in good condition. No violations at this time.
283160484 2007-07-31 The drilling pits have been dug and fenced. Drilling equipment is starting to arrive and the well should be spudded tomorrow.
349948413 2007-10-11 The well has been completed, the tank battery set and the preliminary grading and seeding has been done. The well can be turned on as soon as the required fencing is placed around the tank battery. Preliminary restoration will be approved at that time.
667489470 2007-08-20 The drilling pits are full after recent heavy rains. I contacted Schreiner representatives and told them to get the pits pumped down before they overflowed. The pits are scheduled to be solidified on 8/23.
950965065 2007-07-25 Schreiner has started building the location in anticipation of the drilling rig arriving in the next few days. The affected area will be fenced off.