Well Details

Well ID: 37-005-30723
Loading map...
Operator Name: PENNECO OIL CO INC
First Permit Date: 2010-10-22
Last Permit Date: 2010-10-22
Spud Date: 2010-12-20
Unconventional: No
Horizontal: No
Violations: None
Latitude: 40.709666
Longitude: -79.352416

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-0 3771.0 365.0 0.0 0.0 0.0 0.0
2012-0 5908.0 366.0 0.0 0.0 0.0 0.0
2011-0 5857.0 245.0 0.0 0.0 0.0 0.0
2010-0 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2011-0 PRODUCED FLUID 284.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508 PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO FRANKLIN PA
2011-0 FRACING FLUID WASTE 200.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1919940 2010-09-28 No Violations Noted 200ft bldg review - recommendations identified
1939564 2010-12-29 No Violations Noted Drilling was ongoing at the time of the inspection. Drill pit located onsite and it had more than the required two feet of lined freeboard. E&S controls had been implemented as outlined in the E&S plan. Site was adjacent to a utility shed located on the property. Clean durable rock had been utilized on the shared portion of the access road.
1953842 2011-03-02 No Violations Noted Drilling had been completed, well did not appeared to be equipped for production at the time of the inspection. Site had not been regraded & the drill pit was still located onsite. Pit had more than the required two feet of lined freeboard. Observed no erosion issues in relation to the site or access road. Operator should endeavor to complete site restoration as soon as the weather permits.