Well Details

Well ID: 063-36976
Loading map...
County: Indiana
Municipality: Brush Valley Township
Operator Name: CHEVRON APPALACHIA LLC
Farm/Lease Name: DICK 2H
First Permit Date: 2010-11-03
Last Permit Date: 2010-11-03
Spud Date: 2011-02-27
Unconventional: Yes
Horizontal: Yes
Producing: No
Violations: None
Latitude: 40.499333
Longitude: -79.068277

Well Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1944400 2011-01-20 No Violations Noted Marcellus well. Conductor pipe set. Site ID sign in place. E&S plan on site. Setting up drilling equipment at time of inspection.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed.

Site and access road snow covered at time of inspection, although no obvious signs of accelerated erosion were found leaving access road or well site.  Appeared as though all BMP's were in place in accordance with E&S plan, and were properly maintained.  Minor E&S issue discussed with operator representative Matt Barch, and addressed through compliance assistance in technical inspection of ESCGP-1 plan.  No drill pit constructed on site (closed loop system to be utilized).  No frac pit constructed yet.  No violations found.
1944602 2011-01-19 No Violations Noted
1955025 2011-02-28 No Violations Noted
1956871 2011-03-09 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Well being drilled at time of inspection (5900').

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. No drill pit constructed on site (closed loop system to be utilized). All tanks appeared sound and had adequate freeboard. No frac pit has been constructed on the site. No evidence of any spills or discharges. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan, and adequately maintained. Site is stabilized with rock. Perimeter of site seeded/mulched, and erosion blankets installed. No E&S issues found. No violations found.

1956965 2011-03-10 No Violations Noted
1958656 2011-03-17 No Violations Noted
1965129 2011-03-25 No Violations Noted Marcellus well. Site ID sign in place. E&S plan on site. Drilling recently completed. Not equipped for production.

Approved ESCGP-1 permit on site. Technical review of ESCGP-1 completed. Access road was stabilized with rock. Rock installed in all ditch lines, and culvert outlets. No signs of accelerated erosion on roadway. BMP's installed on site in accordance with E&S plan, and adequately maintained. Site is stabilized with rock. Perimeter of site seeded/mulched, and erosion blankets installed. No impoundments/pits on site. No E&S issues found. No violations found. No ev idence of any spills or discharges.

1979928 2011-06-08 No Violations Noted
2047591 2012-03-02 No Violations Noted
2057469 2012-04-05 No Violations Noted
2121858 2012-12-06 No Violations Noted
2126976 2012-12-06 No Violations Noted At the time of inspection, well sign, ES plan, and ESCGP-1 present. Access road stable. Well site gated. Multi well pad. Site is surrounding by wire fence in order to prevent third party access. Drilling completed 3/18/11. Pad adequately rocked. Wells drilled, not yet fraced nor equipped for production. Site is temporarily stabilized. No ES concerns noted. Operator has plans to permanently restore well site March 2013, a letter has been submitted discussing restoration efforts and timeline to Alan Eichler Program Manager OG SWRO. Hence prior arrangements for restoration to PCSM standards have been made no violations are currently noted; although operator should continue to closely monitor and maintain site and access road until final permanent restoration is achieved as outlined in memo. Department will be notified up commencemnt of final restoration activities. Chevron EHS personnel, Curtis Small, OGI Rick Hoover, and Environmental Trainee Samantha Foulk on site during inspection.

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2012-2 0.0 0.0 0.0 0.0 0.0 0.0
2012-1 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-1 0.0 0.0 0.0 0.0 0.0 0.0
2010-2 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2011-1 DRILL CUTTINGS 352.47 Tons LANDFILL 100172 WASTE MANAGEMENT, INC - ARDEN LANDFILL, INC. WASHINGTON PA