37-111-20305

Well Details

Well ID: 37-111-20305
Loading map...
County: Somerset
Municipality: Addison Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 149073
Farm/Lease Name: PMG GRACE UNIT 2H
First Permit Date: 2011-06-23
Last Permit Date: 2011-06-23
Spud Date: 2012-03-19
Unconventional: Yes
Horizontal: Yes
Well Status: ACTIVE
Violations: 0
Latitude: 39.757769
Longitude: -79.356536

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2011-1 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2011-2 0.0 0.0 0.0 0.0 0.0 0.0
2012-1 0.0 0.0 0.0 0.0 0.0 0.0
2012-2 0.0 0.0 0.0 0.0 0.0 0.0
2013-1 0.0 0.0 0.0 0.0 0.0 0.0
2013-2 474200.0 177.0 0.0 0.0 0.0 0.0
2014-1 399141.0 181.0 0.0 0.0 0.0 0.0
2014-2 316980.0 184.0 0.0 0.0 0.0 0.0
2015-02 24646.0 28.0 0.0 0.0 0.0 0.0
2015-01 46400.0 31.0 0.0 0.0 0.0 0.0
2015-03 32322.0 31.0 0.0 0.0 0.0 0.0

For data sources see[1]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2012-2 DRILL CUTTINGS 574.08 Tons LANDFILL 100419 ADVANCED DISPOSAL SERVICE CHESTNUT VALLEY LANDFILL MCCLELLANDTOWN PA
2012-2 DRILLING FLUID WASTE 40.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001 RONCO WASTE PROCESSING FACILITY MASONTOWN PA
2013-1 FRACING FLUID WASTE 108.7 Bbl REUSE OTHER THAN ROAD SPREADING REUSE FOR DRILLING OR PLUGGING
2013-1 FRACING FLUID WASTE 1.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001 RONCO WASTE PROCESSING FACILITY MASONTOWN PA
2013-2 FRACING FLUID WASTE 538.6 Bbl REUSE OTHER THAN ROAD SPREADING REUSE WITHOUT PROCESSING AT A PERMITTED FACILITY
2013-2 FRACING FLUID WASTE 7.0 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW001 RONCO WASTE PROCESSING FACILITY MASONTOWN PA
2013-2 PRODUCED FLUID 6.0 Bbl REUSE OTHER THAN ROAD SPREADING REUSE WITHOUT PROCESSING AT A PERMITTED FACILITY
2014-1 FLOWBACK FRACTURING SAND 33.56 Tons LANDFILL 100280 VALLEY LANDFILL IRWIN PA
2014-1 PRODUCED FLUID 3.0 Bbl REUSE OTHER THAN ROAD SPREADING REUSE WITHOUT PROCESSING AT A PERMITTED FACILITY
2014-2 PRODUCED FLUID 1.0 Bbl REUSE OTHER THAN ROAD SPREADING REUSE WITHOUT PROCESSING AT A PERMITTED FACILITY
2014-2 PRODUCED FLUID 26.67 Bbl INJECTION DISPOSAL WELL 34-121-23995 WARREN DRILLING CO #1 (SWIW #6) DEXTER CITY OH

For data sources see[2]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
2003970 2011-09-08 No Violations Noted
2016746 2011-11-03 No Violations Noted At the time of inspection, well sign (multi- well pad), ES Plan, ESCGP-1, PPC Plan present. Site gated and locked, as well as monitored by security. Access road and well pad adequately rocked and maintained. Well not yet drilled. No accelerated erosion or sedimentation issues noted during inspection. Bmp's are installed and appear to be functioning, although operator should continue to monitor and maintain all bmp's until final permanent restoration is complete. Previously disturbed areas have been temporarily seeded/mulched with observed growth. No violations noted during this inspection
2051551 2012-03-14 No Violations Noted Site visit was part of spud notification of the PMG Grace 2H.

There appears to be two wells drilled on this pad at this time. TDs are not known. No activity was taking place during inspection. Pad was vacant. Well(s) are not in production. Impoundment is built lined and fenced. Slopes of both the pad and the impoundment are well vegetated and stable. Access road is rocked and stable. BMPs are installed and appear to be working properly. No violations noted at this time.

2067335 2012-05-04 No Violations Noted At the time of inspection, no E&S issues were present at the site. Chevron had contracted Highland #8. Conductor pipe set at 52 ft. (24ï¾’ï¾’pipe) and was grouted in place. 11 3/4ï¾” pipe set at 759ï¾’ and used 514 sks of Type I with 14 bbl return. Drilling deviation was less than 1 %. DEP personnel performed a site walk and did not find any issues. Sedimentary zone at 707 feet was damp.
2078299 2012-06-20 No Violations Noted
2094693 2012-08-06 No Violations Noted At the time of inspection, no E&S issues were present at the site. Chevron had contracted Crown Rig #8. Upper section of well was completed with the following: conductor pipe set at 52 ft. (24ï¾’ï¾’pipe), 11 3/4ï¾” pipe set at 759ï¾’ and used 514 sks of Type I with 14 bbl return and 8 5/8ï¾” pipe at 2314 feet. Current depth was 7,605 feet. Currently, Chevron was building curve for the well.
2094820 2012-08-14 No Violations Noted At the time of inspection, no E&S issues were present at the site. Chevron had contracted Crown Rig #8. Current depth was 13,494 feet. KOP was 7,210 feet. Currently, Chevron was in the process of setting production pipe. Halliburton was present to cement pipe to surface.
2095544 2012-08-28 No Violations Noted At the time of inspection, no E&S issues were present at the site. Crown rig 8 was set up on well 3H to drill the curve and horizontal section.
2095547 2012-08-28 No Violations Noted At the time of inspection, no E&S issues were present at the site. Crown rig 8 was set up on well 3H to drill the curve and horizontal section.
2107579 2012-10-09 No Violations Noted
2123139 2012-12-12 No Violations Noted At the time of inspection, no E&S issues were present at the site. Gas well was not in production
2144615 2013-02-25 No Violations Noted Multi-well pad. Site ID sign, valid permit, E&S plan, ESCGPI, PPC plan all on-site.

At time of inspection, 2H drilled, but not yet equipped for production. 1H, 3H also drilled, not yet equipped for production. Access road in good condition, adequately rocked. No accelerated erosion or sedimentation issues observed in relation to well pad or access road. Department recommends Operator remove debris from rock-lined ditches. Spoke to company representative Beth Smock on 2/8/13 who informed Department that a 20x20 stone pad muster point was constructed alongside access road directly before well pad entrance. At time of inspection, Department noted that muster point did not go outside LOD and observed no potential E&S issues from its construction. Dept representative Samantha Foulk field-approved this change to the E&S plan. (Refer to ESCGP-1 admin inspection ID 2150218).

2160673 2013-04-23 Pending Incident inspection. Company reported a 10 gallon spill. Company could not find spill location. Asked company to locate spill.
2163939 2013-05-02 No Violations Noted Follow up inspection to a 4/21/13 spill. Spill Cleaned up correctely.
2169702 2013-05-22 No Violations Noted
2182696 2013-07-11 No Violations Noted Met with Chevron on site. No issues noted.
2229828 2013-09-26 No Violations Noted At the time of inspection, no E&S issues were present at the site. Well was in production.
2311293 2014-10-08 No Violations Noted Well appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in relation to the site or access road.

For data sources see[3]

References