37-003-22161

Well Details

Well ID: 37-003-22161
Loading map...
Country: United States
State: Pennsylvania
County: Allegheny
Municipality: Plum Borough
Operator Name: PENNECO OIL CO INC
Well Pad ID:
Farm/Lease Name: PARKER 1
License Status:
Spud Date:
Permit Date: 2011-01-27
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.508319
Longitude: -79.706653

For data sources see[1][2][3]

Well History

Date Event
2011-01-27 New Permit Application
2011-04-15 Performed Spud Operation
2011-04-25 Drilling Completion
2011-05-04 Perforation
2011-12-13 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 PENNECO OIL CO INC 0.00 0 0.00 0 0.00 0
2011 PENNECO OIL CO INC 5,969.00 184 72.30 184 0.00 0
2012 PENNECO OIL CO INC 8,229.00 366 0.00 0 0.00 0
2013 PENNECO OIL CO INC 6,580.00 365 0.00 0 0.00 0
2014 PENNECO OIL CO INC 6,158.00 365 0.00 0 0.00 0
2015 PENNECO OIL CO INC 6,046.12 365 0.00 0 0.00 0
2016 PENNECO OIL CO INC 5,263.67 366 0.00 0 0.00 0
2017 PENNECO OIL CO INC 4,685.00 365 0.00 0 0.00 0
2018 PENNECO OIL CO INC 4,059.01 365 0.00 0 0.00 0
2019 PENNECO OIL CO INC 3,742.62 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 PENNECO OIL CO INC Drilling Fluid Waste 1,598.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 PENNECO OIL CO INC Fracing Fluid Waste 240.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2013 PENNECO OIL CO INC Produced Fluid 40.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2013 PENNECO OIL CO INC Produced Fluid 40 Bbl CENT WASTE TRT FAC NPDES PA0095443
2015 PENNECO OIL CO INC Produced Fluid 30 Bbl CENT WASTE TRT FAC NPDES PA0095443
2015 PENNECO OIL CO INC Produced Fluid 30.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095443
2019 PENNECO OIL CO INC Produced Fluid 33.33 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1961867 Primary Facility 2011-03-18 Routine/Complete Inspection No Violations Noted On March 18th, 2011 I visited this site as a routine inspection. Drilling has not yet started. Construction of the pad was underway. The access road was in ok condition. A Site ID and E&S plan were posted onsite. E&S controls were in place. Pits were constructed. Some water was beginning to collect in the pits. Drill cutting disposal should be monitired to be sure they are not placed within the seasonal high water table, No accelerated erosion was observed at the time of inspection.
1975539 Primary Facility 2011-04-15 Routine/Complete Inspection No Violations Noted On April 15th, 2011 I visited this site as a routine inspection. Drilling has not yet started. Equipment was moving onsite. The access road was in ok condition. A Site ID and E&S plan were posted onsite. E&S controls were in place. No accelerated erosion was observed at the time of inspection.
1976429 Primary Facility 2011-04-25 Drilling/Alteration No Violations Noted DRILLING COMPLETE. WEATHERFORD IS LOGGING WELL.
1976437 Primary Facility 2011-04-20 Drilling/Alteration No Violations Noted USE RIG #7 DRILLING AT 1190'.
1976441 Primary Facility 2011-04-18 Drilling/Alteration No Violations Noted 20" CEMENTED ON 4/17/11. USE RIG #7 STARTING UP TO RESUME DRILLING.
1983662 Primary Facility 2011-04-19 Routine/Complete Inspection No Violations Noted On April 19th, 2011 I visited this site as a routine inspection. Drilling has started. Additional rock was being added to the access road A Site ID and E&S plan were posted onsite. E&S controls were in place. The pit appeared to be in good condition and had adequate freeboard. No accelerated erosion was observed at the time of inspection.
1983742 Primary Facility 2011-04-28 Routine/Complete Inspection No Violations Noted On April 28th, 2011 I visited this site as a routine inspection. Drilling was completed. The access road was in good condition. A Site ID and E&S plan were posted onsite. E&S controls were in place. The pit was open, contained fluids, and appeared to be in good condition and had adequate freeboard. No accelerated erosion was observed at the time of inspection.
1991689 Primary Facility 2011-07-11 Drilling/Alteration No Violations Noted THIS GAS WELL IS COMPLETE.
1993501 Primary Facility 2011-08-04 Site Restoration No Violations Noted On August 4th, 2011 I visited this site as a routine inspection. Drilling was completed. The well was in production. The access road was in good condition. A Site ID and E&S plan were still posted onsite. A well tag was present. One tank was surrounded with a dike. The site was restored and vegetation was coming in nicely. No accelerated erosion was observed at the time of inspection.
2111656 Primary Facility 2012-10-31 Routine/Complete Inspection No Violations Noted John Ley WQS, SWRO was on site to conduct an inspection. At the time of the inspection, the well site sign and label were on site. The well was drilled and equipped for production. The associated well apparatus located onsite appeared to be in sound working condition. There were no erosion or sedimentation issues. The area around the pad meets the 70% uniform vegetative coverage.

For data sources see[7]

References