37-005-30437

Well Details

Well ID: 37-005-30437
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: Cowanshannock Township
Operator Name: SNYDER BROS INC
Well Pad ID:
Farm/Lease Name: J LUNDGREN ETAL 6-73
License Status:
Spud Date:
Permit Date: 2009-08-21
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.803590
Longitude: -79.350087

For data sources see[1][2][3]

Well History

Date Event
2009-08-21 New Permit Application
2010-02-15 Performed Spud Operation
2010-02-25 Drilling Completion
2010-03-16 Perforation
2011-07-25 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 SNYDER BROS INC 5,742.00 207 0.00 0 0.00 0
2011 SNYDER BROS INC 6,238.00 329 0.00 0 0.00 0
2012 SNYDER BROS INC 4,017.00 314 0.00 0 0.00 0
2013 SNYDER BROS INC 4,761.00 360 0.00 0 0.00 0
2014 SNYDER BROS INC 3,517.00 356 0.00 0 0.00 0
2015 SNYDER BROS INC 3,078.00 344 0.00 0 0.00 0
2016 SNYDER BROS INC 2,664.00 337 0.00 0 0.00 0
2017 SNYDER BROS INC 1,985.00 276 0.00 0 0.00 0
2018 SNYDER BROS INC 2,848.00 317 0.00 0 0.00 0
2019 SNYDER BROS INC 3,414.00 349 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 SNYDER BROS INC Produced Fluid 20.00 Bbl INJECTION DISPOSAL WELL 34-099-23158

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1821247 Primary Facility 2009-08-18 Complaint Inspection No Violations Noted Site constructed, drilling had not commenced at the time of the inspection. Erosion control measures were implemented as outlined in the E&S plan located onsite. The controls implemented should effectively minimize accelerated erosion & sedimentation, provided they are maintained properly.
1863467 Primary Facility 2010-02-17 Routine/Complete Inspection No Violations Noted Site constructed, drilling had not commenced at the time of the inspection.
1865030 Primary Facility 2010-02-23 Routine/Complete Inspection No Violations Noted Drilling was ongoing at the time of the inspection. Below grade pit located onsite at the time of the inspection. Pit had more than the two feet of lined freeboard. Observed no accelerated erosion & sedimentation on the site or access road at the time of the inspection. The operator should evlauate the access road and site erosion controls as the weather improves to insure they continue to function properly. During moving the rig off-site and any susbequent heavy truck traffic the operator should inspect the access road and place additional rock as neccesary. The operator should also have a plow/broom truck available to address any mud which might be transported onto Route 85.

For data sources see[7]

References