37-051-24393

Well Details

Well ID: 37-051-24393
Loading map...
Country: United States
State: Pennsylvania
County: Fayette
Municipality: German Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 148144
Farm/Lease Name: CROUSHORE UNIT 12H
License Status:
Spud Date:
Permit Date: 2010-09-28
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 39.9028
Longitude: -79.908736

For data sources see[1][2][3]

Well History

Date Event
2010-09-28 New Permit Application
2010-11-05 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2011-06-22 2011-06-22 7,975 1,929,794

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Iron Control A Nalco Iron Control Ethylene glycol 107-21-1 30.00 0.00690000
7.5 Hcl Acid Used to open perfs Hydrochloric acid 7647-01-0 7.50 0.38
Proppant (lbs) Proppant 100.00 8.52
Unislik ST 50 CESI Chemical Friction Reducer Distillates, petroleum, hydrotreated light 64742-47-8 30.00 0.03
GBL Clearwater International Gel Breaker Ethylene glycol 107-21-1 60.00 0.00002000
Biocide EC 6116A Nalco Biocide 2,2-Dibromo-3-nitrilopropionamide 10222-01-2 30.00 0.00688000
Polyethylene glycol 25322-68-3 60.00 0.01
Dibromoacetonitrile 3252-43-5 5.00 0.00115000
CMHPG Ashland Water Viscosifier Carboxymethylhydroxyporoyl guar blend 100.00 0.00199000
Clean Volume (gals) Carrier/Base Fluid 100.00 91.48
Scale Inhibitor A Nalco Scale Inhibitor Ethylene glycol 107-21-1 30.00 0.00680000

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 ATLAS RESOURCES LLC 0.00 0 0.00 0 0.00 0
2011 CHEVRON APPALACHIA LLC 88,699.00 72 0.00 0 0.00 0
2012 CHEVRON APPALACHIA LLC 237,923.00 366 0.00 0 0.00 0
2013 CHEVRON APPALACHIA LLC 156,010.00 365 0.00 0 0.00 0
2014 CHEVRON APPALACHIA LLC 129,253.00 334 0.00 0 0.00 0
2015 CHEVRON APPALACHIA LLC 113,979.00 365 0.00 0 0.00 0
2016 CHEVRON APPALACHIA LLC 101,973.00 366 0.00 0 0.00 0
2017 CHEVRON APPALACHIA LLC 90,920.00 365 0.00 0 0.00 0
2018 CHEVRON APPALACHIA LLC 83,729.00 365 0.00 0 0.00 0
2019 CHEVRON APPALACHIA LLC 79,744.00 365 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 65.00 Bbl LANDFILL SWF 1032-WV0109
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 12,757.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 2,097.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001
2011 CHEVRON APPALACHIA LLC Produced Fluid 385.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CHEVRON APPALACHIA LLC Produced Fluid 1,079.00 Bbl INJECTION DISPOSAL WELL 34-121-2-3995
2012 CHEVRON APPALACHIA LLC Produced Fluid 1,709.00 Bbl REUSE OTHER THAN ROAD SPREADING
2012 CHEVRON APPALACHIA LLC Produced Fluid 240.00 Bbl INJECTION DISPOSAL WELL 34-121-23995
2013 CHEVRON APPALACHIA LLC Produced Fluid 580.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 CHEVRON APPALACHIA LLC Produced Fluid 1,430.33 Bbl REUSE OTHER THAN ROAD SPREADING
2014 CHEVRON APPALACHIA LLC Produced Fluid 20.00 Bbl INJECTION DISPOSAL WELL 34-121-23995
2015 CHEVRON APPALACHIA LLC Produced Fluid 1,054.33 Bbl REUSE OTHER THAN ROAD SPREADING
2016 CHEVRON APPALACHIA LLC Produced Fluid 513.34 Bbl REUSE OTHER THAN ROAD SPREADING
2016 CHEVRON APPALACHIA LLC Produced Fluid 530.36 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW019
2017 CHEVRON APPALACHIA LLC Produced Fluid 279.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2017 CHEVRON APPALACHIA LLC Drilling Fluid Waste 35.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2017 CHEVRON APPALACHIA LLC Produced Fluid 138.33 Bbl REUSE (AT WELL PAD)
2017 CHEVRON APPALACHIA LLC Produced Fluid 36.67 Bbl REUSE AT A WELL PAD OUTSIDE PENNSYLVANIA
2017 CHEVRON APPALACHIA LLC Produced Fluid 3,416.67 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW001
2018 CHEVRON APPALACHIA LLC Produced Fluid 23.33 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2018 CHEVRON APPALACHIA LLC Produced Fluid 294.01 Bbl REUSE (AT WELL PAD)
2018 CHEVRON APPALACHIA LLC Produced Fluid 493.34 Bbl REUSE AT A WELL PAD OUTSIDE PENNSYLVANIA
2018 CHEVRON APPALACHIA LLC Produced Fluid 60.67 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2019 CHEVRON APPALACHIA LLC Produced Fluid 486.66 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1938144 Primary Facility 2010-11-17 Drilling/Alteration No Violations Noted HOIZONTAL MARCELLUS, (ROCKY MOUNTAIN DRILLING ) DRILLED AND CEMENTED 40' OF 24" CONDUTOR CASING. E&S IN GOOD CONDITION.
1938151 Primary Facility 2010-11-29 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S IN GOOD CONDITION. WHIPSTOCK # 17 MOVING TO CROUSHORE # 12-H TODAY.
1938157 Primary Facility 2010-12-03 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S IN GOOD CONDITION. WHIPSTOCK # 17 PREPAIRING TO RUN 11 3/4" COAL STRING CASING.
1938170 Primary Facility 2010-12-09 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S IN GOOD CONDITION. WHIPSTOCK # 17,CEMENTING 8 5/8" INTERMEDIATE CASING STRING EVENING OF 12/8/2010.THE CEMENT FLASH SET LEAVING A UNKWOWN AMOUNT OF CEMENT INSIDE THE 8 5/8" AND FROM THE SHOE TO SURFACE.JOHN RICE CALLED FOR ADVICE. I REFERENCE TO MIKE ARCH FOR ADVICE. MR. RICE DECIDED TO DRILL OUT 8 5/8"CASING. RUN A BOND LOG TO DETERMINE WHERE THE BACK SIDE CEMENT IS LOCATED. PERFORATE ABOVE LOCATED CEMENT AND PERFORM A SQEEZE JOB.
1938173 Primary Facility 2010-12-13 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS,E&S IN GOOD CONDITION.WHIPSTOCK # 17MOVING OFF, NOMAC -235 MOVING ON LOCATION.DRILLING 8 5/8" INSIDE CASING TO 2854',RUNNING BOND LOG TO VERIFY CEMENT LOCATION. TOP OF CEMENT @ (2120') PLANNING TO PERF @ (2020') 100' ABOVE GOOD CEMENT. PERFORMED PERFERATIONS AND DO A SQUEEZE JOB WITH 10 BARRELS OF CEMENT RETURNS TO SURFACE. USED 570 CLASS (A) CEMENT,2% CAL. CHORIDE , NO FLAKE , AND 15.6 POUND WEIGHT MIXTURE. WAITED 12 HRS. TO SET UP.PITS LOOK GOOD.
1939662 Primary Facility 2010-12-27 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS , NOMAC - 235 IS RIG ON LOCATION DRILLED TO 8460 ' CEMENTED BACK TO 6900 ' .E&S AND PITS ARE GOOD. KOP WILL BE @ 6900 ' ,LOADED HOLE WITH MUD AND CAPPED.
1939755 Primary Facility 2010-12-29 Routine/Complete Inspection No Violations Noted HORIZONTAL MARCELLUS
1943663 Primary Facility 2010-01-07 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, NOMAC-235 FINISH DRILLING @ 8300 ' . CEMENTED PLUG BACK TO 7200 ' (KOP). MUDDED AND CAPPED WELL. PATTERSON - 227 MOVING ON STARTING 1/10/2011 (NEW- RIG). E&S AND PITS ARE IIN GOOD CONDITION.
1948362 Primary Facility 2011-02-07 Routine/Complete Inspection No Violations Noted
1955535 Primary Facility 2011-03-08 Routine/Complete Inspection No Violations Noted
1958204 Primary Facility 2011-02-08 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S AND PITS ARE IN GOOD CONDITION.FINISHING RUNNING PROD. STRIG,CLEANING HOLE PREPAIRING TO CEMENT IN LATE TONIGHT.
1958211 Primary Facility 2011-02-07 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S AND PITS ARE IN GOOD CONDITION. KOP 7000' LANDING IN LOWER MARCELLUS @ 8186' DRILLING ON TO TD.
1958216 Primary Facility 2011-02-02 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S AND PITS ARE IN GOOD CONDITION. (REVISE WELL PLAN) ATTACHED WITH PLUG BACK TWO.ATTEMTING NEW ANGLE AT LOWER MARCELLUS FORMATION.
1958226 Primary Facility 2011-01-28 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS,E&S AND PITS IN GOOD CONDITION.(REVISE WELL PLAN),CEMENT PLUG WAS SET @ 6100' TO HIGH IN MARCELLUS 1ST TIME. KOP @ 6985'WITH EXSPECTED LANDING POINT @ 8225'.SMALL O-RING LEAK FROM DISEL GENERATOR MOTOR. CLEAN UP,NO NOTICABLE RESIDUE ON PLASTIC COTAIMENT AREA. THE AMOUNT WAS LESS THAN 2 QUARTS.
1958273 Primary Facility 2011-01-24 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S AND PITS ARE IN GOOD CONDITION.NEW RIG WORKING OUT SMALL PROBLEMS.KOP @ 7200'.STARTING TO GET OFF IN CURVE.
1961130 Primary Facility 2011-03-28 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS,E&S AND PITS LOOK IN GOOD CONDITION. ALL WELLS ON PAD ARE COMPLETED.RIG MOVING OFF.
1964317 Primary Facility 2011-04-06 Routine/Complete Inspection No Violations Noted
1984452 Primary Facility 2011-06-21 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS, E&S AND PITS LOOK IN GOOD CONDITION. RECEIVED CALL FROM JIM BRAUNNS OF CHEVRON CONCERNING H/2 S GAS @ 6 -TANKS DESIGN TO STORE F/W FOR FRACING. STARTED @ 5.6 (PPM) @ 4:45 AND INCREASED TO 20(PPM) BY 6:00 PM,ONLY AT TOP HATCH. REMOVED ALL PERSONALIN AREA AND STARTED MONITORING THIS AREA. CONTINUE FRAC JOB UNTIL FINISH @ 7:00 PM.WAITED TILL 12:00 PM FOR CHEVRON H/2 S SAFETY CREWS WITH AIR- PACKS. THE READING WAS ZERO @ MID-NIGHT.THIS HAS HAPPEN WHEN EXTREME MUGGY AND HIGH TEMPS OCCURED. TALKED ABOUT CHLORINATION BETWEEN PITS AND STORAGE TANKS AS F/W IS BEING TRANSFER OVER.
1984805 Primary Facility 2011-06-27 Routine/Complete Inspection No Violations Noted
1989862 Primary Facility 2011-07-20 Routine/Complete Inspection No Violations Noted
2029228 Primary Facility 2011-12-21 Routine/Complete Inspection No Violations Noted Met onsite with Chevron representative Chad Eisenman. Drilling had been completed, well appeared tohave been equipped for production. Site grading work was in the process of being completed. Discussed final site restoration with Mr. Eisenmann while onsite. Site will be temporarily stabilized during the winter months and in the spring of 2012 final restoration will be completed.
2101460 Primary Facility 2012-09-18 Routine/Complete Inspection No Violations Noted Site ID sign in place, site fenced and gated, tanks in containment, wells labeled.
2488218 Primary Facility 2016-05-20 Routine/Complete Inspection No Violations Noted HORIZONTAL MARCELLUS, Routine Inspection all looks good.
2488219 Primary Facility 2016-05-20 Routine/Complete Inspection No Violations Noted HORIZONTAL MARCELLUS, Routine Inspection all looks good.

For data sources see[8]

References