Well ID: 37-051-24580
Loading map...
County: Fayette
Municipality: Luzerne Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 145470
Farm/Lease Name: HALL/HOGSETT UNIT 13H
First Permit Date: 2013-04-30
Last Permit Date: 2013-04-30
Spud Date: 2013-05-17
Unconventional: Yes
Configuration: Horizontal
Well Status: ACTIVE
Violations: 0
Latitude: 39.929327
Longitude: -79.908822

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-1 0.0 0.0 0.0 0.0 0.0 0.0
2013-2 0.0 0.0 0.0 0.0 0.0 0.0
2014-1 0.0 0.0 0.0 0.0 0.0 0.0
2014-2 0.0 0.0 0.0 0.0 0.0 0.0
2015-02 0.0 0.0 0.0 0.0 0.0 0.0
2015-01 0.0 0.0 0.0 0.0 0.0 0.0
2015-03 0.0 0.0 0.0 0.0 0.0 0.0
16-Jan 0.0 0.0 0.0 0.0 0.0 0.0
15-Aug 0.0 0.0 0.0 0.0 0.0 0.0
15DECU 0.0 0.0 0.0 0.0 0.0 0.0
15JULU 0.0 0.0 0.0 0.0 0.0 0.0
15MAYU 0.0 0.0 0.0 0.0 0.0 0.0
15OCTU 0.0 0.0 0.0 0.0 0.0 0.0
15OCTU 0.0 0.0 0.0 0.0 0.0 0.0
15SEPU 0.0 0.0 0.0 0.0 0.0 0.0
16APRU 0.0 0.0 0.0 0.0 0.0 0.0
16FEBU 0.0 0.0 0.0 0.0 0.0 0.0
16MARU 0.0 0.0 0.0 0.0 0.0 0.0

For data sources see[1]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION COMMENT
2166383 2013-04-10 No Violations Noted Pre-op done on site. All oerimeter E&S in place.
2170016 2013-05-20 No Violations Noted HORIZONTAL MARCELLUS, ROCKY MOUNTAIN DRILLING 24" CONDUCTOR PIPE @ 52' CEMENTING IN WITH NO PROBLEMS (5/18/2013).
2204935 2013-07-05 No Violations Noted HORIZONTAL MARCELLUS, INSPECTION REPORT HALL- HOGSETT # 13 -H (7/5/2013) 9:00 AM, ANDINSPECTION REPORT # 2204935
2204938 2013-07-09 Pending HORIZONTAL MARCELLUS, REFER TO INSPECTION REPORT HALL-HOGSETT # 13-H ,(7/9/2013) PENDING VIOLATIONS.
2204944 2013-07-11 Outstanding Violations - No Viols Req'd HORIZONTAL MARCELLUS, HIGHLANDS # 14 DRILLING ON AIR @ 2314' (TD). RUNNING INTERMEDIATE CASING AND CEMENT TONIGHT.
2204947 2013-07-16 Outstanding Violations - No Viols Req'd HORIZONTAL MARCELLUS, HIGHLANDS # 14 DRILLING ON AIR @ 8101' (TD)' SET 2- CEMENT PLUGS BACK TO 6701'. MUDDING -UP AND CAPPING TODAY. MOVING TO HALL- HOGGSETT# 14-H TONIGHT..
2204972 2013-07-01 No Violations Noted HORIZONTAL MARCELLUS, HIGHLANDS # 14 RIGGING -UP AND PLANNING TO START DRILLING THIS EVENING.
2230523 2013-12-04 No Violations Noted HORIZONTAL MARCELLUS, PACE X -08 MOVING ON TODAY (12/3/2013) RIGGING -UP AND TAGGING -UP (KOP) OF 6742'.
2230535 2013-12-13 No Violations Noted HORIZONTAL MARCELLUS,PACE X- 08 DRILLING ON FLUID @ 11,364 (TD). RAN 51/2" PROD. CASING AND CEMENTING (12/11/2013) RECEIVED CALL ON ( 12/12/2013)WHILE CEMENTING 51/2" PROD, CASING FAILURE TO SEE CEMENT RETURNS TO SURFACE.
2362053 2015-04-13 No Violations Noted The Hall-Hogsett site contained a large area on the slope to the left side of the pad upon entry that exhibited rills and little vegetation. It is recommended that this area be addressed to prevent further accelerated erosion. There were also residual waste containers and a non haz waste barrel on containment that was in disrepair. The containment has multiples holes and a berm breach. Waste barrels should be labeled for contents and dated to comply with storage requirements for waste.

For data sources see[2]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2013-2 DRILL CUTTINGS 901.24 Tons LANDFILL 100172 ARDEN LANDFILL WASHINGTON PA
2013-2 DRILLING FLUID WASTE 955.0 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW001 RONCO WASTE PROCESSING FACILITY MASONTOWN PA
2014-1 DRILL CUTTINGS 5.55 Tons LANDFILL 100172 ARDEN LANDFILL WASHINGTON PA
2014-1 DRILL CUTTINGS 20.1 Tons LANDFILL 100592 SOUTH HILLS LANDFILL SOUTH HILLS PA
2014-1 DRILLING FLUID WASTE 35.0 Bbl REUSE OTHER THAN ROAD SPREADING REUSE WITHOUT PROCESSING AT A PERMITTED FACILITY
2014-2 FRACING FLUID WASTE 3.0 Bbl REUSE OTHER THAN ROAD SPREADING REUSE WITHOUT PROCESSING AT A PERMITTED FACILITY
2014-2 FRACING FLUID WASTE 1.0 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW001 RONCO WASTE PROCESSING FACILITY MASONTOWN PA