37-063-33843

Well Details

Well ID: 37-063-33843
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: Conemaugh Township
Operator Name: ALLIANCE PETRO CO LLC
Well Pad ID:
Farm/Lease Name: ETHEL GOLDSMITH 7
License Status: ACTIVE
Spud Date: 2004-07-22
Permit Date: 2004-06-24
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.477372
Longitude: -79.414654

For data sources see[1][2][3]

Well History

Date Event
2004-06-24 New Permit Application
2004-07-21 Performed Spud Operation
2004-07-24 Drilling Completion
2004-08-03 Perforation
2004-11-18 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2004 PHILLIPS EXPLORATION INC 7121 91 0.00 0 0.00 0
2005 PHILLIPS EXPLORATION INC 17281 365 0.00 0 0.00 0
2006 PHILLIPS EXPLORATION INC 13,038.00 352 0.00 0 0.00 0
2007 PHILLIPS EXPLORATION INC 10531.00 365 0.00 0 0.00 0
2008 PHILLIPS EXPLORATION INC 7466.00 366 0.00 0 0.00 0
2009 PHILLIPS EXPLORATION INC 6767.00 365 0.00 0 0.00 0
2010 PHILLIPS EXPLORATION INC 6,286.00 365 0.00 0 0.00 0
2011 PHILLIPS EXPLORATION INC 5,980.00 364 0.00 0 0.00 0
2012 XTO ENERGY INC 5,910.00 366 0.00 0 0.00 0
2013 XTO ENERGY INC 6,591.00 365 0.00 0 0.00 0
2014 XTO ENERGY INC 5,648.00 365 0.00 0 0.00 0
2015 XTO ENERGY INC 4,545.00 334 0.00 0 0.00 0
2016 XTO ENERGY INC 4,247.80 306 0.00 0 0.00 0
2017 ALLIANCE PETRO CO LLC 3,539.00 334 0.00 0 0.00 0
2018 ALLIANCE PETRO CO LLC 3,645.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2008 PHILLIPS EXPLORATION INC Brine 80.00 Bbl Brine or Industrial Waste Treatment Plt PA0101508
2015 XTO ENERGY INC Produced Fluid 52 Bbl CENT WASTE TRT FAC NPDES PA0095273
2015 XTO ENERGY INC Produced Fluid 52.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1870207 Primary Facility 2010-03-10 Routine/Complete Inspection No Violations Noted According to records, operator completed the well on 7/22/04 to depth of 3746ft. WRAC submitted on 8/24/04. Well head consisted of 8¿ pipe to 4¿ to 2¿ production pipe with shut off valves. Production equipment consisted of separator; totalize meter (8820 MCF) and 100 bbl brine tank (with < 10 bbl fluid). At the time of inspection, no IW and E&S issues at the site. No odor of gas leakage at well head. Missing well tag appears to be painted over during painting of wellhead. DEP request for a new well tag.
1974457 Primary Facility 2011-05-02 Routine/Complete Inspection No Violations Noted Annulus closed ; Site restored ; 100 bbl tank on location
2424284 Primary Facility 2015-11-10 Administrative/File Review In Compliance with Policy SPILL.
2424320 Primary Facility 2015-11-10 Administrative/File Review In Compliance with Policy Admin inspt conducted in response to spill reported under inspt ID 2424284 for reportable release of 35 gal brine.At 1400, Dept contacted Opr rep J.Canose via phone.According to Mr. Canose, release resulted when tank was being prepared to be emptied by water truck.An attempt was made to remove plug on valve w/a wrench;however,threads were corroded,which caused brine to be released from tank before hose could be connected for proper emptying.Per Mr. Canose, hose was immediately placed under draining fluids until tank emptied.Fluids traveled onto ground and into nearby tire rut.Brine was immediately vac’d up.Mr. Canose is estimating release of 35 gal brine,will submit spill calcs to Dept.According to Mr. Canose, excavation of all visibly impacted materials has commenced,two roll-off boxes en route to site.No waterways reported to be impacted.Opr appears to be ICP at this time.A FUI will be conducted to assess any environmental impact and/or issue any associated violations as necessary.
2424452 Primary Facility 2015-11-12 Incident- Response to Accident or Event Violation(s) Noted On-site inspt conducted in response to admin inspt 2424284 for 11/10 reportable release of 35 gal brine from production tank.At time of inspt, all visibly impacted materials appear excavated in accordance with the Dept’s Spill Policy.Temp BMPs installed down-gradient of excavated areas.Two covered roll-off boxes on-site.BT disconnected and moved to edge of well site.WT present, legible.According to records, drilling occurred 7/22/04-7/24/04.Shared AR stable.Dept recommends Opr ensure all disturbed areas on well site are temp stabilized w/in 4 days of cessation of earth disturbance activities per current regs.A FUI will be conducted to ensure site is properly remediated and restored.Viols are being issued for this reportable release of production fluids.At this time, the Dept is requesting the Opr submit all disposal records/manifests upon final disposition of wastes to the Dept at the provided address.
2434486 Primary Facility 2015-12-14 Follow-up Inspection Outstanding Violations - No Viols Req'd On-site FUI conducted in response to violations issued under inspection ID 2424452 (enf ID 331567) for the 11/10 reportable release of 35 gal brine from production tank.At time of inspt, all visibly impacted materials appear excavated in accordance with the Dept’s Spill Policy, not yet backfilled.Temporary BMPs installed down-gradient of excavated areas.Two covered roll-off boxes on-site.Brine tank does not remain on-site.Shared access road stable.A follow-up inspection will be conducted to ensure site is properly remediated and restored.Violations issued under inspection ID 2424452 (enf ID 331567) remain outstanding. Requested written response to violations received 11/30/2015.
2442690 Primary Facility 2016-01-21 Compliance Evaluation No Violations Noted On-site CEI conducted in response to violations issued under inspection ID 2424452 (enf ID 331567) for the 11/10 reportable release of 35 gal brine from production tank.At time of inspection, site appears to have been backfilled, however due to snow-cover, Department unable to adequately verify completion of backfilling. During inspection, Department contacted Operator representative Jason Canose via phone. Mr. Canose verbally confirmed the completion of backfilling at this site.Temporary BMPs remain installed. Two covered roll-off boxes on-site no longer remain on-site.A follow-up inspection is anticipated to be conducted in the future to ensure site is properly restored as per current regulations. Violations may be forthcoming pending future inspections monitoring site remediation and permanent stabilization.Violations issued under inspection ID 2424452 (enf ID 331567) have been corrected.
2634909 Primary Facility 2017-09-12 Routine/Complete Inspection No Violations Noted Inspection conducted to assess remediation of site as a spill previously occurred at this location. Violations were issued under inspection record 2424452 and subsequently corrected under inspection record 2442690.

At time of inspection, well drilled and appears to be equipped for production. No brine tank on-site.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2424452 738997 11/10/2015 2015-11-10 78.54 - GENERAL REQUIREMENTS - Operator failed to control and dispose of fluids, residual waste and drill cuttings, including tophole water, brines, drilling fluids, drilling muds, stimulation fluids, well servicing fluids, oil, and production fluids Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
738997 331567 NOV - Notice of Violation Comply/Closed 2016-02-01

For data sources see[7]