37-063-36529

Well Details

Well ID: 37-063-36529
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: Conemaugh Township
Operator Name: ALLIANCE PETRO CO LLC
Well Pad ID:
Farm/Lease Name: J S MARSHALL 6
License Status:
Spud Date: 2009-08-25
Permit Date: 2009-04-24
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.499068
Longitude: -79.336099

For data sources see[1][2][3]

Well History

Date Event
2009-04-24 New Permit Application
2009-08-25 Performed Spud Operation
2009-08-28 Drilling Completion
2009-09-02 Perforation
2010-09-28 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2009 CONSOL GAS CO 6173.20 365 0.00 0 0.00 0
2010 CONSOL GAS CO 15,042.00 365 0.00 0 0.00 0
2011 CONSOL GAS CO 0.00 0 0.00 0 0.00 0
2012 CNX GAS CO LLC 8,419.00 366 0.00 0 0.00 0
2013 CNX GAS CO LLC 7,366.63 365 0.00 0 0.00 0
2014 CNX GAS CO LLC 5,506.72 365 0.00 0 0.00 0
2015 CNX GAS CO LLC 5,523.98 365 0.00 0 0.00 0
2016 CNX GAS CO LLC 5,416.35 366 0.00 0 0.00 0
2017 CNX GAS CO LLC 3,947.15 365 0.00 0 0.00 0
2018 CNX GAS CO LLC 3,752.46 365 0.00 0 0.00 0
2019 ALLIANCE PETRO CO LLC 4,885.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2009 CONSOL GAS CO Fracking Fluid 880.00 Bbl Brine or Industrial Waste Treatment Plt PA0091472
2009 CONSOL GAS CO Fracking Fluid 500.00 Bbl Brine or Industrial Waste Treatment Plt PA0095443
2009 CONSOL GAS CO Drilling 300.00 Bbl Brine or Industrial Waste Treatment Plt PA0091472
2009 CONSOL GAS CO Drilling 700.00 Bbl Other 37-063-36676
2009 CONSOL GAS CO Brine 145.00 Bbl Brine or Industrial Waste Treatment Plt PA0091472
2010 CONSOL GAS CO Produced Fluid 75.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2010 CONSOL GAS CO Produced Fluid 80.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 CNX GAS CO LLC Produced Fluid 32.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2012 CNX GAS CO LLC Produced Fluid 4.45 Bbl INJECTION DISPOSAL WELL 34-007-22038
2012 CNX GAS CO LLC Produced Fluid 42.70 Bbl INJECTION DISPOSAL WELL 34-013-20609
2014 CNX GAS CO LLC Produced Fluid 33.09 Bbl INJECTION DISPOSAL WELL 34-013-20609

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1822400 Primary Facility 2009-08-20 Routine/Complete Inspection No Violations Noted The silt fence located beside the access road has been overtopped with stone. The fence should be addressed to reduce the risk of off-site transportation of sediment. Well is in pre-drill phase. The operator should also place some silt fence around the top soil stockpile or temporarily seed and mulch it. The operator should continue to monito the access road and well site for erosion and sedimentation until final restoration activities are completed.
1824637 Primary Facility 2009-08-27 Drilling/Alteration No Violations Noted At the time of inspection, no E&S or IW issues at the site. Pit aligned with 20 mil plastic and no freeboard issues. Falcon drilling currently at 2850¿. Falcon set 13¿ conductor pipe at 43¿ and 7¿ at 1231¿and used 160 sks class A cement. Water noted at 395¿. TD expected at 3675¿. Well sign and E&S plan located at the entrance way of site.
1824652 Primary Facility 2009-08-19 Routine/Complete Inspection No Violations Noted Well pad was currently being constructed. Well site marked with a stake. E&S issues constructed. Pit aligned with 20 mil plastic. Called the DEP WQ personnel for assistances at the site. Water not draining from the access road. No drainage area along the road and entrance way had not collection are or drainage area. Water lying in front of access road and mud on the road coming from this well site.
1833239 Primary Facility 2009-09-30 Routine/Complete Inspection No Violations Noted At the time of inspection, the well was drilled. The brine tank was in sound condition, surrounded by a dike. Pits were in good condition with fluids removed; plans are to solidify pit upon approval. Access road was in stable condition with functioning BMP¿s (ie. filter fence). No accelerated erosion or sedimentation was observed in relation to the site or access road. Noted a 6 inch field ditch with pipe was being installed to the left hand side of the access road.
1925531 Primary Facility 2010-11-03 Site Restoration No Violations Noted At the time of inspection, well drilled and in production. Site adequately and uniformly restored with >70% vegetative growth, site had been regraded to preexisting contours and land uses. No accelerated erosion or sedimentations issues were noted. Acces road stable. Brine tank sound surrounded by dike. Observed a large pile of rock onsite in front of well, appears operator may use in roadway ditches.

For data sources see[7]

References