37-111-20193

Well Details

Well ID: 37-111-20193
Loading map...
Country: United States
State: Pennsylvania
County: Somerset
Municipality: Quemahoning Township
Operator Name: ALLIANCE PETRO CO LLC
Well Pad ID:
Farm/Lease Name: VINCENT L. CHARLTON 1
License Status: ACTIVE
Spud Date:
Permit Date: 1989-10-06
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: Yes
Latitude: 40.082669
Longitude: -79.004130

For data sources see[1][2][3]

Well History

Date Event
1989-10-06 New Permit Application
1989-11-30 Performed Spud Operation
1990-02-19 Drilling Completion
1990-02-19 Perforation
1990-05-21 NEWLY DRILLED
2002-04-17 Perforation
2016-03-03 REWORKED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
1991 CONSOL GAS CO 772823.00 365 0.00 0 0.00 0
1992 CONSOL GAS CO 229283.00 297 0.00 0 0.00 0
1993 CONSOL GAS CO 188121.00 346 0.00 0 0.00 0
1994 CONSOL GAS CO 124738.00 365 0.00 0 0.00 0
1995 CONSOL GAS CO 59563.00 365 0.00 0 0.00 0
1996 CONSOL GAS CO 36218 365 0.00 0 0.00 0
1997 CONSOL GAS CO 62042 365 0.00 0 0.00 0
1998 CONSOL GAS CO 50083 365 0.00 0 0.00 0
1999 CONSOL GAS CO 34922 365 0.00 0 0.00 0
2000 CONSOL GAS CO 13481 365 0.00 0 0.00 0
2001 CONSOL GAS CO 8901 365 0.00 0 0.00 0
2002 CONSOL GAS CO 44725 365 0.00 0 0.00 0
2003 CONSOL GAS CO 54453 365 0.00 0 0.00 0
2005 CONSOL GAS CO 41326 365 0.00 0 0.00 0
2006 CONSOL GAS CO 35386.00 365 0.00 0 0.00 0
2007 CONSOL GAS CO 27922.00 365 0.00 0 0.00 0
2008 CONSOL GAS CO 23022.11 365 0.00 0 0.00 0
2009 CONSOL GAS CO 18217.98 365 0.00 0 0.00 0
2010 CONSOL GAS CO 15,820.00 365 0.00 0 0.00 0
2011 CONSOL GAS CO 0.00 0 0.00 0 0.00 0
2012 CNX GAS CO LLC 14,445.00 366 0.00 0 0.00 0
2013 CNX GAS CO LLC 11,894.43 365 0.00 0 0.00 0
2014 CNX GAS CO LLC 9,868.30 365 0.00 0 0.00 0
2015 CNX GAS CO LLC 8,726.15 365 0.00 0 0.00 0
2016 CNX GAS CO LLC 8,187.38 366 0.00 0 0.00 0
2017 CNX GAS CO LLC 3,440.17 242 0.00 0 0.00 0
2018 CNX GAS CO LLC 7,725.41 365 0.00 0 0.00 0
2019 ALLIANCE PETRO CO LLC 4,798.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
1991 CONSOL GAS CO Brine 344.00 Bbl
1996 CONSOL GAS CO Brine 1.25 Bbl Other IXING MUD
1996 CONSOL GAS CO Brine 0.61 Bbl Injection Disposal Well 5690201
1997 CONSOL GAS CO Brine 208.00 Bbl Injection Disposal Well 111-20006
1998 CONSOL GAS CO Brine 201.24 Bbl Injection Disposal Well 5690201
1998 CONSOL GAS CO Brine 119.33 Bbl Brine or Industrial Waste Treatment Plt PA0026034
2002 CONSOL GAS CO Fracking Fluid 525.00 Bbl Brine or Industrial Waste Treatment Plt
2005 CONSOL GAS CO Brine 82.00 Bbl Other 11120260
2013 CNX GAS CO LLC Produced Fluid 24.15 Bbl Injection Disposal Well PAS2D912BSOM

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1792365 Primary Facility 2009-04-16 Drilling/Alteration No Violations Noted Based on records, well completed on 1/8/90 to a depth of 9,120 ft from grade and maintains an active permit. During inspection, well tag was present on the production equipment. The well was completed with 36" flange well assembly retrofitted to 3 gate valves and reduced to 2 inch production lines. Pressure readings on the dual pen data logging unit showed 200 psi on outside pressure and 25 psi on inside pressure. Site also contained separator, heating unit and brine tank. The valves were located in the on position. No signs of gas/fluid leakage occurring around the well and production equipment. Brine tank was approximately quarter filled. Tank shows former stain mark. At the time of the inspection, no visible signs of E&S issues. Plastic debris located near brine tank
2669345 Primary Facility 2017-12-08 Routine/Complete Inspection No Violations Noted DEP arrived onsite at 11:55 hrs CNX spence Johnson. And john Eisel from moody present. Purpose of the sampling was to collect sample from the Orkiskany formation. Mr Eisel collected a gas sample using boscom 611. Tubing showed 75% gas, casing showed 57 %, and anulus showed 60 % gas. Casing showed 900 psi, tubing at 900 psi and annulus at 260 psi. Mr Eisel used the Isotube sampling system for the casing and tubing ports. Samples collected at 12:10 hours for tubing and 12:17 hours for casing port. An additional sample was collected at annulus port using tedlar bag. Dep departed at 12:45 hours
682338 Primary Facility 1989-12-07 Routine/Complete Inspection No Violations Noted AT 1872"; E&S OK
682339 Primary Facility 1989-12-14 Routine/Complete Inspection No Violations Noted E&S, PITS OK; AT 2800'
682340 Primary Facility 1989-12-15 Drilling/Alteration No Violations Noted E&S OK
682341 Primary Facility 1989-12-21 Drilling/Alteration No Violations Noted AT 8373'; E&S OK
682342 Primary Facility 1990-01-03 Drilling/Alteration No Violations Noted E&S OK; AT 8730'
682343 Primary Facility 1990-01-04 Routine/Complete Inspection No Violations Noted E&S, PITS OK, AT 8863
682344 Primary Facility 1990-01-23 Routine/Complete Inspection No Violations Noted E&S, PITS OK
682929 Primary Facility 1990-10-25 Site Restoration No Violations Noted SITE RESTORED; TANK

For data sources see[7]