37-125-24311

Well Details

Well ID: 37-125-24311
Loading map...
Country: United States
State: Pennsylvania
County: Washington
Municipality: Robinson Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 146945
Farm/Lease Name: ROBINHILL UNIT 9H
License Status:
Spud Date:
Permit Date: 2010-10-19
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 40.457361
Longitude: -80.357111

For data sources see[1][2][3]

Well History

Date Event
2010-10-19 New Permit Application
2010-12-07 Performed Spud Operation
2010-12-21 Drilling Completion
2011-04-05 Perforation
2011-04-05 Performed Stimulation
2012-11-06 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2011-04-07 2011-04-07 5,904 3,889,569

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Iron Control Agent
Scale Inhibitor Dibromoacetonitrile 3252-43-5 5.00 0.00100000
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 30.00 0.00600000
Polyethylene glycol 25322-68-3 60.00 0.01
Distillates, petroleum, hydrotreated light 64742-47-8 30.00 0.03
Carboxymethylhydroxyporoyl guar bln 100.00 1.02
Ethylene glycol 107-21-1 30.00 0.00600000
Hydrochloric acid 7647-01-0 32.00 3.49
Used to open perfs
Biocide
Water Carrier/Base Fluid 100.00 91.40
Sand Proppant 100.00 8.59
Friction Reducer
Water Viscosifier

For data sources see[5]

Stimulation Data

Stimulation Date Phase Number Chemical Agent Volume (gal) Treating Pressure (psi) Breakdown Pressure (psi)
2011-04-05 0 0 0

For data sources see[6]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 ATLAS RESOURCES LLC 0.00 0 0.00 0 0.00 0
2011 CHEVRON APPALACHIA LLC 110,147.00 46 0.00 0 502.56 46
2012 CHEVRON APPALACHIA LLC 268,703.00 366 0.00 0 804.46 366
2013 CHEVRON APPALACHIA LLC 246,386.00 365 0.00 0 482.15 365
2014 CHEVRON APPALACHIA LLC 264,045.00 365 270.76 184 891.91 365
2015 CHEVRON APPALACHIA LLC 163,146.00 281 317.90 159 0.00 0
2016 CHEVRON APPALACHIA LLC 0.00 0 0.00 0 0.00 0
2017 CHEVRON APPALACHIA LLC 0.00 0 0.00 0 0.00 0
2019 CHEVRON APPALACHIA LLC 0.00 0 0.00 0 0.00 0

For data sources see[7]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 910.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 350.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 392.00 Bbl IDENTIFY METHOD IN COMMENTS 34-167-29359
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 75.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE
2011 CHEVRON APPALACHIA LLC Produced Fluid 10,210.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2011 CHEVRON APPALACHIA LLC Produced Fluid 3,087.00 Bbl INJECTION DISPOSAL WELL 34-121-2-3995
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 2,275.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2011 CHEVRON APPALACHIA LLC Produced Fluid 4,690.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 CHEVRON APPALACHIA LLC Produced Fluid 865.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2011 CHEVRON APPALACHIA LLC Produced Fluid 960.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001
2011 CHEVRON APPALACHIA LLC Drilling Fluid Waste 3,120.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2011 CHEVRON APPALACHIA LLC Produced Fluid 8,515.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 34-007-24355
2011 CHEVRON APPALACHIA LLC Produced Fluid 110.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2011 CHEVRON APPALACHIA LLC Fracing Fluid Waste 475.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2012 CHEVRON APPALACHIA LLC Produced Fluid 5,415.00 Bbl INJECTION DISPOSAL WELL 34-121-23995
2013 CHEVRON APPALACHIA LLC Produced Fluid 2,669.00 Bbl INJECTION DISPOSAL WELL 34-121-23995
2014 CHEVRON APPALACHIA LLC Produced Fluid 2,484.00 Bbl INJECTION DISPOSAL WELL 34-121-23995
2015 CHEVRON APPALACHIA LLC Fracturing Fluid Waste 18.94 Tons LANDFILL 100172
2015 CHEVRON APPALACHIA LLC Produced Fluid 40.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW001
2015 CHEVRON APPALACHIA LLC Produced Fluid 1,280.00 Bbl INJECTION DISPOSAL WELL 34-121-23995

For data sources see[8]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1938169 Primary Facility 2010-12-16 Drilling/Alteration No Violations Noted Whipstock 17- TD@3246, Drilling vertical ahead, returns on cement, site and location good, pit good
1943252 Primary Facility 2011-01-06 Routine/Complete Inspection No Violations Noted On January 6th, 2011 I conducted an inspection of the above site. A seam of coal had been encountered during construction of the pad and drilling pit. I met with Atlas representatives Gary Bowlen, Chad Eisenman, and Nick Staffieri on site. Approximately 300 tons of coal was encountered. Laboratory analysis showed a BTU value of 7,141 and a sulfur content of 0.60%. The coal was stock piled on site on a base of crushed limestone and surrounded by an earthen berm. A coal handling report was provided (attached). The coal will be mixed with 18 tons of limestone when replaced and encapsulated. I instructed the operator to cover the coal stock pile to avoid contact with precipitation and prevent any acidic runoff.
1944795 Primary Facility 2010-01-16 Complaint Inspection No Violations Noted
1953099 Primary Facility 2011-01-25 Routine/Complete Inspection No Violations Noted On January 25th, 2011 I conducted a follow up inspection of the above site in response to the coal encounter and inspection on January 6th, 2011. The stock pile is now covered with soil to prevent contact with precipitation. no runoff was observed from the stock pile. The rig was moving on site. Crews were laying out containment plastic under the rig and associated equipment. Drilling has not yet started. The access road was in good condition. A Site ID and E&S Plan were posted. The pits apperaered to be in good condition. No spills, leaks, or accelerated erosion were obseerved at the time of inspection.
1953668 Primary Facility 2011-01-27 Drilling/Alteration No Violations Noted Crown 8 - Rigged up , picking up directional tools to begin building curve, site and location good, pit good.
1953671 Primary Facility 2011-01-31 Drilling/Alteration No Violations Noted Crown 8 - TD@9131, 51/2 run and cemented back to surface, rigging down, site and location good, pit good.
1958462 Primary Facility 2011-02-09 Routine/Complete Inspection No Violations Noted On February 9th, 2011 I conducted a routine inspection of the above site. No runoff was observed from the coal stock pile. The rig has moved off site. The access road was in good condition. A Site ID and E&S Plan were posted. The pits apperaered to be in good condition. No spills, leaks, or accelerated erosion were observed at the time of inspection.
1958811 Primary Facility 2011-02-23 Routine/Complete Inspection No Violations Noted On February 23rd, 2011 I conducted a routine inspection of the above site. No runoff was observed from the coal stock pile. The rig has moved off site. The access road was being repaired. A Site ID and E&S Plan were posted. The pits were being expanded by raising the berm. Drill cuttings were hauled offsite. Water trucks wee bringing water in to fill the pits. No spills, leaks, or accelerated erosion were observed at the time of inspection.
1972157 Primary Facility 2011-04-13 Complaint Inspection No Violations Noted 4/12/11 ¿ Called complainant and talked over situation. Made preliminary arrangements to visit week of April 18th.
1972158 Primary Facility 2011-04-19 Complaint Inspection No Violations Noted 4/19/11 ¿ I sampled the McDonald¿s well for total coliforms and inorganic compounds. I also took one of the McDonald¿s cartridges, particulate filters for microscopic analysis. I also took photos of the well location.
1984476 Primary Facility 2011-05-27 Routine/Complete Inspection No Violations Noted On May 27th, 2011 I conducted a routine inspection of the above site. Drilling and frac were complete. Site restoration was underway. The access road was in good condition. A Site ID and E&S Plan were posted. The pits were closed and filled. Drill cuttings were hauled offsite. Efforts were being made to stabilize the fill slope and handle several spring time seeps. No spills, leaks, or accelerated erosion were observed at the time of inspection.
1986459 Primary Facility 2011-06-13 Routine/Complete Inspection No Violations Noted On June 13th, 2011 I met with Chevron representative George Bozek on above site to discuss restoration efforts. Drilling and frac were complete. Site restoration was underway. The access road was in good condition. A Site ID and E&S Plan were posted. The pits were closed and filled. Drill cuttings were hauled offsite. Efforts were being made to stabilize the fill slope and handle several spring time seeps. At this time water is being directed around the site. Final restoration plan to include additional riprap and filter sock to remain in place until permanent vegetation is established. No spills, leaks, or accelerated erosion were observed at the time of inspection.
2082333 Primary Facility 2012-07-06 Routine/Partial Inspection No Violations Noted On July 6, 2012, I stopped at Robinhill #9 to check the condensate control measures Chevron took. The well’s annulus was vented to a small tank and the pipes had matting underneath them. I found no problems.
2083647 Primary Facility 2012-07-12 Routine/Complete Inspection No Violations Noted On July 12, 2012, I stopped at Robinhill #9 with Brian Rankin & Jared Reichard of Chevron to check the restoration of Robinhill #9. This well site is currently shut down because of a small condensate release. Chevron made repairs and they were able to restrict the condensate release to the well’s cellar. Brian told me that they would be removing the rock in the cellar and talking it to a landfill.
2085178 Primary Facility 2012-07-20 Routine/Complete Inspection No Violations Noted
2163799 Primary Facility 2013-04-16 Routine/Complete Inspection No Violations Noted
2212399 Primary Facility 2013-10-02 Routine/Complete Inspection No Violations Noted
2300597 Primary Facility 2014-07-29 Site Restoration No Violations Noted
2353951 Primary Facility 2015-03-19 Routine/Complete Inspection No Violations Noted

For data sources see[9]

References