Well Details

Well ID: 34-155-24075
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date:
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 41.1957213865
Longitude: -80.7749813747

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1193037062 2014-02-11 A mechanical integrity test was performed on the well. 2040 psi. of pressure was placed on the tubing/casing annulus. The test passed without pressure loss.
-1296066111 2014-02-10 The packer installation was witnessed.
-130641778 2014-06-09 The pump was in operation at the time. There were no violations found.
-1384390051 2013-09-12 Express Energy Services installed a cellar. A corrugated culvert, 8 feet deep and 8 feet in diameter, was grouted in place, using a ready mix truck.
-1550982709 2014-06-20 A mechanical integrity test on the injection line was witnessed. A pressure of 1680 psi. was placed on the injection line. The test passed with a gain in pressure.
-1827666455 2013-09-13 I witnessed Express Energy cement the 30" conductor casing using approximately 22 yards grout.
-254408939 2013-09-18 100 feet of 20 inch diameter conductor was cemented at 95 feet below ground level, using 260 sacks of Class-A cement with 2% CaCl and 1/2 lb./sk. of cellophane flakes. Cement operation and site conditions were acceptable.
-477006335 2014-01-03 The well owner was grading and compacting soil for the surface facility construction. The drilling contractor was moving drilling equipment off the pad. All conditions were acceptable.
-741839577 2014-04-10 An attempt was made to pressure test the flow line. Equipment was not ready and the test was postponed.
1098679789 2014-01-16 A contractor was running a radioactive tracer test. All conditions were acceptable.
1379950823 2013-08-26 I was with UIC Inspector Steven Oaks, Glenda Ostman-Besama ( ODNR ) and Steve Kilper with America Water Management to location various sites to install seismic monitoring stations for there disposal well.
1379959780 2013-09-20 The operator was closing the pit. The top of cement around the conductor was approximately two feet from the cellar floor. All conditions were acceptable.
1391109016 2014-01-29 A roof was on the pump house. There was no work in progress at the time.
1395666950 2014-03-04 Northeast Region Supervisor, UIC Inspector Steve Ochs and myself performed a status check on the above location. Tank pad and tanks are under construction. We walked the location. There were no violations noted at this time.
1402332904 2014-05-14 The purpose of this inspection was to review the construction of the surface facility.

My inspection was accompanied by Tom Tomastik and Andrew Adgate. We met with Steve Kilper, with American Water Management Services. The surface facility construction was consistent with the facility plan and met all permit specifications.

2129979424 2014-01-09 The operator was moving mud and cuttings inside the drilling pits, in order to make room for cement. The cement will be used to solidify the pits. All conditions were acceptable.
217938545 2013-09-13 40 feet of 30 inch diameter casing was cemented with 8 yards of concrete. Cement operation and site conditions were acceptable.