If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 37-051-00118 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.91975,"lon":-79.849944,"icon":""}]} |
County: Fayette | |
Municipality: German Township | |
Operator Name: THE PRODUCTION CO LLC | |
Well Pad ID: | |
Farm/Lease Name: | |
First Permit Date: 1856-08-15 | |
Last Permit Date: 1856-08-15 | |
Spud Date: 1800-01-01 | |
Unconventional: No | |
Horizontal: No | |
Well Status: ACTIVE | |
Violations: 6 | |
Latitude: 39.91975 | |
Longitude: -79.849944 |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|---|---|---|---|---|---|
1991-0 | 2325.0 | 364.0 | 0.0 | 0.0 | 0.0 | 0.0 |
1996-0 | 1921.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
1996-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
1997-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
1998-0 | 30.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
1999-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2003-0 | 2648.87 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2004-0 | 3315.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2005-0 | 1972.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2007-0 | 1043.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2008-0 | 550.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2009-0 | 182.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2010-0 | 0.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2011-0 | 12.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2012-0 | 12.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2013-0 | 12.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2014-0 | 12.0 | 365.0 | 0.0 | 0.0 | 0.0 | 0.0 |
For data sources see[1]
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|
For data sources see[2]
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID | VIOLATION CODE | VIOLATION_COMMENT |
---|---|---|---|---|---|---|
1852514 | 2009-12-16 | Violation(s) Noted | 578592 | 105GEN - Encroachment-General | No E&S control measures were in place where the pipeline crossed the stream. | |
1852514 | 2009-12-16 | Violation(s) Noted | 578592 | 105GEN - Encroachment-General | No E&S control measures were in place where the pipeline crossed the stream. | |
1852514 | 2009-12-16 | Violation(s) Noted | 578593 | 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) | No stabilization measures were taken on the cleared pipeline area to prevent erosion. There were not any erosion and sedimentation (﾿E&S﾿) control measures where the new pipeline crossed a creek. | |
1852514 | 2009-12-16 | Violation(s) Noted | 578593 | 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) | No stabilization measures were taken on the cleared pipeline area to prevent erosion. There were not any erosion and sedimentation (﾿E&S﾿) control measures where the new pipeline crossed a creek. | |
1852514 | 2009-12-16 | Violation(s) Noted | 578594 | 102.4NOPLAN - No E&S plan developed, plan not on site | No E&S control plan for the project was available on the work site. | |
1852514 | 2009-12-16 | Violation(s) Noted | 578594 | 102.4NOPLAN - No E&S plan developed, plan not on site | No E&S control plan for the project was available on the work site. | |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580130 | 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) | Accelerated erosion and sedimentation occurred and was transported off the site. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580130 | 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) | Accelerated erosion and sedimentation occurred and was transported off the site. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580130 | 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) | Accelerated erosion and sedimentation occurred and was transported off the site. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580131 | 102.4INADPLN - E&S Plan not adequate | Best management control measures were not adequate for the well site. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580131 | 102.4INADPLN - E&S Plan not adequate | Best management control measures were not adequate for the well site. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580131 | 102.4INADPLN - E&S Plan not adequate | Best management control measures were not adequate for the well site. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580132 | 102.4NOPLAN - No E&S plan developed, plan not on site | No E&S control plan for the project was available on the work site for review. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580132 | 102.4NOPLAN - No E&S plan developed, plan not on site | No E&S control plan for the project was available on the work site for review. |
1858651 | 2010-01-20 | Violation(s) Noted | On January 20, 2010, I conducted a routine inspection at the site to see if E&S control measures were installed. The E&S BMPs that were installed entailed staked hay bales that were not entrenched into the ground as called for in the DEP﾿s Erosion and Sediment Pollution Control Program Manual. As a result, the run off that occurred from the previous rain/snow melt event undermined the hay bales. It was evident that a large amount of sediment left the site. The road side trenches were filled with mud and the farm fields across the streets had mud conveyed across them via the culverts under Ralf-New Salem Road and Shimpko Hollow Road. It was apparent that some of the sediment transported off site at the Shimpko Hollow Road pipeline crossing went into an unnamed tributary to Dunlap Creek. An E&S control plan for the pipeline project was not available on site to review. | 580132 | 102.4NOPLAN - No E&S plan developed, plan not on site | No E&S control plan for the project was available on the work site for review. |
1864936 | 2010-01-20 | No Violations Noted | Inspection related to the gas line replacement that this well is attached to. | |||
1864965 | 2010-02-03 | No Violations Noted | Inspection related to the gas line replacement that this well is attached to. |
For data sources see[3]