X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-021-21078

Well Details

Well ID: 37-021-21078
Loading map...
County: Cambria
Municipality: Chest Township
Operator Name: DORSO LP
Well Pad ID:
Farm/Lease Name: MASCI UNIT 2
First Permit Date: 2008-01-22
Last Permit Date: 2008-01-22
Spud Date: 2008-08-05
Unconventional: No
Horizontal: No
Well Status: ACTIVE
Violations: 0
Latitude: 40.694792
Longitude: -78.633641

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2008-0 2136.0 93.0 0.0 0.0 0.0 0.0
2009-0 6420.0 365.0 0.0 0.0 0.0 0.0
2010-0 4746.0 365.0 0.0 0.0 0.0 0.0
2011-0 3476.0 365.0 0.0 0.0 0.0 0.0
2012-0 2833.0 365.0 0.0 0.0 0.0 0.0
2013-0 2326.0 365.0 0.0 0.0 0.0 0.0
2014-0 1857.0 365.0 0.0 0.0 0.0 0.0

For data sources see[1]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2009-0 BRINE 65.0 Bbl BRINE OR INDUSTRIAL WASTE TREATMENT PLT PA0101508 PA BRINE PA
2011-0 PRODUCED FLUID 40.0 Bbl ROAD SPREADING CLEARFIELD COUNTY ROADSPREADING - CHEST TOWNSHIP PA
2012-0 PRODUCED FLUID 80.0 Bbl ROAD SPREADING CLEARFIELD COUNTY ROADSPREADING - CHEST TOWNSHIP PA

For data sources see[2]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
1817407 2009-07-31 No Violations Noted According to records, well completed on 8/8/08 to a depth of 3,627 ft and WRAC submitted on 10/6/08. Active permit since 1/22/08. Well head completed with 7﾿ pipe reduced to 4﾿ and reduced to 2﾿ production line with 3 shut off valves. Production equipment consisted of heater, separator, data logger and 100 bbl tank. Brine tank was nearly full. Data logger showed pressures of 180 psi/75 psi. No E&S issues and no IW issues during inspection surrounding the production well. Wellhead was painted recently. Called Dorso and talked to Dave Scott. Well tag probably covered in paint and requested that a new tag added to well head. Brine tank on schedule for pump out next week
1888990 2010-06-03 No Violations Noted At the time of inspection, well was drilled and in production. Well tag wasdifficult to read as it was painted over, but data logger was clearly marked. Although it is recommended that operator clearly identify the well with API number. Brine tank appeared stable. Attempts to restore the site were apparent, but less than 70% vegetative growth was observed, particularly in the area were it appears a pit may have been previously located. It is recommended that the operator promptly reseed the site in order to reach optimal, permanent restoration. Area surrounding well head was mostly rocked. No accelerated erosion or sedimentation issues were noted in relation to access road or well site. Access road was stable. Follow up inspection will be done to ensure proper and uniform permanent stabilzation/restoration is achieved.

For data sources see[3]

References