37-003-22168

Well Details

Well ID: 37-003-22168
Loading map...
County: Allegheny
Municipality: Kilbuck Township
Operator Name: AMER NATURAL RESOURCES LLC
Well Pad ID:
Farm/Lease Name: CHARLES LENZNER UNIT 2
First Permit Date: 2011-03-14
Last Permit Date: 2011-03-14
Spud Date: 2011-05-05
Unconventional: No
Configuration: Vertical
Well Status: ACTIVE
Violations: 0
Latitude: 40.534375
Longitude: -80.119433

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2011-0 0.0 0.0 0.0 0.0 0.0 0.0
2012-0 0.0 0.0 0.0 0.0 0.0 0.0
2013-0 0.0 0.0 0.0 0.0 0.0 0.0
2014-0 0.0 0.0 0.0 0.0 0.0 0.0
2013-0 0.0 0.0 0.0 0.0 0.0 0.0
2011-0 0.0 0.0 0.0 0.0 0.0 0.0
2012-0 0.0 0.0 0.0 0.0 0.0 0.0
2014-0 0.0 0.0 0.0 0.0 0.0 0.0

For data sources see[1]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION COMMENT
1976559 2011-04-18 No Violations Noted EXCAVATOR DIGGING PIT.

E&S, OK AND ACCESS IS STONED.

1979464 2011-05-10 No Violations Noted RIG DOWN.

SIT, PIT, E&S, AND ACCESS, OK.

1979466 2011-05-09 No Violations Noted USE RIG #7 RAN 9 5/8" CASING IN HOLE. CASING WILL BE CEMENTED LATER IN THE DAY.
1979496 2011-05-09 No Violations Noted DRILLING IS COMPLETE. THE SITE IS CLEAN AND DOZED. THE PIT LEVEL IS OK.
1983161 2011-05-12 No Violations Noted DRILLING COMPLETE. EQUIPTMENT GONE.

SITE, PIT, E&S, AND ACCESS, OK.

1983732 2011-04-20 No Violations Noted On April 20th, 2011 I conducted a routine inspection of the above site. Drilling has not yet started. A site ID sign and E&S plan were posted at the site. The access road could use some additional rock. All E&S controls were in place and constructed according to the plan at site. Pit was constructed. No accelerated erosion was observed at the time of inspection. The operator should continue to inspect the E&S controls until the site is restored and 70% vegetative cover is achieved.
1983807 2011-05-04 No Violations Noted On May 4th, 2011 I conducted a routine inspection of the above site. Drilling has not yet started. A site ID sign and E&S plan were posted at the site. The access road was being rocked. All E&S controls were in place and constructed according to the plan at site. Pit was constructed. No accelerated erosion was observed at the time of inspection. The operator should continue to inspect the E&S controls until the site is restored and 70% vegetative cover is achieved.
1983812 2011-05-11 No Violations Noted On May 11th, 2011 I conducted a routine inspection of the above site. Drilling has started. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site. Pit appeared to be in good condition. The operator should continue to inspect the E&S controls until the site is restored and 70% vegetative cover is achieved.
2018481 2011-10-05 No Violations Noted THE PIT IS OPEN. WELL WAS NEVER COMPLETED. NO ACTIVITY SINCE MAY 2011.
2027979 2011-12-08 No Violations Noted E&S plan on site (originally only ofr one well but now includes Lenzer #3 & #4 also).

The access road is good.

The drill pit was good and had adequate freeboard.

Working on the silt fence at inspection.

Additional stabilization on banks.

Weekly inspections and after percipitation events are required.

2051738 2012-03-20 No Violations Noted On December 5, 2012, the Department received a request for a six-month extension for the reclamation of American Natural Resourcesï¾’ (ANR) Charles Lenzer Unit #2. The well reached total depth on 5/11/11 and restoration should have been done by 2/11/12.

However, ANR was unable to complete the restoration on time because of the extremely wet summer and fall (they included documentation). I granted the extension and the new restoration date will be 8/11/12.

2065239 2012-04-03 No Violations Noted PUMP JACK SET AND LOOKS TO BE IN USE. TANKS ARE SET. SITE RESTORED.
2086051 2012-07-24 No Violations Noted On March 15, 2012, the Department granted American Natural Resources (ANR) a six-month extension on the reclamation of their Charles Lenzner #4 site. The new reclamation date is August 5, 2012.
On July 24, 2012, WQS John Ley and I stopped at ANRï¾’s\ï¾’, Charles Lenzner #4 site to check the restoration progress.  The site is in fair shape.  Overall the it is vegetated but the silt fence is still up.  We also did not see signs on the well itself.

Iï¾’m recording no violations at this time, but the site could use tending.

2100596 2012-09-06 No Violations Noted On September 6, 2012, WQS John Ley and I stopped at ANRï¾’s\ï¾’, Charles Lenzner #2 site to check the restoration progress. The site is in fair shape. Overall the it is vegetated but the silt fence is still up. We also did not see signs on the well itself.

Site restoration requires 70% perennial vegetation and the fence removed.

2247336 2014-01-22 No Violations Noted EXTREAM COLD PREVENTED EQUIPTMENT FROM STARTING. PLUGGING IS DELAYED.
2247425 2014-01-21 No Violations Noted OIL AND BRINE TANKS ARE STILL ON THE PAD. FRONTIER ENERGY SERVICE RIG IS SET UP TO PLUG THIS WELL.
2251811 2014-01-24 No Violations Noted APPALACHIAN WELL SERVICES HAS SET BOTTOM PLUG FROM TD TO 1,637'. HIGHER PLUGS WILL BE SET LATER.
2251812 2014-01-28 No Violations Noted RIG IS DOWN. PLUGGING IS NOT COMPLETE. TANKS ARE ON THE PAD.
2251849 2014-02-12 No Violations Noted WELL IS PLUGGED. 7" BOND LOG WAS POSITIVE. PROPER PLUGS WERE SET. PEA GRAVEL WILL BE ADDED.
2251853 2014-03-04 No Violations Noted WELL IS PLUGGED. VENTED MARKER WITH API NUMBER IS INSTALLED. STORAGE TANKS ARE GONE.

For data sources see[2]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2012-0 Drilling Fluid Waste (in Barrels) 568.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 FLUID RECOVERY SERVICE JOSEPHINE FACILITY JOSEPHINE PA
2011-0 Drilling Fluid Waste (in Barrels) 420.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 FLUID RECOVERY SERVICE JOSEPHINE FACILITY JOSEPHINE PA

For data sources see[3]

References