37-063-36909

Well Details

Well ID: 37-063-36909
Loading map...
Operator Name: XTO ENERGY INC
First Permit Date: 2010-08-17
Last Permit Date: 2010-08-17
Spud Date: 2010-10-15
Unconventional: No
Horizontal: No
Violations: None
Latitude: 40.857125
Longitude: -79.160333

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-0 2796.0 93.0 0.0 0.0 0.0 0.0
2012-0 0.0 0.0 0.0 0.0 0.0 0.0
2011-0 0.0 0.0 0.0 0.0 0.0 0.0
2010-0 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1904341 2010-08-10 No Violations Noted Proposed site staked. Site not constructed.

Request for waiver of distance requirement from wetlands associated with Little Mahoning Creek. Revisions to E&S plan requested and received. Spoke to operator representative Tom Baun and consultant Jesse Hickman about these revisions. Revised plan should protect wetlands from adverse impact during site/well development if properly implemented and maintained.

1925213 2010-10-27 No Violations Noted Site id sign in place. E&S plan on site. Well not equipped for production (not yet fraced). Spudded on 10/15/10.

Waiver of distance requirement from wetlands associated with Little Mahoning Creek approved on 8/10/10. Access road is stable. Access road entrance is adequately rocked. Areas of disturbance along roadway have been seeded/mulched. Culverts rip-rapped. No signs of accelerated erosion on access road. BMP's are in place in accordance with E&S plan on road and site.

  • Rain/water run-off has nearly washed out underneath the silt fence/hay bales in one small area on the down-slope side of the site.
   Additional measures need to be taken to ensure E&S problems are avoided.  Spoke to operator representative Tom Baun about this concern, who indicated the work would be done immediately and I would be contacted upon completion.

Drill pit is properly lined, appears sound, and has adequate freeboard. No violations found.


1925241 2010-11-02 No Violations Noted Inspection conducted with oil & gas inspector Rick Hoover in response to compliance assistance inspection of 10/27/10.

Site id sign in place. E&S plan on site. Spudded on 10/15/10. Access road is stable. Access road entrance is adequately rocked. Areas of disturbance along roadway have been seeded/mulched. Culverts rip-rapped. No signs of accelerated erosion on access road. BMP's are in place in accordance with E&S plan on road and site. Drill pit is properly lined, appears sound, and has adequate freeboard. Lined frac pit appeared sound and had adequate freeboard. Additional BMP's have been installed below the site to ensure any E&S issues are avoided. Site is in compliance.

1926049 2010-11-02 No Violations Noted
2121862 2012-12-07 No Violations Noted
2121913 2012-12-07 No Violations Noted