Well Details

Well ID: 37-005-31244
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: East Franklin Township
Operator Name: SNYDER BROS INC
Well Pad ID: 152962
Farm/Lease Name: FURNACE RUN
License Status: Active
Spud Date: 2016-03-13
Permit Date: 2015-09-02
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.851283
Longitude: -79.544428

For data sources see[1][2][3]

Well History

Date Event
2015-09-02 New Permit Application
2016-01-20 Performed Spud Operation
2016-01-21 Drilling Completion
2016-02-25 Drilling Completion
2019-06-11 Newly Drilled
2019-06-11 Skidded Rig

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2016-06-13 2016-07-03 6,509 13,058,700 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 FR-16FW Keane Friction Reducer Ammonium chloride 12125-02-9 1.5 0.000458097 560.661
Alcohols, C12-16, ethoxylated 68551-12-2 1 0.000305398 373.774
distillates (petroleum), hydrotreated light 64742-47-8 17.5 0.00534447 6541.05
Oleic Acid Diethanolamide 93-83-4 1.5 0.000458097 560.661
Water 7732-18-5 55 0.0167969 20557.6
AI-600P Weatherford Corrosion Inhibitor 2-Butoxyethanol 111-76-2 3 0.00004808 58.842
Ethylene Glycol 107-21-1 30 0.00048078 588.423
1-Decanol 112-30-1 3 0.00004808 58.842
Alkyl Pyridine 68391-11-7 0.6 0.00000881 10.788
Dimethylformamide 68-12-2 15 0.00024039 294.211
1-Octanol 111-87-5 3 0.00004808 58.842
Nonyl Phenol Ethoxylate, Branched 127087-87-0 10 0.00016026 196.141
Triethyl Phosphate 78-40-0 1.8 0.00002805 34.325
Methanol 67-56-1 1.8 0.00002805 34.325
Cinnamaldehyde 104-55-2 10 0.00016026 196.141
Pyridine, alkyl derives, quaternized with Benzyl chloride 68909-18-2 10 0.00016026 196.141
Hydrochloric Acid (15%) FSTI Acidizing Hydrochloric Acid 7647-01-0 15 0.099013 121181
Water 7732-18-5 75 0.495065 605905
Water Snyder Brothers Carrier/Base Fluid Water 7732-18-5 100 89.0398 108,975,000.0
FFR730 NALCO Friction Reducer Oxyalkylated alcohol Proprietary 3 0.00117893 1442.88
FEAC-30 Keane Iron Control Acetic Acid 64-19-7 45 0.00100895 1234.84
Citric Acid 77-92-9 27.5 0.000616578 754.624
Sand (Proppant) Keane Proppant Crystallilne silica 14808-60-7 100 10.2001 12,483,800.0
EC6330a NALCO Scale Inhibitor Ethylene Glycol 107-21-1 3 0.000281319 344.304
Sodium Phosphate, Tribasic 7601-54-9 3 0.000281319 344.304
K-139 NALCO Biocide Ethanol 64-17-5 3 0.000507977 621.708
Quaternary ammonium compounds,
benzyl-C12-16-alkyldimethyl, chlorides
68424-85-1 7.5 0.00126994 1554.27
Glutaraldehyde 111-30-8 3 0.000507977 621.708

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2016 SNYDER BROS INC 352,474.00 67 0.00 0 0.00 0
2017 SNYDER BROS INC 1,078,555.00 304 0.00 0 0.00 0
2018 SNYDER BROS INC 728,546.00 280 0.00 0 0.00 0
2019 SNYDER BROS INC 692,421.00 351 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2016 SNYDER BROS INC Drill Cuttings 1,163.42 Tons LANDFILL 100585
2016 SNYDER BROS INC Fracturing Fluid Waste 35.85 Bbl INJECTION DISPOSAL WELL 34-155-24079
2016 SNYDER BROS INC Produced Fluid 4,140.42 Bbl REUSE OTHER THAN ROAD SPREADING
2016 SNYDER BROS INC Fracturing Fluid Waste 5,582.01 Bbl REUSE OTHER THAN ROAD SPREADING
2016 SNYDER BROS INC Produced Fluid 79.38 Bbl INJECTION DISPOSAL WELL 34-155-24063
2016 SNYDER BROS INC Fracturing Fluid Waste 3,880.78 Bbl INJECTION DISPOSAL WELL 34-155-23196
2016 SNYDER BROS INC Drilling Fluid Waste 230.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW011
2016 SNYDER BROS INC Produced Fluid 145.95 Bbl INJECTION DISPOSAL WELL 34-133-24462
2016 SNYDER BROS INC Produced Fluid 2,316.53 Bbl INJECTION DISPOSAL WELL 34-155-24079
2016 SNYDER BROS INC Produced Fluid 5,979.15 Bbl INJECTION DISPOSAL WELL 34-099-23158
2016 SNYDER BROS INC Fracturing Fluid Waste 54.44 Tons LANDFILL 100585
2016 SNYDER BROS INC Produced Fluid 238.13 Bbl INJECTION DISPOSAL WELL 34-155-23196
2016 SNYDER BROS INC Synthetic Liner Materials 7.02 Tons LANDFILL 100585
2016 SNYDER BROS INC Fracturing Fluid Waste 2,776.67 Bbl INJECTION DISPOSAL WELL 34-099-23158
2017 SNYDER BROS INC Produced Fluid 6,990.29 Bbl REUSE (AT WELL PAD)
2017 SNYDER BROS INC Produced Fluid 70.40 Bbl INJECTION DISPOSAL WELL 34-155-24063
2017 SNYDER BROS INC 12,509.34 Bbl INJECTION DISPOSAL WELL 34-155-24079
2017 SNYDER BROS INC 33.29 Bbl INJECTION DISPOSAL WELL 34-099-23158
2017 SNYDER BROS INC 6,375.78 Bbl REUSE (AT WELL PAD)
2017 SNYDER BROS INC 13.67 Tons LANDFILL 100585
2017 SNYDER BROS INC Produced Fluid 933.29 Bbl INJECTION DISPOSAL WELL 34-099-23158
2017 SNYDER BROS INC Waste Water Treatment Sludge 13.67 Tons LANDFILL 100585
2017 SNYDER BROS INC Produced Fluid 13,678.48 Bbl INJECTION DISPOSAL WELL 34-155-24079
2017 SNYDER BROS INC Synthetic Liner Materials 4.08 Tons LANDFILL 100585
2018 SNYDER BROS INC Produced Fluid 1,352.00 Bbl REUSE (AT WELL PAD)
2018 SNYDER BROS INC Produced Fluid 20,464.50 Bbl INJECTION DISPOSAL WELL 34-099-23158
2018 SNYDER BROS INC Produced Fluid 486.30 Bbl INJECTION DISPOSAL WELL 34-155-24079
2019 SNYDER BROS INC Produced Fluid 11,523.00 Bbl INJECTION DISPOSAL WELL 34-099-23158
2019 SNYDER BROS INC Other Oil & Gas Wastes 19.20 Bbl INJECTION DISPOSAL WELL 34-099-23158
2019 SNYDER BROS INC Produced Fluid 703.70 Bbl INJECTION DISPOSAL WELL 34-099-23171
2019 SNYDER BROS INC Produced Fluid 2,439.60 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2441909 Primary Facility 2016-01-20 Routine/Complete Inspection No Violations Noted Site construction was still ongoing, perimeter E&S controls had been installed as outlined in the approved ESCGP. Conductor rig is to scheduled to be onsite the afternoon of 01/20/16. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2443456 Primary Facility 2016-01-26 Drilling/Alteration No Violations Noted Well tagged-basement set-well spudded-drilled to 40' and 40' of 26" conductor pipe set and grouted. Well covered with steel plate.
2446474 Primary Facility 2016-02-03 Routine/Complete Inspection No Violations Noted Drilling had commenced but was not ongoing at the time of the inspection. Top-hole drill rig was enroute to the well-site. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2453078 Primary Facility 2016-02-25 Drilling/Alteration No Violations Noted Cleaned hole to 130'. Cemented with 228 sks unitropic. No returns. Shut down-plan is to plug and skid to next well as per Oil & Gas team guidance according to regulations.
2466904 Primary Facility 2016-03-21 Drilling/Alteration No Violations Noted Rig ran-cemented 40'of30"-113'of26" and 994'of13.375"pipe. Cement jobs ok. Log book ok. This is Furnace Run 31244 2HA skid well.
2466970 Primary Facility 2016-03-22 Routine/Complete Inspection No Violations Noted Drill rig located onsite and drilling was ongoing at the time of the inspection. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2468857 Primary Facility 2016-03-29 Drilling/Alteration No Violations Noted Rig TD'd top hole @ 5947' on 3/26/2016 and skidded to next hole. On site log book up to date and all looked ok.
2492304 Primary Facility 2016-06-13 Drilling/Alteration No Violations Noted Keane had just moved in - hooked up equipment on this well and was pressure testing in prep for frac. Equipment looked ok.
2492735 Primary Facility 2016-06-14 Drilling/Alteration No Violations Noted Keane started frac @ 6:00 this am and had completed the first stage on this 2H well at the time of this inspection. Equipment-grounding-all containments looked good. Noise reduction manifold was in place and frac job was relatively quiet.
2494675 Primary Facility 2016-06-17 Drilling/Alteration No Violations Noted Keane was just starting the stage 5 frac on this well of the 166 stage zipper frac planned for the 4 wells on this pad. All on site equipment and the daily activity electronic log looked good.
2496648 Primary Facility 2016-06-23 Drilling/Alteration No Violations Noted Keane had just fracked stage 70 of the planned 166 stage zipper frac on the 4 wells on this site. All on site equipment-containment looked ok.
2500115 Primary Facility 2016-07-06 Drilling/Alteration No Violations Noted Last frac plug set in curve. Snubbing unit due in shortly. Frac stack being removed from well @ time of inspection. All equipment on site looked ok.
2501621 Primary Facility 2016-07-15 Drilling/Alteration No Violations Noted Snubbing unit crew drilled out plugs and was tripping out of hole getting ready to hook up to run production tubing. All equipment on site looked ok.
2505525 Primary Facility 2016-07-28 Routine/Complete Inspection No Violations Noted Drilling and well stimulation activities appeared to have been completed. Work was underway to equip the wells for production. Site work was underway related to the PCSM for the associated ESCGP. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2528545 Primary Facility 2016-10-17 Routine/Complete Inspection No Violations Noted Well tagged-shut in. Annulus was open. Well head casing-production set equipment-tank battery/containment dike looked ok.
2537955 Primary Facility 2016-11-18 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2546437 Primary Facility 2016-12-21 Site Restoration No Violations Noted Well appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All disturbed areas had been effectively stabilized with vegetation achieving 70% uniform coverage all PCSM controls had been implemented as outlined in the site restoration plans.
2563713 Primary Facility 2017-02-21 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production, brine tank located onsite. Brine tank appeared to be in sound condition. No accelerated erosion or sedimentation observed in relation to the site or access road. AST that had been onsite for flowback containment had been deconstructed and removed. There was no staining observed indicative that any spills or leaks occurred.
2643085 Primary Facility 2017-10-03 Routine/Complete Inspection No Violations Noted All site and access road erosion controls had been implemented and maintained as outlined in the E&S plan included within the ESCGP. There was no observed accelerated erosion or sedimentation in relation to the site or access. Brine tanks located onsite within secondary containment. Both the tanks and secondary containment appeared to be in sound condition.
2672740 Primary Facility 2017-12-19 Routine/Complete Inspection No Violations Noted At time of inspection, wells 2H-A, 3H-A, 4H, 1H all drilled and appear equipped for production.
2705288 Primary Facility 2018-03-14 Routine/Complete Inspection No Violations Noted This well is tagged and in production. The well head casing, piping, production set equipment, tank battery and dike containment look excellent.
2771542 Primary Facility 2018-09-06 Routine/Complete Inspection No Violations Noted Well appears equipped for production. Well head surrounded by cement barriers. Four brine tanks on site.
2798015 Primary Facility 2018-11-05 Routine/Complete Inspection No Violations Noted This well is tagged and in production. The annulus is open. The well head casing, piping, production set equipment, dike containment and tank battery look ok.
2820998 Primary Facility 2019-01-02 Routine/Complete Inspection No Violations Noted This well is tagged and in production with the annulus open. The well head casing, piping, production set equipment, containment dike and tank battery look ok.

For data sources see[8]