37-005-31293

Well Details

Well ID: 37-005-31293
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: West Franklin Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 152144
Farm/Lease Name: PAD W9 PER-W09-2H
License Status: Active
Spud Date: 07/05/2017
Permit Date: 6/14/2017
Unconventional Well: Y
Configuration: Horizontal Well
Latitude: 40.830910
Longitude: -79.672353

For data sources see[1][2][3]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2018 PENNENERGY RESOURCES LLC 468,630.00 157 0.00 0 0.00 0
2019 PENNENERGY RESOURCES LLC 191,537.00 90 0.00 0 0.00 0

For data sources see[4]

Waste Data

Period Waste Type Quantity Disposal Method Waste Facility ID
2017-08 Drill Cuttings (in Tons) RWC 810 308.83 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017-09 Produced Fluid (in Barrels) RWC 802 806.72 Bbl REUSE (AT WELL PAD)
2017-11 Drill Cuttings (in Tons) RWC 810 22.42 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017-11 Drilling Fluid Waste (in Barrels) RWC 803 130.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2017-11 Drilling Fluid Waste (in Barrels) RWC 803 130.00 Bbl INJECTION DISPOSAL WELL 34-155-23223
2017-12 Drill Cuttings (in Tons) RWC 810 505.56 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017-12 Drilling Fluid Waste (in Barrels) RWC 803 740.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2017-12 Drilling Fluid Waste (in Barrels) RWC 803 560.00 Bbl INJECTION DISPOSAL WELL 34-155-23223
2018-02 Drilling Fluid Waste (in Barrels) RWC 803 55.83 Bbl REUSE (AT WELL PAD)
2018-04 Servicing Fluid (in Tons) RWC 808 3.79 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-04 Waste Water Treatment Sludge (in Tons) RWC 804 2.25 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018-05 Produced Fluid (in Barrels) RWC 802 9.88 Bbl REUSE (AT WELL PAD)
2018-05 Produced Fluid (in Tons) RWC 802 9.55 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-06 Produced Fluid (in Barrels) RWC 802 43.83 Bbl REUSE (AT WELL PAD)
2018-06 Produced Fluid (in Tons) RWC 802 15.26 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-07 Produced Fluid (in Barrels) RWC 802 2,619.91 Bbl REUSE (AT WELL PAD)
2018-07 Produced Fluid (in Tons) RWC 802 9.08 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018-07 Produced Fluid (in Tons) RWC 802 3.50 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-08 Produced Fluid (in Barrels) RWC 802 10.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2018-08 Produced Fluid (in Barrels) RWC 802 18.33 Bbl INJECTION DISPOSAL WELL 34-155-23223
2018-08 Produced Fluid (in Barrels) RWC 802 110.40 Bbl REUSE (AT WELL PAD)
2018-08 Produced Fluid (in Tons) RWC 802 4.48 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-09 Filter Socks (in Tons) RWC 812 0.50 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018-09 Produced Fluid (in Barrels) RWC 802 210.00 Bbl REUSE (AT WELL PAD)
2018-09 Produced Fluid (in Tons) RWC 802 2.12 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018-09 Produced Fluid (in Tons) RWC 802 0.42 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-09 Servicing Fluid (in Tons) RWC 808 16.52 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-10 Produced Fluid (in Barrels) RWC 802 48.84 Bbl REUSE (AT WELL PAD)
2018-11 Produced Fluid (in Barrels) RWC 802 135.63 Bbl REUSE (AT WELL PAD)
2018-12 Produced Fluid (in Barrels) RWC 802 1,246.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2018-12 Produced Fluid (in Barrels) RWC 802 721.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2018-12 Produced Fluid (in Barrels) RWC 802 20.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2018-12 Produced Fluid (in Barrels) RWC 802 20.00 Bbl INJECTION DISPOSAL WELL 34-155-23223
2018-12 Produced Fluid (in Barrels) RWC 802 18.33 Bbl INJECTION DISPOSAL WELL 34-155-23795
2018-12 Produced Fluid (in Barrels) RWC 802 100.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2018-12 Produced Fluid (in Barrels) RWC 802 17.47 Bbl REUSE (AT WELL PAD)
2018-12 Synthetic Liner Materials (in Tons) RWC 806 4.28 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018-12 Waste Water Treatment Sludge (in Tons) RWC 804 4.48 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019-01 Produced Fluid (in Barrels) RWC 802 223.67 Bbl INJECTION DISPOSAL WELL 34-155-21893
2019-01 Produced Fluid (in Barrels) RWC 802 129.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2019-01 Produced Fluid (in Barrels) RWC 802 376.43 Bbl INJECTION DISPOSAL WELL 34-155-23795
2019-01 Produced Fluid (in Barrels) RWC 802 136.78 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019-01 Produced Fluid (in Barrels) RWC 802 1,531.17 Bbl REUSE (AT WELL PAD)
2019-02 Produced Fluid (in Barrels) RWC 802 650.39 Bbl REUSE (AT WELL PAD)
2019-03 Produced Fluid (in Barrels) RWC 802 1,870.57 Bbl REUSE (AT WELL PAD)

For data sources see[5]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2612498 Primary Facility 2017-07-06 Drilling/Alteration No Violations Noted Well sign present-spudded 7-5-2017 with 40' of 16" casing in a 8' round - 8' deep cellar.
2619275 Primary Facility 2017-07-26 Routine/Complete Inspection No Violations Noted Drilling had commenced but was not ongoing at the time of the inspection. Well development impoundment construction was in its final stages with final grading and mulching for temporary stabilization being completed. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All erosion controls had been implemented and maintained as outlined in the E&S plan contained within the ESCGP.
2630669 Primary Facility 2017-08-28 Drilling/Alteration No Violations Noted The Rig had just run and cemented 2,814' of 8 5/8" casing-cemented with 720 sks cement and got 20 bbl cement return. Daily drilling info and all equipment on site looked ok.
2637399 Primary Facility 2017-09-15 Routine/Complete Inspection No Violations Noted Drilling was ongoing for 005-31296 at the time of the inspection. Secondary containment, and tertiary containment for number areas on the well pad was implemented as outlined. Well development impoundment construction had been completed and the impoundment was not lined and not in use. All access road and site erosion controls had been implemented as outlined in the E&S plan contained within the ESCGP. All erosion controls appeared to be maintained and functioning properly. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2661676 Primary Facility 2017-11-16 Routine/Complete Inspection No Violations Noted At time of inspection, 3H actively being drilled. 1H, 2H, 4H, 5H, 6H all spudded, not yet completed.

Operator representatives John Rice and Bobby Harrage on-site.

2665168 Primary Facility 2017-11-29 Drilling/Alteration No Violations Noted The rig had just skidded to this hole and was in the process of setting up to commence drilling at the time of this inspection. The daily drilling log and all equipment on site looked ok.
2670284 Primary Facility 2017-12-06 Routine/Complete Inspection No Violations Noted At time of inspection, drilling rig on 2H. 1H, 3H, 4H, 5H, 6H have all been spudded.

Operator representative Bobby Harrage on-site.

2678887 Primary Facility 2017-12-27 Routine/Complete Inspection No Violations Noted At time of inspection, drilling rig on 4H. Wells 1H, 2H, and 3H have been completed. Wells 5H and 6H have been spudded, not yet completed.

Operator representatives Heath Cunningham and Todd White on-site.

2691333 Primary Facility 2018-01-25 Routine/Partial Inspection No Violations Noted At time of inspection, well 2H drilled to total depth. Wells 1H, 3H, 4H, 5H, and 6H also drilled to total depth. These wells have not yet been frac'd.

The rig is in the process of exiting the site. Because of the large volume of vehicle traffic, the Department did not inspect the whole site due to safety concerns.

Operator representative James on-site.

2695906 Primary Facility 2018-02-15 Routine/Complete Inspection No Violations Noted At time of inspection, well 2H drilled to total depth. Wells 1H, 3H, 4H, 5H, and 6H also drilled to total depth. These wells have not yet been frac'd.

No rig on-site during this inspection.

2709358 Primary Facility 2018-03-15 Routine/Complete Inspection No Violations Noted At time of inspection, well 2H drilled, not yet frac'd. Frac'g not yet completed for wells 1H, 4H, 5H, and 6H. Frac'g operations ongoing for well 4H during this inspection. Well 3H frac'd.
2724503 Primary Facility 2018-04-30 Drilling/Alteration No Violations Noted Operator had just finished fracking stage 2 of the planned 27 stages at the time of this inspection. All paperwork and equipment on site looked ok. A Scada pressure monitoring unit will be set up on the offset Snyder wells in order to monitor these wells for potential communication later on in the frac stages. All equipment on site looked ok.
2726891 Primary Facility 2018-05-07 Drilling/Alteration No Violations Noted Operator had just finished fracking stage 23 of the planned 27 stages at the time of this inspection. All paperwork and equipment on site looked ok. A Scada pressure monitoring unit will be set up on the offset Snyder Mushroom Farms #1,2,4 and 5 wells in order to monitor these wells for potential communication later on in the frac stages. At the rime of this inspection the #4 Mushroom Farm well was being monitored. All equipment on site looked ok.
2727586 Primary Facility 2018-05-08 Routine/Complete Inspection No Violations Noted At time of inspection, frac'g of wells 1H, 2H, 3H, 4H, 5H, and 6H have been completed. Equipment being removed from site. Operator intends to begin drilling out plugs on Monday 5/14/18.

Operator representative Frank Kocher on-site.

2747764 Primary Facility 2018-07-02 Drilling/Alteration No Violations Noted On this date this well has been drilled, fracked and is awaiting flow back. The operator is moving equipment in to this well pad today to begin flowing back all 6 wells on this pad. The well is shut in, is tagged, the well head casing and all equipment on site looked ok.
2792880 Primary Facility 2018-10-23 Routine/Complete Inspection No Violations Noted Well appears equipped for production. Well head surrounded by cement barriers. Small generator on site located on secondary containment. Three brine tanks on site.
2821541 Primary Facility 2019-01-03 Routine/Complete Inspection No Violations Noted This well is tagged and in production. The well head casing, piping, production set equipment, containment dike and tank battery look ok.

For data sources see[6]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 04/27/2018 05/08/2018 6235 12,880,000.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 TRS 11800 Tight Rock Solutions Friction Reducer Alkyl Alcohol Not Assigned 10 0.00680457 8480.91
Oxyalkylated alcohol Not Assigned 5 0.00340229 4240.45
Hydrotreated Light Distillate 64742-47-8 30 0.0204137 25442.7
Inorganic Salt Not Assigned 10 0.00680457 8480.91
AP Breaker Lubrizol Breaker Ammonium persulfate 7727-54-0 100 0.00040117 500
Unihib G Geosafe Corrosion Inhibitor Butyl digycol 0000112-34-5 75 0.000618792 771.234
Thiourea 0000062-56-6 1 0.00000825 10.283
Formaldehyde 0000050-00-0 1 0.00000825 10.283
Methanol 0000067-56-1 5 0.00004125 51.416
Alcohols C10-16, ethoxylated 0068002-97-1 50 0.000412528 514.156
Hydrochloric Acid (7.5%) PVS Acidizing Hydrochloric Acid 7647-01-0 7.5 0.138145 172178
Water 7732-18-5 92.5 1.70379 2,123,530.0
TRS 805X Tight Rock Solutions Friction Reducer Alcohol Alkoxylates Not Assigned 5 0.0028421 3542.26
Aliphatic Hydrocarbon Not Assigned 30 0.0170526 21253.6
TRS 3001 Tight Rock Solutions Scale Control Amine Triphosphate Not Assigned 30 0.00757399 9439.87
Ethylene Glycol 107-21-1 5 0.00126233 1573.31
Sodium Phosphate, Tribasic 7601-54-9 5 0.00126233 1573.31
Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 86.2382 107,483,000.0
Sand (Proppant) Sargent/Momentive/Prefferred Proppant Silica Substrate 14808-60-7 100 11.7503 14,645,100.0
Other Chemical(s) Listed Above See Trade Name(s) List Formaldehyde 0000050-00-0 1 0.00000825 10.283
Alcohols C10-16, ethoxylated 0068002-97-1 50 0.000412528 514.156
Alkyl Alcohol Not Assigned 10 0.00680457 8480.91
Ethylene Glycol 107-21-1 5 0.00126233 1573.31
Thiourea 0000062-56-6 1 0.00000825 10.283
Methanol 0000067-56-1 5 0.00004125 51.416
Sodium Phosphate, Tribasic 7601-54-9 5 0.00126233 1573.31
Alcohol Alkoxylates Not Assigned 5 0.0028421 3542.26
Water 7732-18-5 92.5 1.70379 2,123,530.0
Oxyalkylated alcohol Not Assigned 5 0.00340229 4240.45
Inorganic Salt Not Assigned 10 0.00680457 8480.91
BIOC12031A Nalco Biocide Glutaraldehyde 111-30-8 30 0.00544507 6786.49

For data sources see[7]