Well Details

Well ID: 34-013-20828
Loading map...
Country: United States
State: Ohio
County: Belmont
Municipality: Goshen Township
Operator Name: RICE DRILLING D LLC
Well Pad ID: US-OH-001101
Farm/Lease Name: THUNDERSTRUCK
License Status: Producing
License Date: 2014-12-08
Spud Date: 2014-08-16
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2015-03-26
Well Total Depth: 18702.00 ft
Configuration: Horizontal
Latitude: 39.970000
Longitude: -81.020000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-08-05 Proposed Formations:UTICA/POINT PLEASANT, Issued Date:8/5/2014, Expired Date:8/4/2016 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
APP 2014-12-08 Proposed Formations:UTICA/POINT PLEASANT, Issued Date:12/8/2014, Expired Date:12/7/2016 12:00:00 PM, Drilling unit acres:521.0892, Proposed Well Type:OG, Proposed Well Class:EDPW
Reached Total Depth 2015-03-26
Correction to Well 2016-01-22 UNIT CHANGE. ACREAGE AND TAKE POINT.
Completion Report Received 2016-08-08
Correction to Well 2016-10-21 CHANGE IN ACREAGE TAKEPOINT AS COMPLETED PLAT-ALE
Construction Permit Expires 2016-12-07
Record Last Modified 2017-10-23

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2016-07-28 9487 18622 0
9487 18622 0
9487 18622 0

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2016-03-09 H2O 1 9821 Bbl 500160 Weatherford STAGE 1/55

30 SHOTS STAGES 2-54 SEE IMAGES

2016-04-19 H2O 8 10088 Bbl 500370 Weatherford STAGE 55/55

30 SHOTS

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2016 RICE DRILLING D LLC 2108927 0 159
2017 RICE DRILLING D LLC 3520033 0 364
2018 RICE DRILLING D LLC 1490559 0 365
2019 RICE DRILLING D LLC 310888 0 90

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2016 RICE DRILLING D LLC Brine 89966 159
2017 RICE DRILLING D LLC Brine 60571 364
2018 RICE DRILLING D LLC Brine 30412 365
2019 RICE DRILLING D LLC Brine 6319 90

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1569664294 2018-4-25 0:00: PW No Violations 0.50
-1814176703 2020-3-23 0:00: PW No Violations 0.20
-1904516622 2014-8-15 0:00: AM No Violations 0.50
-2111643191 2018-8-21 0:00: PW No Violations 0.50
-724197268 2018-12-5 0:00: PW No Violations 0.20
0525992041 2018-01-10 Production Wells No Violations This well is equipped with 5.5-inch diameter production casing. The well appears to be free flowing without any artificial lift technology present at this time. The well is piped to a gas processing unit and then a production area that contains five 400 barrel production fluid holding tanks. Production records in RBDMS are current to 2017.
0724197268 2018-12-05 Production Wells No Violations Status check inspection found well pad surface and lease road of stone construction and in good repair. The well pad site does have an earthen berm that appears to be sufficient and preforming with vegetation established. No movement of the outward slopes was observed. There lease road is equipped with a gale and signage is present at the entry point of the lease road along with being posted on each well head. There is a 3rd party midstream point on the left rear corner of the well pad that consists of a contact tower and glycol heater. There are 5 wells on the pad with 5 processing units. All 5 wells were equipped with riser pipes and transducers on the A&B sections for annular pressure monitoring. The production tree valves are open. The production fluid facility consists of 5 steel construction 400 barrel fluid capacity tanks situated inside a polymer lined steel containment dike area. Vegetation and erosion was observed on all outward facing slopes and all earthen stock pile areas.
0999903436 2015-08-18 Preliminary Restoration No Violations On this day the wells were awaiting completion operations. The site was evaluated to confirm that proper vegetation and erosion controls had been established and maintained. This site has passed the preliminary restoration.
1569664294 2018-04-25 Production Wells No Violations The well is equipped with 5.5-inch diameter production casing. The well appears to be free flowing with no artificial lift technology present. The well is piped to a gas processing unit. From there, it is routed to a production area that contains five 400-barrel production fluid holding tanks. Annular pressures read on the gauges provided appeared to be 1 pounds in between the outside of the 9.625-inch diameter casing and the inside of the 13.375-inch diameter casing and 600 pounds between the outside of the 5.5-inch diameter casing and the inside of the 9.625-inch diameter casing. The production records within RBDMS are currently updated to 2017.
1823021061 2014-08-16 Casing String Witnessed No Violations On the day of my inspection the 26 conductor pipe was set and cemented. See cement ticket for details. No violations noted.
1877970831 2014-09-29 Casing String Witnessed No Violations On the day of my inspection H.A.D drilling had reached total depth for the surface casing and 24 was ran and cemented. See cement ticket for details. No violations noted.
1904516622 2014-08-15 Administrative Inspection Violations Noted Rice Energy (RICE DRILLING D LLC) has neglected to provide proper notification for the commencement of drilling operations. Rice Energy shall follow the requirements provided in the Ohio Revised Code.
2027378311 2017-09-14 Production Wells No Violations This well is equipped with 5.5-inch diameter production casing. The well appears to be free flowing without any artificial lift technology present at this time. The well is piped to a gas processing unit and then to five 400 barrel production fluid holding tanks. Production records in RBDMS are current to 2017.
2111643191 2018-08-21 Production Wells No Violations On the day of my inspection I witnessed that the well was equipped with a 4-string casing design and was in normal production. Annular pressure monitoring was in place on both the 9.625-inch diameter casing gauge read 35 pounds per square inch, the 13.375-inch diameter casing gauge read 420 pounds per square inch. Production equipment included an individual Gas Processing unit, and 5- 400-barrel production fluid tanks shared with the other producing wells on the pad. The well pad and all equipment were within earthen containment with secondary containment around the production tanks. There were multiple Emergency Shutoff Devices on location, Identification tag were present, and production was current.
525992041 2018-1-10 0:00: PW No Violations 0.50
999903436 2015-8-18 0:00: PL No Violations 1.00

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1904516622 US-OH-119142 2014-09-24 Failure to submit water samples urban