Well Details

Well ID: 34-059-24230
Loading map...
Country: United States
State: Ohio
County: Guernsey
Municipality: Spencer Township
Operator Name: EQT PRODUCTION COMPANY
Well Pad ID: US-OH-000357
Farm/Lease Name: SPENCER
License Status: Plugged Back
License Date: 2012-08-09
Spud Date: 2012-11-02
Spud Drilling Contractor: SAVANNAH DRILLING
Final Drill Date: 2012-12-10
Well Total Depth: 11246.00 ft
Configuration: Vertical
Latitude: 39.900000
Longitude: -81.650000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2012-08-09 Proposed Formations:TRENTON BLACK RIVER, Issued Date:8/9/2012, Expired Date:8/9/2014 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
Plugged Back 2012-12-01
Reached Total Depth 2012-12-10
Completion Report Received 2013-01-31
End of Confidential Data 2013-11-29
Construction Permit Expires 2014-08-09
Record Last Modified 2017-10-30

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 03/04/2013 03/08/2013 6406 5,374,410.0 369481

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 WG-36 Halliburton Gelling Agent Guar Gum 9000-30-0 100 0.00556 0
LoSurf-300D Halliburton Increases the viscosity of the fluid Poly(oxy-1,2-ethanediyl), alpha-(4-nonylphenyl)-omega-hydroxy-,

branched

127087-87-0 5 0.00259 0
Heavy aromatic petroleum naptha 64742-94-5 30 0.01969 0
Ethanol 64-17-5 60 0.04304 0
Naphthalene 91-20-3 5 0.00307 0
Trimethylbenzene 95-63-6 1 0.00057 0
BE-9 Halliburton Biocide Tributyl tetradecyl phosphonium chloride 81741-28-8 10 0.00381 0
SP Breaker Halliburton Oxidizing Breaker Sodium Persulfate 7775-27-1 100 0.00026 0
HAI-OS Halliburton Protects casing Propargyl Alcohol 107-19-7 10 0.00017 0
Methanol 67-56-1 60 0.00102 0
FR-66 Halliburton Friction Reducer Hydrotreated light petroleum distillate 64742-47-8 30 0.02654 0
Water Halliburton Carrier Water 7732-18-5 100 84.957 0
LP-65 Halliburton Scale Inhibitor Ammonium Chloride 12125-02-9 10 0.00245 0
Sand Halliburton Proppant Crystalline Silica 14808-60-7 100 14.6762 0
28% HCl Halliburton Dissolves cement & minerals in perforations Hydrochloric Acid 7647-01-0 28 0.13699 0

For data sources see[3]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2013 EQT PRODUCTION COMPANY Brine 7122 135
2014 EQT PRODUCTION COMPANY Brine 5991 332
2015 EQT PRODUCTION COMPANY Brine 2051 255
2016 EQT PRODUCTION COMPANY Brine 1132 260
2017 PIN OAK ENERGY PARTNERS LLC Brine 390 264
2018 PIN OAK ENERGY PARTNERS LLC Brine 569 360
2019 PIN OAK ENERGY PARTNERS LLC Brine 50 90

For data sources see[4] [5]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1226811114 2014-1-28 0:00: PL No Violations 0.50
-1288567483 2018-4-10 0:00: PW No Violations 2.00
-1312166452 2016-12-16 0:00 PW No Violations 1.00
-1445370408 2019-1-25 0:00: PW No Violations 0.30
-290989011 2015-4-6 0:00:0 PW No Violations 1.00
-333322650 2020-7-23 0:00: PW No Violations 1.00
-464881941 2013-3-11 0:00: PW No Violations
-478953518 2012-11-13 0:00 DD No Violations
-525320467 2012-9-24 0:00: DD No Violations
-605061679 2019-8-8 0:00:0 PW No Violations 1.00
-829311527 2013-12-11 0:00 PW No Violations
0290989011 2015-04-06 Production Wells No Violations On the day of my inspection accompanied by ODNR Inspector Matt Fulk, I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, and 4-400bbl tanks and 140bbl within containment. The well was equipped with a pumping unit powered by electricity with valves in the open position.
0464881941 2013-03-11 Production Wells No Violations On the day of my inspection I witnessed the coil tubing truck rigging up and preparing to drill the frac plugs out.
0478953518 2012-11-13 Drill / Deepen / Reopen No Violations Inspection revealed that drilling rig crew was in process of running 20 casing and preparing to cement it in place.
0525320467 2012-09-24 Drill / Deepen / Reopen No Violations Site construction underway, entrance way has been made and contractor is working there way back toward drill pad.
0684171910 2016-07-28 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, 4-400 barrel tanks and 140 barrel tank within containment. The well was equipped with plunger lift system with valves in the open position. The impoundment has been closed, reclaimed to grade and seeded.
0712996020 2015-09-22 Production Wells No Violations On the day of my inspection I witnessed Kilbarger Service rig #7 was on site and tripped out rods and 2.875 inch tubing. Currently Kilbarger was tripping 2.875 inch tubing back in to convert well to a plunger lift system. Tubing will be set at 6464 feet at 60 degrees in the curve and a Venturi Viper plunger will be installed. Production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, and 4-400bbl tanks and 140bbl within containment. Completed walk around with Production Specialists Dan Mallet and Kenny McCord revealing proper containment and no violations.
0829311527 2013-12-11 Production Wells No Violations On the day of my inspection, I found the well currently in production, I spoke with a employee of EQT and was told the well is paraffin locked and was in the process of pumping hot water down the back side of the well, there are (4) four hundred barrel production tanks (1) three hundred barrel steel tank and (1) one hundred barrel tank setting inside a steel sealed containment, there is temporary containment established around the well, the I.D. is located at the entry of the lease road.
1125116829 2012-11-07 Drill / Deepen / Reopen No Violations Met with Company and Contractors in a Pre-spud Meeting. Savanna Rig 654 is rig drilling well. The pad has been completed and all erosion controls are in place.
1175350441 2017-06-23 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, 4-400 barrel tanks and a 140 barrel tank within containment. The well was equipped with plunger lift system with valves in the open position. Identification was present and production records were current.
1226811114 2014-01-28 Preliminary Restoration No Violations The site passed preliminary restoration according to 1509.072A.
1288567483 2018-04-10 Production Wells No Violations
1312166452 2016-12-16 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, 4-400 barrel tanks and a 140 barrel tank within containment. The well was equipped with plunger lift system with valves in the open position.
1353537739 2012-11-21 Drill / Deepen / Reopen No Violations Inspection revealed that drilling rig has reached 5555 and were cleaning well bore to prepare to log and side wall core and then run 9.625 casing and cement it in place.
1353973624 2012-11-26 Drill / Deepen / Reopen No Violations Stopped by drilling rig for update they were coring Utica Shale@6370 and preparing to pull first 60 core barrel and then they plan on coring three more runs then log well and then plug back well to drill horizontal.
1354037855 2012-11-27 Production Wells No Violations On the day of my inspection the rig is currently drilling the vertical hole for the core plug.
1355238969 2012-12-11 Production Wells No Violations Pryor to my inspection I received a phone call from the company man Darrel Bradley letting me know the Savanna Rig #654 made there TD mark on the date of 12/10/2012. On the day of my inspection I witnessed the rig crew removing the drill pipe and running the five inch back in the well bore.
1358265959 2013-01-15 Production Wells No Violations On the day of my inspection the pit was being solidified.
1375968526 2013-08-08 Production Wells No Violations On the day of my inspection I witnessed Viking well services swabbing the well, there was workers from EQT hooking up flow lines from the well head to the tanks, there was containment around the well head and no spills to report.
1375968921 2013-08-08 Production Wells No Violations I am onsite today training with Mike Hartshorn and witnessed that Viking Well Services was swabbing the well. EQT was hooking up flow lines to the tanks. Containment was in place around well and tanks no spills to report.
1390917513 2014-01-28 Preliminary Restoration No Violations The site passed preliminary restoration according to 1509.072A.
1445370408 2019-01-25 Production Wells No Violations The inspection reveled the well is equipped with a gas plunger lift system. The well was once hooked up to a large Weatherford pumping unit. The horse head has been removed and is lying on the ground. The well is equipped with a flange style well head and 2 7/8-inch tubing, motor valve and logic control box. The tank site consists of 4-400-barrel steel tanks enclosed within a galvanized impoundment and rubberized floor. The Gas Production Unit is tied into the tanks and goes thru a gas vapor recovery system and then a combustor chamber within a wooden fence. The rods and polished rod are lying on the racks at the south end of the pad. The identification is posted at the entrance to the pad. The production records are current with the Division.
1449495369 2015-12-07 Production Wells No Violations
1542845519 2013-02-04 Production Wells No Violations The well is currently shut in.
1902884508 2018-03-30 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, 4-400 barrel tanks and 2-100 barrel tanks within containment. The well was equipped with plunger lift system with valves in the open position. The disconnected pumping unit remains onsite. Identification was present and production records were current.
2064918232 2012-10-10 Drill / Deepen / Reopen No Violations Inspection revealed that pad construction is nearly complete.

Note: Filter sock is in place and ditch lines are stoned to help prevent erosion issues.

684171910 2016-7-28 0:00: PW No Violations 1.50
712996020 2015-9-22 0:00: PW No Violations 2.00

For data sources see[6]