34-173-20587

Well Details

Well ID: 34-173-20587
Loading map...
Country: United States
State: Ohio
County: Wood
Municipality: Milton Township
Operator Name: HILCORP ENERGY COMPANY
Well Pad ID:
Farm/Lease Name: HILCORP-RES 2
License Status: Plugged and Abandoned
License Date: 2018-02-02
Spud Date: 2018-03-23
Spud Drilling Contractor: H A D INC
Final Drill Date: 2018-04-06
Well Total Depth: 2003.00 ft
Configuration: Vertical
Latitude: 41.270000
Longitude: -83.770000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2018-02-02 Proposed Formations:BLACK RIVER, KNOX, PRE-CAMBRIAN, Issued Date:2/2/2018, Expired Date:2/2/2020 12:00:00 PM, Drilling unit acres:45.13, Proposed Well Type:OG, Proposed Well Class:EDPW
Reached Total Depth 2018-04-06
Record Last Modified 2018-05-09
Construction Permit Expires 2020-02-02

For data sources see[2]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1472281299 2018-3-14 0:00: CS No Violations
-1759346217 2019-10-30 0:00 PB No Violations 3.00
-1761787223 2018-3-29 0:00: DD No Violations
-1790181137 2019-10-16 0:00 PB No Violations 0.40
-227708221 2018-3-26 0:00: CS No Violations
-311453305 2018-4-4 0:00:0 DD No Violations
-646849893 2018-3-29 0:00: CS No Violations
0227708221 2018-03-26 Casing String Witnessed No Violations Witnessed the installation of the 9.625 inch surface casing and also the installation of 550 sacks of Class A Cement. Circulation was broken during the installation of the cement and no cement was observed back to surface. A Cement bond log will be required before additional drilling.
0311453305 2018-04-04 Drill / Deepen / Reopen No Violations The drilling of the well has been completed. Well was drilled to a depth of 1990 feet and it was plugged back to a depth of 1736 feet. Production casing was installed at a depth 1464 and 500 sacks of cement was installed. Drilling rig is in the process of moving to the next drilling site.
0337141320 2018-03-28 Casing String Witnessed No Violations After a cement bond log was run, cement was determined to be at a depth of 182 feet below the top of the surface casing. One hundred and fifty sacks of grout was installed and no cement was observed back to service. Pressure on the casing was achieved.
0646849893 2018-03-29 Casing String Witnessed No Violations Witnessed the cement at the surface of the surface casing. Operator is currently installing wellhead and will be testing BOP later in the day.
1321088008 2018-06-12 Production Wells No Violations Received notice from representative from Hilcorp Energy that well is planned to be plugged in the near future. Advised that a plugging plan was needed before plugging activities begin. Wellhead is currently protected by fencing.
1337549067 2019-10-30 0:00 PB No Violations 5.50
141241231 2019-7-1 0:00:0 PB No Violations
1472281299 2018-03-14 Casing String Witnessed No Violations Conductor casing installation was proposed for today but got canceled because of the need for a water well on site. At the present time, drilling contractor is drilling a water well to be used for drilling a new oil and gas well and area approximately one acre has been leveled and stoned for the drilling rig.
1475628609 2018-03-28 Casing String Witnessed No Violations Witnessed the cementing of the surface casing with five hundred and fifty sacks of Class A Cement. Cement returns to surface was not witnessed. A cement bond log will be required to locate the location of the cement.
1523383277 2018-04-10 Drill / Deepen / Reopen No Violations Service rig is on well at the present time. Will be completing well in the near future.
1524084373 2018-04-16 Drill / Deepen / Reopen No Violations Service rig is currently on site. Tubing has been installed in well and currently operator is removing the excess water from the wellbore.
1525442826 2018-03-15 Casing String Witnessed No Violations Inspected the installation of 13.375 inch conductor casing. The conductor casing was installed concentrically and no cement was needed.
1565558361 2018-05-03 Preliminary Restoration No Violations Drilling equipment has been moved off site. Leveling of site will need to be completed before preliminary restoration is approved.
1572457173 2019-10-29 0:00 PB No Violations 5.00
1663741760 2018-03-28 Casing String Witnessed No Violations Witnessed the installation of one hundred and fifty sacks of Class A Cement. Cement was not witnessed at the surface. Cement operator was able to hold a limited amount of pressure on the casing after the cement was installed. A cement bond log will be required before additional cement is added to the annulus of the surface casing.
1761787223 2018-03-29 Drill / Deepen / Reopen No Violations After a second bond log was run, cement was determined to be at a height that was inside of the conductor casing. Drilling operator topped off cement in the surface casing and cement was observed at the surface. Drilling activities to complete the well will continue.
2074803428 2019-12-12 0:00 FR No Violations 0.30
337141320 2018-3-28 0:00: CS No Violations