{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.571574,"lon":-79.847302,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Allegheny | |
Municipality: Indiana Township | |
Operator Name: MARCO DRILLING INC | |
Well Pad ID: | |
Farm/Lease Name: CHARLES L VOGLE ETUX 1 | |
License Status: | |
Spud Date: | |
Permit Date: 2010-02-18 | |
Well Type: GAS | |
Unconventional Well: N | |
Configuration: Vertical Well | |
Conservation: No | |
Latitude: 40.571574 | |
Longitude: -79.847302 |
Date | Event |
---|---|
2010-02-18 | New Permit Application |
2010-05-14 | Performed Spud Operation |
2010-05-28 | Drilling Completion |
2010-06-16 | Perforation |
2013-09-18 | NEWLY DRILLED |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2010 | MARCO DRILLING INC | 443.00 | 90 | 362.40 | 90 | 0.00 | 0 |
2011 | MARCO DRILLING INC | 358.61 | 365 | 157.14 | 365 | 0.00 | 0 |
2012 | MARCO DRILLING INC | 502.8 | 365 | 237.04 | 365 | 0.00 | 0 |
2013 | MARCO DRILLING INC | 596.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2014 | MARCO DRILLING INC | 527.00 | 365 | 88.71 | 365 | 0.00 | 0 |
2015 | MARCO DRILLING INC | 109.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2016 | MARCO DRILLING INC | 603.00 | 365 | 125.88 | 365 | 0.00 | 0 |
2017 | MARCO DRILLING INC | 487.00 | 365 | 64.00 | 365 | 0.00 | 0 |
2018 | MARCO DRILLING INC | 453.00 | 365 | 58.00 | 365 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2010 | MARCO DRILLING INC | Produced Fluid | 240.00 Bbl | ROAD SPREADING | |
2011 | MARCO DRILLING INC | Produced Fluid | 65.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0091472 |
2011 | MARCO DRILLING INC | Produced Fluid | 85.00 Bbl | STORAGE PENDING DISPOSAL OR REUSE | |
2011 | MARCO DRILLING INC | Produced Fluid | 70.00 Bbl | ROAD SPREADING | |
2011 | MARCO DRILLING INC | Produced Fluid | 100.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2012 | MARCO DRILLING INC | Produced Fluid | 50.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095273 |
2012 | MARCO DRILLING INC | Produced Fluid | 105.00 Bbl | ROAD SPREADING | |
2013 | MARCO DRILLING INC | Produced Fluid | 4,620.00 Bbl | CENT WASTE TRT FAC NPDES | PA0095273 |
2013 | MARCO DRILLING INC | Produced Fluid | 4,620.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0095273 |
2016 | MARCO DRILLING INC | Produced Fluid | 349.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0101508 |
2016 | MARCO DRILLING INC | Produced Fluid | 349 Bbl | CENT WASTE TRT FAC NPDES | PA0101508 |
2017 | MARCO DRILLING INC | Produced Fluid | 182.00 Bbl | CENT WASTE TRT FAC NPDES DISCHARGE | PA0095273 |
2018 | MARCO DRILLING INC | Produced Fluid | 119.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE004 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
1875602 | Primary Facility | 2010-04-08 | Routine/Complete Inspection | No Violations Noted | On April 8, 2010 I conducted an inspection for an OG 57 Request for waiver of distance requirement. The well site is proposed to be constructed within 100 ft. from Long Run. Well was site staked. Construction has not begun at site. Proposed E & S plan should protect stream from adverse impact during site/well development if properly implemented & maintained. Drill cuttings are to be encapsulated. Operator must ensure that the bottom of the pit is at least 20 inches above the seasonal high groundwater table. |
1885611 | Primary Facility | 2010-05-19 | Routine/Complete Inspection | No Violations Noted | On May 19, 2010 I conducted a routine inspecion of the above site. Drilling was taking place. The access road was in good condition. A site ID sign and E&S plan were present. E&S controls were in place and constructed according to the plan on site. The pits appeared to be in good condition. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uinform 70% vegetative cover is achieved. |
1890199 | Primary Facility | 2010-05-27 | Routine/Complete Inspection | No Violations Noted | On May 27, 2010 I conducted a routine inspecion of the above site. Drilling was taking place. The access road was in good condition. A site ID sign and E&S plan were present. E&S controls were in place and constructed according to the plan on site. The pits appeared to be in good condition. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uniform 70% vegetative cover is achieved. |
1894980 | Primary Facility | 2010-05-19 | Drilling/Alteration | No Violations Noted | SITE,PIT,OK.DRILLING AT 840'. |
1895131 | Primary Facility | 2010-05-25 | Drilling/Alteration | No Violations Noted | USE RIG 5 RUNNING DRILL RODS AFTER BIT CHANGE.HOLE AT 1584 FT. |
1895144 | Primary Facility | 2010-06-03 | Drilling/Alteration | No Violations Noted | NEIGHBOR SAID SHE WAS CONCERNED THAT SOME DUST OR MIST HAD TRAVED ONTO HER PROPERTY.THE RIG WAS GONE WHEN I ARRIVED.I WIPED THE SIDE OF HER HOUSE WITH A PAPER TOWEL AND IT WAS CLEAN. I TALKED TO OPERATOR AND THEN THE NEIGHBOR AND TOLD HIM THAT THERE WERE NO CHEMICALS USED WHILE DRILLING. |
1895145 | Primary Facility | 2010-05-28 | Drilling/Alteration | No Violations Noted | DRILLING COMPLETE.TD 3250 ft.USE RIG 5 WAITING FOR LOGGING TRUCK. |
1895148 | Primary Facility | 2010-06-14 | Drilling/Alteration | No Violations Noted | I RECIEVED CALL FROM CONCERN NEIGHBOR.SHE WAS WORRIED ABOUT A LOUD NOISE AND HISSING SOUND SHE THOUGHT CAME FROM DRILLING SITE.THE LOUD NOISE WAS CREW BLOWING DOWN WELL BEFORE RUNNING TUBING INTO THE WELL. |
1895156 | Primary Facility | 2010-06-11 | Drilling/Alteration | No Violations Noted | DRILLING COMPLETE. USE RIG 5 HAS MOVED OFF THE SITE. PIT IS GONE,AND THE SITE IS BEING GRADED. |
1902494 | Primary Facility | 2010-07-01 | Routine/Complete Inspection | No Violations Noted | On July 1st, 2010 I conducted a routine inspecion of the above site. Drilling was completed. The access road was in good condition. A site ID sign and E&S plan were present. E&S controls were in place and constructed according to the plan on site. The pits were closed and filled. A pump jack and various piping was being installed. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uniform 70% vegetative cover is achieved. |