37-005-30714

Well Details

Well ID: 37-005-30714
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: Manor Township
Operator Name: EXCO RESOURCES PA LLC
Well Pad ID: 148754
Farm/Lease Name: LENAPE HEIGHTS UNIT 6H
License Status:
Spud Date:
Permit Date: 2010-09-16
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.737075
Longitude: -79.514817

For data sources see[1][2][3]

Well History

Date Event
2010-09-16 New Permit Application
2010-12-03 Performed Spud Operation
2011-03-28 Drilling Completion
2011-06-09 Perforation
2014-04-14 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2011-06-09 2011-06-09 6,884

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 3 HCl Acid Calfrac Well Services Perforation Breakdown Hydrochloric acid 7647-01-0 100.00 0.67
Water Base Fluid Water 100.00 87.78
DWP-944 Calfrac Well Services Biocide Polyethylene glycol 25322-68-3 70.00 0.02
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 40.00 0.01
DAP-901 Calfrac Well Services Scale Inhibitor Organic phosphonate 30.00 0.00575000
Phosphoric acid ammonium salt 5.00 0.00096000
Methanol 67-56-1 30.00 0.00575000
Ammonium chloride 12125-02-9 10.00 0.00192000
Oxyalkylated polyamine 5.00 0.00096000
Amine salt 5.00 0.00096000
DAP-103 Calfrac Well Services Iron Control Citric acid 77-92-9 60.00 0.00293000
DAP-923 Calfrac Well Services Corrosion Inhibitor Methanol 67-56-1 60.00 0.00070000
Ethoxylated C14-15 alcohols 68951-67-7 30.00 0.00035000
Thiourea polymer 68527-49-1 30.00 0.00035000
Propargyl alcohol 107-19-7 10.00 0.00012000
Fatty acids, tall-oil 61790-12-3 30.00 0.00035000
Alkenes, C>10 .alpha.- 64743-02-8 5.00 0.00006000
Sand (Proppant) Calfrac Well Services Propping Agent Quartz 14808-60-7 99.90 11.38
DWP-612 Calfrac Well Services Friction Reducer No Hazardous Materials 100.00 0.08

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 EXCO RESOURCES PA INC 0.00 0 0.00 0 0.00 0
2011 EXCO RESOURCES PA INC 137,521.00 61 0.00 0 0.00 0
2012 EXCO RESOURCES PA LLC 975,660.00 366 0.00 0 0.00 0
2013 EXCO RESOURCES PA LLC 627,555.00 365 0.00 0 0.00 0
2014 EXCO RESOURCES PA LLC 484,866.00 365 0.00 0 0.00 0
2015 EXCO RESOURCES PA LLC 457,577.40 365 0.00 0 0.00 0
2016 EXCO RESOURCES PA LLC 373,238.00 366 0.00 0 0.00 0
2017 EXCO RESOURCES PA LLC 318,992.00 365 0.00 0 0.00 0
2018 EXCO RESOURCES PA LLC 282,206.00 364 0.00 0 0.00 0
2019 EXCO RESOURCES PA LLC 252,594.00 361 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 EXCO RESOURCES PA INC Produced Fluid 4,828.18 Bbl INJECTION DISPOSAL WELL 34-119-27350
2011 EXCO RESOURCES PA INC Drilling Fluid Waste 794.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 EXCO RESOURCES PA INC Drilling Fluid Waste 599.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE EPA ID: 748-163
2011 EXCO RESOURCES PA INC Drilling Fluid Waste 100.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2011 EXCO RESOURCES PA INC Produced Fluid 2,029.60 Bbl REUSE OTHER THAN ROAD SPREADING
2011 EXCO RESOURCES PA INC Fracing Fluid Waste 1,168.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0028207
2011 EXCO RESOURCES PA INC Drilling Fluid Waste 112.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0028207
2011 EXCO RESOURCES PA INC Fracing Fluid Waste 4,759.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 EXCO RESOURCES PA INC Fracing Fluid Waste 455.00 Bbl INJECTION DISPOSAL WELL 34-007-20919
2012 EXCO RESOURCES PA LLC Produced Fluid 2,848.76 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2012 EXCO RESOURCES PA LLC Produced Fluid 493.91 Bbl INJECTION DISPOSAL WELL 34-013-20611
2012 EXCO RESOURCES PA LLC Produced Fluid 630.06 Bbl REUSE OTHER THAN ROAD SPREADING
2012 EXCO RESOURCES PA LLC Produced Fluid 1,782.92 Bbl INJECTION DISPOSAL WELL 34-119-27350
2012 EXCO RESOURCES PA LLC Produced Fluid 101.87 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW008
2012 EXCO RESOURCES PA LLC Produced Fluid 3,530.12 Bbl STORAGE PENDING DISPOSAL OR REUSE
2013 EXCO RESOURCES PA LLC Produced Fluid 429.19 Bbl REUSE OTHER THAN ROAD SPREADING
2013 EXCO RESOURCES PA LLC Produced Fluid 105.21 Bbl STORAGE PENDING DISPOSAL OR REUSE
2013 EXCO RESOURCES PA LLC Produced Fluid 3,807.96 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2013 EXCO RESOURCES PA LLC Produced Fluid 48.00 Bbl INJECTION DISPOSAL WELL 34-119-27350
2014 EXCO RESOURCES PA LLC Produced Fluid 3,326.89 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2015 EXCO RESOURCES PA LLC Produced Fluid 3,028.60 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2016 EXCO RESOURCES PA LLC Produced Fluid 2,147.30 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2016 EXCO RESOURCES PA LLC Produced Fluid 308.90 Bbl REUSE OTHER THAN ROAD SPREADING
2017 EXCO RESOURCES PA LLC Produced Fluid 1,852.70 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2017 EXCO RESOURCES PA LLC 1,248.00 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2017 EXCO RESOURCES PA LLC Produced Fluid 105.20 Bbl REUSE (AT WELL PAD)
2017 EXCO RESOURCES PA LLC 105.20 Bbl REUSE (AT WELL PAD)
2018 EXCO RESOURCES PA LLC Produced Fluid 207.10 Bbl INJECTION DISPOSAL WELL 34-007-21847
2018 EXCO RESOURCES PA LLC Produced Fluid 1,149.10 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE
2019 EXCO RESOURCES PA LLC Produced Fluid 1,125.70 Bbl INJECTION DISPOSAL WELL PAS2D205BCLE

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1933769 Primary Facility 2010-12-13 Routine/Complete Inspection No Violations Noted Drill rig onsite, drilling was ongoing at the Lenape Heights 6H (005-30714) well located on the pad. Drill pit had more than the required two feet of lined freeboard. E&S controls appeared to have been implemented as outlined in the E&S plan. Site is covered by ESCGP-1 ESX09-005-0006. Operator should continue to monitor the E&S controls and the access road until well development activities for the four wells located on the pad have been completed.
1946895 Primary Facility 2011-02-02 Routine/Complete Inspection No Violations Noted Drill rig onsite, drilling was not ongoing at the Lenape Heights 6H (005-30714) well located on the pad. No drill pit was located onsite as the drill rig set-up is a closed loop system where all drill cuttings are captured and hauled to an off-site landfill. E&S controls appeared to have been implemented as outlined in the E&S plan. Site is covered by ESCGP-1 ESX09-005-0006. Operator should continue to monitor the E&S controls and the access road until well development activities for the four wells located on the pad have been completed.
1947945 Primary Facility 2011-02-02 Drilling/Alteration No Violations Noted
1951858 Primary Facility 2011-02-23 Drilling/Alteration No Violations Noted Frontier rig released prior to completion of drilling
1960151 Primary Facility 2011-03-16 Drilling/Alteration No Violations Noted Rigging up Patterson UTI 257
1972874 Primary Facility 2011-04-05 Routine/Complete Inspection No Violations Noted
1983996 Primary Facility 2011-06-27 Complaint Inspection No Violations Noted Well stimulation activities were ongoing at the time of the inspection. Spoke with pad manager Rick Olson regarding the water that had been observed on Penn View Road. Mr. Olson stated that the water is river water that is being withdrawn from the Allegheny River and deposited onto the paved roads to address dust issues. Mr. Olson stated that initially he questioned the water on the road and he contacted his superiors at EXCO and inquired about the watering of roads. He was informed that they were indeed spreading river water to minimize dust in the residential areas. This practice had been suspended during rainy days, however was begun again recently. Observed no accelerated erosion or sedimentation issues while onsite, however a full site inspection was not performed due to the ongoing well stimulation activities.
1987403 Primary Facility 2011-07-11 Incident- Response to Accident or Event Violation(s) Noted Inspection performed as a result of the operator notifying the Department of a release of flowback fluids to the ground. Wells were actively being flared at the time of the inspection. According to Doug Byers, who WQS Higgins met onsite an out of service pipe was left adjacent to the flare trailers brought onsite. This pipe still contained flowback fluid. Upon ignition of the flare stacks the fluid in the pipe was heated resulting in the pipe bursting and releasing the flowback fluid to the well pad immediately adjacent to the flar trailers and to a stormwater management trap. A vacuum truck located onsite vacuumed any fluid left on the surface. Prior to excavating the affected fill area the flare stacks had to be safely moved to another section of the well pad. Once this is completed the affected soil will be excavated and sampled to insure that all of the contaminated media had been excavated.
2019236 Primary Facility 2011-09-30 Compliance Evaluation No Violations Noted Drilling had been completed, wells appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. Noted that the roll-offs boxes that had contained the contaminated mdeia excavated as a result of the flowback discharge had been removed. There was no observed accelerated erosion or sedimentation observed in relation to the access road or well-site. Noted that the public road leading to the well pad had been repaved. Site required final stabilization, i.e. final grading, seeding & mulching. The Department recommends that the operator undertake temporary erosion controls to insure continued site stabilization through the winter months.
2030067 Primary Facility 2011-12-29 Administrative/File Review No Violations Noted review for compliance
2042790 Primary Facility 2012-02-15 Routine/Complete Inspection No Violations Noted Drilling had been completed, well appeared to be equipped for production. Brine tank located onsite and it appeared to be in sound condition. Erosion controls had been implemented and maintained as outlined in the approved ESCGP.
2252471 Primary Facility 2014-03-11 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tank located onsite and it appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2325798 Primary Facility 2014-12-03 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tank located onsite and it appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2444304 Primary Facility 2016-01-28 Routine/Complete Inspection No Violations Noted Well was appropriately labeled and brine tank located onsite. Brine tank appeared to be in sound condition. Brine tank containment was holding a minimal amount of water. There was no observed accelerated erosion & sedimentation in relation to the site or access road.
2560292 Primary Facility 2017-02-09 Routine/Complete Inspection No Violations Noted Well tagged-in production. Well head casing-production set equipment-tank battery-dike containment looked ok.
2694710 Primary Facility 2018-02-15 Routine/Complete Inspection No Violations Noted At time of inspection, well 6H drilled and appears equipped for production. Wells 3H, 4H, and 5H also drilled and appear equipped for production.
2841387 Primary Facility 2019-02-15 Routine/Partial Inspection No Violations Noted At the time of inspection, well was producing. The well integrity appeared to be in good condition, with no leaks or spills. Only some minor rust was observed. Flow could be heard. The cellar was filled to surface with gravel. There was a tubing gauge that was reading 204 psi. The well was properly labeled and the Emergency Response sign was posted at the entrance to the site. There were 4 tanks contained within a lined steel dike. 2 dual line heaters were also being used.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
1987403 615205 07/11/2011 2011-07-11 78.54* - Failure to properly control or dispose of industrial or residual waste to prevent pollution of the waters of the Commonwealth. Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
615205 272516 NOV - Notice of Violation Comply/Closed 2011-10-13
615205 279689 CACP - Consent Assessment of Civil Penalty Comply/Closed 2012-01-23 2012-01-23 $5,000.00 $5,000.00

For data sources see[8]