37-007-20394

Well Details

Well ID: 37-007-20394
Loading map...
Country: United States
State: Pennsylvania
County: Beaver
Municipality: New Sewickley Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 145356
Farm/Lease Name: B1 PER B1-1H
License Status:
Spud Date:
Permit Date: 2013-05-24
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.739594
Longitude: -80.169089

For data sources see[1][2][3]

Well History

Date Event
2013-05-24 New Permit Application
2013-09-10 Performed Spud Operation
2013-10-03 Drilling Completion
2013-12-11 Drilling Completion
2015-03-04 Perforation
2015-04-27 Newly Drilled
2016-01-05 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2015-03-30 2015-04-08 5,327 11,456,500 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 EC6116A Nalco Biocide Polyethylene Glycol 25322-68-3 60 0.0131171 14704.1
Dibromoacetonitrile 3252-43-5 5 0.00109309 1225.34
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 30 0.00655853 7352.03
WGA-3 PfP Technology Water Viscosifier Guar Gum 9000-30-0 100 0.0012935 1450
LEB 10X Weatherford Gel Breaker Ethylene Glycol 107-21-1 40 0.00001344 15.068
Sand (Proppant) Sargent Proppant Silica 14808-60-7 99.9 11.0378 12,373,300.0
Hydrochloric Acid (7.5%) Axiall Acidizing Hydrogen Chloride 7647-01-0 40 0.869734 974960
Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 86.6503 97,133,800.0
Unihib G GeoSafe Acid Corrosion Inhibitor Thiourea 62-56-6 1 0.00000713 7.994
Glycol Ether 112-34-5 60 0.000427856 479.621
Methanol 67-56-1 5 0.00003565 39.968
Ethoxylated Alcohol 68002-97-1 35 0.000249582 279.779
Formaldehyde 50-00-0 1 0.00000713 7.994
Acetophenone 98-86-2 1 0.00000713 7.994
Unislik ST50 CESI Friction Reducer Petroleum Distillates, Hydrotreated Light 64742-47-8 30 0.0241228 27041.3
Scale Hib A Nalco Scale Inhibitor Ethylene Glycol 107-21-1 30 0.00341891 3832.56
Iron Control A Nalco Iron Control Ethylene Glycol 107-21-1 30 0.00324811 3641.09

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2013 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2014 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2015 PENNENERGY RESOURCES LLC 481,253.00 140 0.00 0 2,033.00 140
2016 PENNENERGY RESOURCES LLC 857,892.00 366 0.00 0 2,433.00 366
2017 PENNENERGY RESOURCES LLC 657,957.00 328 0.00 0 1,461.00 328
2018 PENNENERGY RESOURCES LLC 588,563.00 355 0.00 0 1,157.00 355
2019 PENNENERGY RESOURCES LLC 519,804.00 351 0.00 0 1,032.00 351

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2013 PENNENERGY RESOURCES LLC Drilling Fluid Waste 1,300.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE EPA ID: 748-163
2013 PENNENERGY RESOURCES LLC Drill Cuttings 625.00 Tons LANDFILL CID # 28726
2015 PENNENERGY RESOURCES LLC Fracturing Fluid Waste 45.40 Tons LANDFILL CID # 28726
2015 PENNENERGY RESOURCES LLC Servicing Fluid 15.00 Bbl LANDFILL CID # 28726
2016 PENNENERGY RESOURCES LLC Synthetic Liner Materials 10.45 Tons LANDFILL CID # 28726
2016 PENNENERGY RESOURCES LLC Produced Fluid 391.05 Bbl INJECTION DISPOSAL WELL 34-155-23223
2016 PENNENERGY RESOURCES LLC Produced Fluid 254.17 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Produced Fluid 254.17 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Other Oil & Gas Wastes 103.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Produced Fluid 1,557.36 Bbl INJECTION DISPOSAL WELL 34-155-22403
2016 PENNENERGY RESOURCES LLC Other Oil & Gas Wastes 103.00 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Produced Fluid 505.29 Bbl INJECTION DISPOSAL WELL 34-155-23196
2016 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 17.05 Tons LANDFILL UT2300249
2016 PENNENERGY RESOURCES LLC Produced Fluid 13,410.15 Bbl REUSE OTHER THAN ROAD SPREADING
2017 PENNENERGY RESOURCES LLC Produced Fluid 3,327.49 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC 2,411.21 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Produced Fluid 121.19 Bbl INJECTION DISPOSAL WELL 34-155-23196
2018 PENNENERGY RESOURCES LLC Produced Fluid 1,184.55 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Produced Fluid 32.93 Bbl INJECTION DISPOSAL WELL 34-155-23795
2019 PENNENERGY RESOURCES LLC Produced Fluid 30.36 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 PENNENERGY RESOURCES LLC Produced Fluid 29.08 Bbl INJECTION DISPOSAL WELL 34-155-22403
2019 PENNENERGY RESOURCES LLC Produced Fluid 137.55 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 1,705.17 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Produced Fluid 59.09 Bbl INJECTION DISPOSAL WELL 34-155-23196

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2201873 Primary Facility 2013-09-05 Administrative/File Review No Violations Noted This preoperational inspection satisfies operator's obligation as outlined under Title 58 , Ch 32 § 3258 a. 1.
2205405 Primary Facility 2013-09-18 Routine/Complete Inspection No Violations Noted This well had conductor set. Cellar was covered with steel plate. The inspection for this well was conducted concurrently with the inspection for site number 768793 (inspection report # 2205390.) Impoundment was under construction without liner. No erosion or sedimentation issues were apparent.
2206049 Primary Facility 2013-09-11 Drilling/Alteration No Violations Noted auger rig is drilling a 22" hole for a 16" conductor. site and e&s, are ok.
2206054 Primary Facility 2013-09-18 Drilling/Alteration No Violations Noted CELLER AND CONDUCTOR ARE IN, AND COVERED WITH A STEEL PLATE.
2210208 Primary Facility 2013-10-01 Drilling/Alteration No Violations Noted DRILLING TOP HOLE AT 1,438'. THE SITE IS IN GOOD CONDITION.
2212251 Primary Facility 2013-10-08 Drilling/Alteration No Violations Noted TOP HOLE COMPLETE. SITE IS OK.
2213879 Primary Facility 2013-10-16 Drilling/Alteration No Violations Noted WELL IS COVERED WITH A STEEL PLATE. PAD PROTECTION HAS BEEN LEFT DOWN.
2223172 Primary Facility 2013-11-14 Drilling/Alteration No Violations Noted top hole drilling is complete. patterson 259 is on the pad and will finish the well. The site is in good condition.
2227159 Primary Facility 2013-11-25 Drilling/Alteration No Violations Noted TOP HOLE COMPLETE. RIG IS ON THE PAD DRILLING ANOTHER WELL AND THE B1-1H IS NEXT.
2227168 Primary Facility 2013-12-05 Drilling/Alteration No Violations Noted DRILLING AT 4,677'. RIG CHANGING TO HEAVEY MUD, THEN THEY WILL BEGIN DRILLING THE CURVE.
2231779 Primary Facility 2013-12-12 Drilling/Alteration No Violations Noted HALIBURTON IS CEMENTING THE 5.5" PRODUCTION CASING. RIG WILL MOVE TO B1-3HUD.
2232281 Primary Facility 2013-10-10 Routine/Complete Inspection No Violations Noted This well was partially drilled and properly labeled. The inspection for this well was conducted concurrently with the inspection for site number 768793 (inspection report # 2232277.) Impoundment was dug and unlined. No erosion or sedimentation issues were apparent.
2232812 Primary Facility 2013-11-05 Routine/Complete Inspection No Violations Noted The inspection for this well was conducted concurrently with the inspection for site number 768793 (inspection report # 2232809.) Temporary stabilization appeared adequate. No erosion or sedimentation issues were observed.
2232822 Primary Facility 2013-11-12 Routine/Complete Inspection No Violations Noted The inspection for this well was conducted concurrently with the inspection for site number 768793 (inspection report # 2232820.) Water impoundment was being lined. No erosion or sedimentation issues were apparent.
2236881 Primary Facility 2014-01-13 Routine/Complete Inspection No Violations Noted The inspection for this well was conducted concurrently with the inspection for site number 768793 (inspection report # 2236823.) Two minor slips were noted on pad's embankments. Crews were erecting equipment in preparation for stimulation operations. An above ground storage tank (AST) was being erected. Inspector confirmed with operator's representative that it would be used for flow back fluids. Operator's representative agreed to provide a copy of the OG-71 for the AST.
2247352 Primary Facility 2014-01-02 Drilling/Alteration No Violations Noted the site is being prepared for frac.
2247363 Primary Facility 2014-01-14 Drilling/Alteration No Violations Noted FRACING ON HOLD TILL OTHERS ARE FRACED. FLOWBACK WILL BE RECYCLED.
2251708 Primary Facility 2014-03-06 Drilling/Alteration No Violations Noted WELL IS DRILLED BUT NOT FRACED. SITE IS OK.
2251711 Primary Facility 2014-01-29 Drilling/Alteration No Violations Noted WELL IS DRILLED BUT NOT FRACED. SITE IS OK.
2251843 Primary Facility 2014-02-11 Drilling/Alteration No Violations Noted WELL IS DRILLED AND THE RIG IS GONE. SNOW REMOVAL IS THE ONLY ACTIVITY.
2255748 Primary Facility 2014-03-17 Drilling/Alteration No Violations Noted WELL IS DRILLED BUT OTHER WORK IS ON HOLD.
2257679 Primary Facility 2014-03-20 Drilling/Alteration No Violations Noted WELL IS DRILLED BUT NOT FRACED.
2259898 Primary Facility 2014-04-01 Drilling/Alteration No Violations Noted THIS WELL IS DRILLED BUT NOT FRACED.
2275099 Primary Facility 2014-04-08 Drilling/Alteration No Violations Noted THIS WELL IS DRILLED BUT NOT FRACED. THE WELL IS SHUT IN. THE SITE IS OK.
2361542 Primary Facility 2015-04-10 Routine/Complete Inspection No Violations Noted
2367409 Primary Facility 2015-04-02 Drilling/Alteration No Violations Noted THIS WELL IS BEING FRACED AND MAY BE FLARED LATER.
2372402 Primary Facility 2015-04-20 Drilling/Alteration No Violations Noted ALL FRAC PLUGS ARE DRILLED OUT. TUBING WILL BE RUN.
2374334 Primary Facility 2015-05-26 Routine/Complete Inspection No Violations Noted
2390945 Primary Facility 2015-07-01 Drilling/Alteration No Violations Noted FLOWBACK IS PRODUCING FLUID AT A RATE OF 120 BBL PER HR. THE SITE IS OK.
2391261 Primary Facility 2015-07-17 Drilling/Alteration No Violations Noted THIS WELL IS FRACED AND IS BEING HOOKED UP TO BEGIN PRODUCTION.
2392553 Primary Facility 2015-07-17 Routine/Complete Inspection No Violations Noted
2439246 Primary Facility 2016-01-04 Routine/Complete Inspection No Violations Noted
2478957 Primary Facility 2016-04-22 Routine/Complete Inspection No Violations Noted
2561367 Primary Facility 2017-02-14 Routine/Complete Inspection No Violations Noted On 2/14/2017, Brian MacQuarrie onsite at unconventional well site. Act 9 sign in place. Erosion and Sedimentation Plan onsite. Three wells in production. Wells properly tagged. Two 400 bbl tanks installed within stainless steel containment structure. Freshwater impoundment maintained and fenced in. Erosion and Sedimentation Best Management Practices installed and maintained. Site stabilized with vegetative growth in previously disturbed areas. No apparent E/S issues.
2666338 Primary Facility 2017-12-01 Routine/Complete Inspection No Violations Noted Site had been constructed as outlined in the E&S plan contained within the ESCGP. All site and access road erosion controls had been implemented and properly maintained. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All disturbed areas had been stabilized with vegetation attaining 70% uniform vegetative cover. Well appeared to be equipped for production. Two produced fluids tanks were located onsite within containment. Both the tanks and containment appeared to be in sound condition.
2683655 Primary Facility 2018-01-18 Routine/Complete Inspection No Violations Noted Site had been constructed as outlined within the E&S Plan contained within the ESCGP. Evaluation of erosion control functionality and maintenance was not feasible due to snow and ice conditions. Well appeared to be equipped for production. Two brine tanks were located onsite within secondary containment. Both the tanks and containment appeared to be in sound condition. Well development impoundment located onsite and it was observed to contain frozen fluids and snow.
2698789 Primary Facility 2018-02-27 Routine/Complete Inspection No Violations Noted Site and access road had been constructed in accordance with the ESCGP. All site and access road erosion controls had been implemented and maintained properly. All disturbed slopes and soil stockpiles had been stabilized with vegetation. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that significant precipitation events had recently ceased. Two produced fluids tanks were located onsite within secondary containment. Both the tanks and containment appeared to be in sound condition. There was an Act 9 sign located onsite in accordance with 25 Pa Code Chapter 78a.55(i).
2761039 Primary Facility 2018-08-07 Complaint Inspection No Violations Noted At the time of inspection well equipped for production. Two brine tanks within secondary containment and appears structurally sound. GPUs within containment. No E&S issues.

For data sources see[8]