37-129-28731

Well Details

Well ID: 37-129-28731
Loading map...
Country: United States
State: Pennsylvania
County: Westmoreland
Municipality: South Huntingdon Township
Operator Name: CHEVRON APPALACHIA LLC
Well Pad ID: 148841
Farm/Lease Name: MATTY-MOMYER UNIT 4H
License Status:
Spud Date:
Permit Date: 2011-12-23
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 40.184828
Longitude: -79.721317

For data sources see[1][2][3]

Well History

Date Event
2011-12-23 New Permit Application
2012-05-09 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2013-02-14 2013-02-14 7,234 6,678,605

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 ASP 900 Nalco Friction Reducer Ammonium Sulfate 7783-20-2 30.0 None
EC6116A Nalco Biocide Dibromoacetonitrile 3252-43-5 5.0 0.00116
FR-66 Halliburton Friction Reducer Hydrotreated Light Distillite 64742-47-8 30.0 0.03492
Clean Volume (gals) Carrier/Base Fluid 91.57 100.0
EC6673W Nalco Iron Control Ethylene Glycol 107-21-1 30.0 0.00686
Proppant (lbs) Proppant 8.43 9.28899
EC6486A Nalco Scale Inhibitor Ethylene Glycol 107-21-1 30.0 0.0073
7.5 Hcl Acid Reagent/PP G Used to open perfs Hydrochloric Acid 7647-01-0 7.5 0.29057
EC 6116A Nalco Biocide 1,1-Dibromo-3-nitrilopropionamide 10222-01-2 30.0 0.00696
Polyethylene Glycol 25322-68-3 60.0 0.01391
WG-36 Halliburton Water Viscosifier Guar Gum 9000-30-0 100.0 0.00146
GBW-30 Halliburton Gel Breaker Carbohydrates 95.0 0.00049
Hemicellulase enzyme 9012-54-8 15.0 0.00008000

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2011 CHEVRON APPALACHIA LLC 0.00 0 0.00 0 0.00 0
2012 CHEVRON APPALACHIA LLC 0.00 0 0.00 0 0.00 0
2013 CHEVRON APPALACHIA LLC 693,021.00 275 0.00 0 0.00 0
2014 CHEVRON APPALACHIA LLC 813,349.00 365 0.00 0 0.00 0
2015 CHEVRON APPALACHIA LLC 525,414.00 365 0.00 0 0.00 0
2016 CHEVRON APPALACHIA LLC 415,530.00 366 0.00 0 0.00 0
2017 CHEVRON APPALACHIA LLC 344,357.00 365 0.00 0 0.00 0
2018 CHEVRON APPALACHIA LLC 300,162.00 365 0.00 0 0.00 0
2019 CHEVRON APPALACHIA LLC 255,929.00 365 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2012 CHEVRON APPALACHIA LLC Drill Cuttings 1,558.67 Tons LANDFILL 100419
2012 CHEVRON APPALACHIA LLC Fracing Fluid Waste 2,065.00 Bbl REUSE OTHER THAN ROAD SPREADING
2012 CHEVRON APPALACHIA LLC Drilling Fluid Waste 1,010.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001
2013 CHEVRON APPALACHIA LLC Fracing Fluid Waste 22,768.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001
2013 CHEVRON APPALACHIA LLC Fracturing Fluid Waste 30.04 Tons LANDFILL 073 114 654
2013 CHEVRON APPALACHIA LLC Produced Fluid 5,275.00 Bbl REUSE OTHER THAN ROAD SPREADING
2013 CHEVRON APPALACHIA LLC Fracing Fluid Waste 4,174.50 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW001
2013 CHEVRON APPALACHIA LLC Produced Fluid 17.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW001
2013 CHEVRON APPALACHIA LLC Fracing Fluid Waste 13,113.00 Bbl REUSE OTHER THAN ROAD SPREADING
2013 CHEVRON APPALACHIA LLC Drilling Fluid Waste 520.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW001
2014 CHEVRON APPALACHIA LLC Produced Fluid 2,540.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 CHEVRON APPALACHIA LLC Fracturing Fluid Waste 35.67 Tons STORAGE PENDING DISPOSAL OR REUSE MID074259565
2015 CHEVRON APPALACHIA LLC Produced Fluid 1,195.00 Bbl REUSE OTHER THAN ROAD SPREADING
2016 CHEVRON APPALACHIA LLC Produced Fluid 435.52 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW019
2016 CHEVRON APPALACHIA LLC Produced Fluid 660.01 Bbl REUSE OTHER THAN ROAD SPREADING
2017 CHEVRON APPALACHIA LLC Produced Fluid 3,311.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW001
2017 CHEVRON APPALACHIA LLC Produced Fluid 225.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2017 CHEVRON APPALACHIA LLC Produced Fluid 57.50 Bbl REUSE AT A WELL PAD OUTSIDE PENNSYLVANIA
2017 CHEVRON APPALACHIA LLC Produced Fluid 287.50 Bbl REUSE (AT WELL PAD)
2018 CHEVRON APPALACHIA LLC Produced Fluid 278.50 Bbl REUSE (AT WELL PAD)
2018 CHEVRON APPALACHIA LLC Produced Fluid 55.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW019
2018 CHEVRON APPALACHIA LLC Produced Fluid 332.00 Bbl REUSE AT A WELL PAD OUTSIDE PENNSYLVANIA
2019 CHEVRON APPALACHIA LLC Produced Fluid 530.00 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2064920 Primary Facility 2012-05-04 Routine/Complete Inspection No Violations Noted Pre drilling E&S inspection. No issues noted.
2065490 Primary Facility 2012-05-07 Routine/Complete Inspection No Violations Noted This was a spud inspection. No issues noted.
2068927 Primary Facility 2012-05-07 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS
2070095 Primary Facility 2012-05-21 Drilling/Alteration No Violations Noted 5/21/2012 Yost rig 6 drlling top hole on Chevron pad, depth of 495'.
2077515 Primary Facility 2012-06-08 Drilling/Alteration No Violations Noted HORIZONTAL MARCELLUS
2085520 Primary Facility 2012-07-11 Drilling/Alteration No Violations Noted 7/11/2012 Patterson rig 339 has tagged the plug and going to kick off and drill the lateral.
2085533 Primary Facility 2012-07-16 Drilling/Alteration No Violations Noted 7/16/2012 Patterson rig drilling lateral, depth of 12,846. KOP 7236' and LP 8329'.
2085544 Primary Facility 2012-07-18 Drilling/Alteration No Violations Noted 7/18/2012 Patterson rig 339 running 5.5 production csg. Well TD 14,033.
2093504 Primary Facility 2012-08-02 Drilling/Alteration No Violations Noted 8/2/2012 Patterson rig 339 finishing up on the 3H well.
2093636 Primary Facility 2012-08-13 Drilling/Alteration No Violations Noted 8/13/2012 Patterson rig 339 stacked out on pad waiting for the top hole rig to finish up.
2107435 Primary Facility 2012-10-15 Routine/Complete Inspection No Violations Noted Routine inspection. No issues noted.
2123118 Primary Facility 2012-12-12 Drilling/Alteration No Violations Noted 12/12/2012 wait on frac.
2159711 Primary Facility 2013-04-19 Routine/Complete Inspection No Violations Noted Routine inspection no issues noted.
2174938 Primary Facility 2013-06-12 Routine/Complete Inspection No Violations Noted Inspection the result of a restoration inspection received by the Department on 06/07/2013. At the time of inspection the well appears to be drilled and stimulated. During the inspection it appeared that the Operator was in the process of flowing back to a pit located onsite. The pit appeared to be in sound condition and had the required 2' of freeboard. The erosion and sedimentation plan was on site and appears to be implemented as designed and all associated BMPs appear to properly installed and functioning. The Department suggests the Operator continue to inspect the site weekly and after significant precipitation events to ensure stability of the site is maintained.
2216347 Primary Facility 2013-10-24 Routine/Complete Inspection No Violations Noted At the time of inspection the well appeared to be drilled and equipped for production. The well apparatus, brine tanks, and GPU units located onsite appear to be in sound working condition. The Department notes that the Operator appears to be in the process of regrading the site in preparation for site restoration. The erosion and sedimentation plan was on site and appears to be properly implemented as outlined in the plan. No observation of accelerated erosion or sedimentation in relation the well pad area of access road. The Department suggests the Operator continue to monitor the site weekly and after significant precipitation events to ensure the site stability in maintained.
2228523 Primary Facility 2013-11-11 Routine/Complete Inspection No Violations Noted At the time of inspection the well appeared to be drilled and equipped for production. The well apparatus, brine tanks, and GPU units located onsite appear to be in sound working condition. The Department notes that the Operator appears to be in the process of regrading the site in preparation for site restoration. The erosion and sedimentation plan was on site and appears to be properly implemented as outlined in the plan. No observation of accelerated erosion or sedimentation in relation the well pad area of access road. The Department suggests the Operator continue to monitor the site weekly and after significant precipitation events to ensure the site stability in maintained.
2326837 Primary Facility 2014-12-08 Routine/Complete Inspection No Violations Noted At the time of inspection the well appeared to be drilled and equipped for production. The well apparatus, brine tanks, and GPU units located onsite appear to be in sound working condition. The Department suggests the Operator continue to monitor the site weekly and after significant precipitation events to ensure the site stability in maintained.
2376322 Primary Facility 2015-06-04 Routine/Complete Inspection No Violations Noted At the time of inspection the wells appeared to be drilled and equipped for production. Well apparatus, brine tanks and gas production units appear to be in sound condition.
2378652 Primary Facility 2015-06-11 Routine/Complete Inspection No Violations Noted On site inspection with Operator to discuss issues outlined on inspection #2376319. At the time of inspection the wells appeared to be drilled and equipped for production. Well apparatus, brine tanks and gas production units appear to be in sound condition.
2444511 Primary Facility 2016-01-28 Routine/Partial Inspection No Violations Noted Inspection in response to the Operators submission of a "Well Site Restoration Report on 11/26/2014. At the time of inspection earth disturbance activities at the site authorized by the Well Permit are complete, the site has been stabilized and the Post Construction Stormwater Management BMP's have been installed
2475710 Primary Facility 2016-04-18 Routine/Complete Inspection No Violations Noted Tag, 2 tanks, e&s ok.
2647763 Primary Facility 2017-10-16 Routine/Complete Inspection No Violations Noted Well drilled and equipped for production. Well tag present. Well apparatus, brine tanks and gas production units appear to be in sound condition. No accelerated erosion or sedimentation observed on well site or access road.
2671942 Primary Facility 2017-12-06 Routine/Complete Inspection No Violations Noted At the time of inspection well equipped for production. Brine tank within secondary containment and appears to be structurally sound. No E&S issues.
2808804 Primary Facility 2018-11-30 Routine/Complete Inspection No Violations Noted At the time of inspection well equipped for production. Brine tank within secondary containment and appears structurally sound. No E&S issues.
2845200 Primary Facility 2019-02-27 Routine/Complete Inspection No Violations Noted This well is tagged and in production. The well head casing, piping, production set equipment, containment dike and tank battery look ok.

For data sources see[8]