| Well ID: 34-111-24375 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.818347026,"lon":-81.30419839,"icon":""}]} |
| County: | |
| Municipality: | |
| Operator Name: | |
| Well Pad ID: | |
| Farm/Lease Name: | |
| First Permit Date: | |
| Last Permit Date: | |
| Spud Date: 2013-06-15 | |
| Unconventional: | |
| Horizontal: | |
| Producing: No | |
| Violations: 0 | |
| Latitude: 39.818347026 | |
| Longitude: -81.30419839 |
| PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
|---|
| PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
|---|
| INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID | VIOLATION CODE | VIOLATION_COMMENT |
|---|---|---|---|---|---|---|
| -1019705439 | 2014-02-21 | At 8:00 am I met Bill Stolarik, Conrad Baston, Tom Wince, Joe Honeycutt, and Josh Allred to discuss the slip that has developed. Conrad stated that the construction records from the site indicated that neither the rig nor any production equipment was jeopardized by the slip. Conrad agreed to submit to ODNR DOGRM a plan in writing as soon as it is finalized. The rig is currently drilling at a depth of 13459'. | ||||
| -1290355557 | 2014-02-20 | On the day of my inspection I witnessed that Patterson UTI Drilling Rig #342 was drilling an 8.5 inch diameter lateral hole at a depth of 12313 feet on 13.1# oil based drilling mud with an estimated td of 16824 feet. Site inspection accompanied by Company Man revealed a slip on the northeast corner of drill pad. Core samples have been taken and are awaiting results for a plan of action to address. I requested that Antero expedite a plan to address the slip as thaw has begun and the slip will only worsen. At the time of inspection simultaneous operation was taking place with the drilling and 2 wells producing. Repairs were being made to the drilling unit primary containment. Noble County Inspector Eric Conrad made call to Antero Construction Engineer and he stated that a plan would be emailed to Eric tonight. Monroe County Inspector Bill Stolarik will meet with them tomorrow. | ||||
| -1481759976 | 2013-12-13 | On site inspection to document the status of the drilling process, The well bore has been drilled to the point of the 1st intermediate casing string and the larger rig is slated to move in soon. | ||||
| -1630461767 | 2014-04-17 | Compliance notice follow up inspection found the earthen slip mentioned in the initial violation has been repaired accordingly, the preliminary restoration addressing the drill site as a hole will be approved upon the completion of all well activity on the drilling pad. | ||||
| -1878666156 | 2014-01-13 | Status check inspection on the drilling progress found the current drilling depth to be 4,100' in the 12.250 2nd intermediate well bore section, the company is drilling on air. | ||||
| -1993117978 | 2013-08-14 | The well is in the production testing stages and is being flow tested. The tubing pressure is 5000 psi. I asked the company man on site to place proper well identification on each well head. | ||||
| -261401772 | 2014-02-14 | Stopped by drill site to check for containment around dirty water tanks, all produced water is being stored within containment area. | ||||
| -71550009 | 2013-11-20 | On site electrical inspection with Brad Sellers the Divisions inter agency coordinator and a inspector with the Ohio Department of Commerce- electrical inspector, On the day of inspection deficiencies were found in the grounding system on the electrical service generator feeding the site trailers, We also discovered the internal grounding system inside the electrical panels servicing the site trailers were insufficiently wired according to the National Electric Code. Antero's people were on site and made the needed corrections accordingly. | ||||
| -782216571 | 2014-07-30 | Status check inspection on the preliminary restoration found the well drilling and stimulation process is now complete and the well is in line and producing with 8- 400 barrel production tanks on site servicing all 6 wells on the drill pad now in production. | ||||
| -96776965 | 2014-02-20 | My inspection finds the rig, Patterson 342, is drilling 8.5" hole at a depth of 12370'. I am accompanied by inspector L.J. Parkins. Due to an electrical storm we were unable to perform a full site inspection. | ||||
| 1259155127 | 2013-12-12 | Wells have been spudded but not completed. Waiting on drill rig for drilling intermittent strings and lateral. | ||||
| 1371592464 | 2013-06-16 | On this day I witnessed the setting of 85' of 26 conductor casing with 30 barrels of cement returns to surface, the 100' minimum per permit requirements could not be reached due to the initial site excavation removing 80' of cover down to solid bedrock. Division Deputy Chief Dave Claus was made aware of this issue on 06/14/13 by Dave Ball on 3411124374. | ||||
| 1385157101 | 2013-11-22 | Inspector on site to witness the cementing of the 18.625 surface casing, 413' of pipe was set inside of a 435' 24 diameter bore hole and cemented with 849 sacks of class A 2% calcium 1/4# flake cement with 63 barrels of good cement returns witnessed to surface and the casing pressure tested to 500 psi over lift pressure upon the landing of the cement plug. | ||||
| 1385797853 | 2013-11-26 | on site inspection to witness the cementing of 2,054' of 13.375 casing, Allied Cement services cemented the casing back to surface with good cement returns and lift pressure with the casing pressure tested to 500# over lift pressure upon the landing of the cement plug. All records received. | ||||
| 1392734875 | 2014-02-18 | My inspection today finds the drilling rig, Patterson 342, is drilling 8.5" hole at a depth of 9707'. Upon inspection of the containment I reminded the company representative to closely monitor it as the snow melts. A substantial slip has developed on the east side of the pad. The company drilling representative stated that soil sampling was done and a plan developed to stabilize the slip. | ||||
| 1393002274 | 2014-02-20 | I called Daniel Smith with Antero and asked him about the slip. Mr. Smith stated that Antero engineers were formulating a plan to stabilize the slip. I received a call from Conrad Baston, Antero Civil Engineering General Manager, at 3:42pm. He agreed to meet onsite and discuss the slip. | ||||
| 1393065583 | 2014-02-21 | On the day of my inspection I was accompanied by Inspector Eric Conrad and Antero's environmental construction personnel with the inspection and meeting purpose of reviewing a slip that has occurred on the North East corner of the drill site pad, On this day the company has presented a remedial plan of action to repair the slip along with a temporary plan of action to stabilize the area by the means of diverting the surface water infiltrating the area, protective boundaries will be established for safety reasons. Completed engineered drawings will be submitted immediately upon completion to the Division, The affected area was photographed and my direct supervisor Rocky King notified and sent pictures of the situation. | ||||
| 1393263877 | 2014-02-24 | Status check inspection of the drilling progress found the production borehole total depth to be drilled has been reached at 16,656', the company is encountering formation gas pressure at 500 units and is attempting to bring the 13.7# mud weight up to properly control the gas pressure before pulling out of the hole with the drill string. Inspection of the recent slip area found the slip has not progressed since my last inspection. | ||||
| 1393506060 | 2014-02-27 | On this day following up on NOV-1290355557, I contacted Monroe County Inspector Bill Stolarik and he and Noble County Inspector Eric Conrad have met with Antero Resources Corp. Construction Engineer and a plan has been submitted to address slip. Temporary berms are in place to redirect surface water from impacting slip. | ||||
| 1395871686 | 2014-03-26 | Compliance follow-up inspection found the company has beginning the slip repair by the means of bringing in an auger rig to set 21 45' pilings to be cemented in place and a wall erected between the pilings. | ||||
| 1399556908 | 2014-05-08 | Status check inspection on the stimulation process found Gofrac services on location preparing to stimulate stage # 22 with a solid completion plug set at 12,811' and perforations from 12,797' to 12,650' with 1000 gallons of 15% HCL acid used. | ||||
| 1492639396 | 2014-04-09 | Status check inspection on the slip repair process found the retaining wall being installed is complete and the company is removing the instable material from below the wall that is locates in the slip, the company is hauling in larger rock to place below to replace the unstable soil that has slipped, photographs were taken of the repair process. | ||||
| 2048193753 | 2013-06-12 | Notification was received that the said well is to be spudded and the conductor set on this day. I inspected the site and reviewed the permit conditions with the drilling superintendent for Express Energy who is the drilling contractor. I shall Gps the well once the conductor is set. | ||||
| 2143071725 | 2014-04-01 | Status check inspection on the remedial work over slip repair on the North East side of the location, 90% of the pilings have been installed and cemented in place with a minimum of 20' set into bedrock, the company shall then install a barrier supportive wall between the pilings finishing the project by then installing perferated drains and catch basins before backfilling. | ||||
| 606867988 | 2014-02-23 | Status check inspection on the drilling progress found the current drilling depth to be 15,783' in the Horizontal well bore section using a 8.5 direction drilling assembly with a current mud weight of 13.2# and directional azimuth of 333.19 degrees with a total estimated drilling depth to be 16,824'. The drilling supervisor and myself did walk the location and review the recent slip on the North East side of the location and observed the company has made efforts to deter the surface water from further infiltrating the area. | ||||
| 63835264 | 2014-06-23 | Status check inspection of the completion process found Key Energy's completion service rigging up on the well assembling the well control Blow out preventer stack and Cudd completion services tubing snubbing unit standing by to assemble their unit, proper containment is in place and the 500 barrel flow back tanks have proper grounding. | ||||
| 777045000 | 2014-01-15 | Status check inspection found the 12.250 2nd intermediate borehole total drilling depth has been reached at 7041' the company was conditioning the borehole in preparation to run the 9.625 intermediate casing. |