37-003-22111

Well Details

Well ID: 37-003-22111
Loading map...
Operator Name: PENNECO OIL CO INC
First Permit Date: 2010-03-15
Last Permit Date: 2010-03-15
Spud Date: 2010-04-12
Unconventional: No
Horizontal: No
Violations: None
Latitude: 40.484261
Longitude: -79.713102

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-0 3671.0 365.0 0.0 0.0 50.19 365.0
2012-0 4841.0 366.0 0.0 0.0 297.63 366.0
2011-0 6919.0 365.0 0.0 0.0 351.52 365.0
2010-0 6612.0 214.0 0.0 0.0 387.4 214.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2010-0 DRILLING FLUID WASTE 385.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2010-0 FRACING FLUID WASTE 1360.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2010-0 PRODUCED FLUID 25.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2011-0 PRODUCED FLUID 25.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443 HART RESOURCE TECHNOLOGIES, INC. - CREEKSIDE CREEKSIDE PA

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1877536 2010-04-15 No Violations Noted On April 15th, 2010 I conducted a routine inspection of the above site. Drilling was taking place at the time of the inspection. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site. The drilling pits looked to be in good condition and were well below the minimum 2' of freeboard.
1882813 2010-04-20 No Violations Noted COMPLAINT #27065 NOISE AND SOAP IN THE AIR. THE RIG HAS MOVED FROM THIS SITE AND THERE IS NOT ANY SOAP IN THE PIT.
1882829 2010-04-19 No Violations Noted DRILLING AT 3343'. ESTIMATED TD AT 3500'.
1882842 2010-04-15 No Violations Noted DAVE HILL DRILLING AT 1949'. 7' CASING TO BE SET AT 2109'.
1883344 2010-04-30 No Violations Noted On April 30th, 2010 I conducted an inspection of the above site in response to several odor complaints. Drilling was completed at the time of the inspection. A swabbing rig was on site and likely the source of the odors. The frac pit had been recently constructed. The drilling pits looked to be in good condition. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uniform 70% vegetative cover is reached.
1884491 2010-04-28 No Violations Noted RIG SET UP BAILING. E&S OK.
1884504 2010-04-28 No Violations Noted COMPLAINT # 271010 FOR ODORS. RIG BAILING WELL CAUSING SOME ODORS. CREW WILL FINISH UP 4/29/10.
1884518 2010-04-30 No Violations Noted WELL SWABED. TUBING IN. RUNNING RODS.
1884575 2010-04-22 No Violations Noted SITE IS CLEAN, AND PIT LEVEL OK. SERVICE RIG ON SITE BUT NOT SET UP.
1894963 2010-05-13 No Violations Noted SITE IS GRADED AND PIT IS GONE.SITE NEEDS SEEDED.RODS IN NO JACK.
1895036 2010-06-15 No Violations Noted DRILLING COMPLETE.THERE NO JACK BUT TUBING AND RODS ARE IN. TANK IS SET AND DIKED.THE ACCESS ROAD IS STONED.
1904613 2010-07-09 No Violations Noted On July 9th, 2010 I conducted a routine inspection of the above site. Drilling had been completed and the well was in production. The pits have been closed and filled. The tanks were in place and a dike constructed around them. A site ID sign and E&S plan were posted at the site. The access road was in good condition. All E&S controls were in place and constructed according to the plan at site. The site was graded, seeded, and mulched. The operator should continue to inspect the E&S controls routinely and after each runoff event until the site is restored and uniform 70% vegetative cover is reached.
1912623 2010-08-02 No Violations Noted ODOR COMPLAINT #272590. SLIGHT CRUDE ODOR FROM TANK VENT. OPERATOR WILL INSTALL A CARBON FILTER.
1927308 2010-10-05 No Violations Noted OIL AND GAS WELL. SITE RESTORED. OIL TANK HAS A VAPOR FILTER. ALL WELL EQUIPTMENT IS FENCED.
1947179 2011-01-07 No Violations Noted OIL AND GAS WELL. TANKS WITH VAPOR FILTERS. EQUIPTMENT FENCED AND LOCKED. SITE AND ACCESS STONED.