34-067-21558

Well Details

Well ID: 34-067-21558
Loading map...
Country: United States
State: Ohio
County: Harrison
Municipality: Archer Township
Operator Name: EAP OHIO LLC
Well Pad ID: US-OH-001585
Farm/Lease Name: DAVIS TRUST 19-11-5
License Status: Producing
License Date: 2018-10-30
Spud Date: 2018-10-30
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2018-11-21
Well Total Depth: 22432.00 ft
Configuration: Horizontal
Latitude: 40.300000
Longitude: -81.050000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2018-10-30 Proposed Formations:POINT PLEASANT, Issued Date:10/30/2018, Expired Date:10/29/2020 12:00:00 PM, Drilling unit acres:335.7, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2018-11-21
Record Last Modified 2019-01-23
Construction Permit Expires 2020-10-29

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
22173 22176 0
9275 9396 0
9275 9396 0

For data sources see[3]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1170653341 2018-11-6 0:00: CS No Violations 5.00
-1552374147 2019-4-24 0:00: CT No Violations 1.00
-286099603 2018-11-1 0:00: CS No Violations 1.50
-608463212 2019-5-6 0:00:0 CT No Violations 1.00
0286099603 2018-11-01 Casing String Witnessed No Violations PAD ADDRESS:83690 Bargar Road, Cadiz. On the day of my inspection I witnessed Express had augured a 36 inch diameter hole to 50 feet and sleeved in with 30 inch diameter casing. That casing was previously grouted with 12 yards. Express then drilled a 26 inch diameter hole to 120 feet. 120 feet of 20 inch diameter, 94# conductor casing was run. Express was onsite with 216 sacks of class A cement. Additives include 2% CaCl and .5 lb./sack cello-flake. Cement weighed with mudscale at 15.6 ppg and yield of 1.18. Cement was displaced with 39 barrels of fresh water. No cement returned to surface.
0363303328 2019-05-14 Completion Testing No Violations On the day of my inspection I was accompanied by Inspector Jeff Adams. A Profrac frac crew is on location tied into the 1H, 3H, and 201H wells. Stage 75/87 is perforated on this well. Plug set at 11210, with bottom perforation at 11195 and top perforation at 11075. Stage desgin calls for 330000 lbs of sand and approximately 10000 barrels of fluid. The 13.375x9.625 annular pressure is 10 psi and the 9.625x5.5 annular pressure is zero.
0390319924 2019-04-08 Completion Testing No Violations On the day of my inspection I met with Blake James, Eric Visky, and Dan Imlay, all consultants for Encino. Profrac is onsite tied into this well and the 5H. They are currently running wireline on stage 13/87. Stage 13 plug wasset at 20505, with bottom perforation at 20499 and top perforation at 20375. 13.375x9.625 annular pressure is 0 and 9.625 x 5.5 annular pressure is 0.
0487704048 2019-05-23 Completion Testing No Violations On the day of my inspection I was accompanied by Inspector Jeff Adams. We witnessed a Profrac frac crew onsite tied into the 1H, 3H, and 201H wells. Stage 75/87 is awaiting frac. Stage 75 plug set at 11205, with bottom perforation at 11195 and top perforation at 11075. Twelve 350 barrel steel produced water tanks are on location, within their own containment. Tanks had <50 barrels each remaining in them.
0608463212 2019-05-06 Completion Testing No Violations On the day of my inspection I witnessed a Profrac frac crew onsite. Profrac is currently tied into the 1H, 3H, 5H and the 201H wells. Stage 72/87 plug set at 11655 feet, with bottom perforation at 11646 feet and top perforation at 11525 feet. The 13.375x9.625 annular pressure was 0 psi and the 9.625x5.5 annular pressure was 18 psi.
1170653341 2018-11-06 Casing String Witnessed No Violations On the day of my inspection I witnessed the surface casing cement job. Patterson 571 drilled a 17.5 inch diameter open hole to a depth of 705 feet. Previous casing set and cemented was 20 inch diameter conductor casing to a depth of 120 feet. Wyoming Casing ran 701.5 feet of 13.375 inch diameter casing, j-55, 54.5 lbs/foot, with 3.5 stick up. Casing shoe is at 698 feet. Casing was centralized. Shoe track is 45 feet long. Halliburton was onsite with 615 sacks of class A neocem cement. Cement weighed with mudscale at 15.8 ppg and yield of 1.22. 30% excess ran in open hole. Cement displaced with 101 barrels of fresh water. 30 barrels of gel pumped ahead of cement. 20 barrels of cement returned to surface, and floats held with 1 barrel back.
1541511249 2018-10-31 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed Express Energy has drilled this hole to 50 feet with a 36 inch diameter auger bit and cemented a 30 inch diameter casing in with 12 yards of grout. The hole kept falling in. Identified myself to Superintenant David Newman.
1552374147 2019-04-24 Completion Testing No Violations On the day of my inspection I witnessed Profrac crew on location tied into the 5H and this well. During my inspection they are pressure testing to start pumping stage 56/87. Stage 56 plug I set at 14055 feet, with bottom perforation at 14045 feet and top perforation at 13925 feet. Stage design is to pump 3000 gallons of 7.5% HCL acid, 330000 lbs of sand, and approximately 10000 barrels of fluid. Stage not witnessed. The 13.375x9.625 annular pressure is 0 psi and the 9.625x5.5 annular pressure is 0 psi.
1555355522 2019-04-15 Completion Testing No Violations On the day of my inspection I witnessed Procfrac pump stage 26/87. Met with company man Jesse Cammer and Blake James. Plug was set at 18562, with bottom perforation at 18545 and top perforation at 18425. Clean fluid pumped was 9085 barrels, in addition to 71 barrels of 7.5% HCL acid and 1220 barrels of produced water. Profrac pumped 198380 lbs of 100 mesh sand and 132940 lbs of 40/70 sand for a total of 331320 lbs. Average rate was 93.6 barrels per minute (BPM) and average pressure was 10204 psi. The maximum rate was 97.6 bpm and the maximum pressure was 10889 psi. Break down pressure was 7731 psi and Initial shut in pressure (ISIP) was 5332 psi. Frac gradient of 1.09 psi/ft. 13.375x9.625 annular pressure is 15 psi and the 9.625x5.5 annular pressure is 15 psi.
1559754195 2019-06-05 Completion Testing No Violations On the day of my inspection I was accompanied by Supervisor Eric Conrad. During the inspection we witnessed Stone Rig 15 drilling out frac plugs. Rig is drilling with a 4.5 inch diameter bit and 2.875 inch diameter tubing. They are currently drilling on plug 44 at 15750 feet. The 13.375x9.625 annular pressure was zero and the 9.625x5.5 annular pressure is 250 psi.
2001357751 2018-11-16 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed Patterson 571 drilling an 8.5 inch diameter hole at 10654. Current mud weight is 11.2 ppg. 8.75 inch diameter hole was drilled to 8082. Kick off point for the curve is at 8345 and it was landed at 9468. Company man Neil Brown said estimated total depth is 22501. He also said they started on 12 ppg mud and experienced losses of 225 barrels and have not had any issues since theyve reduced mud weight.
2073463417 2019-9-17 0:00: PL No Violations 1.00
337563188 2019-6-19 0:00: CT No Violations 1.00
363303328 2019-5-14 0:00: CT No Violations 1.00
390319924 2019-4-8 0:00:0 CT No Violations 2.00
487704048 2019-5-23 0:00: CT No Violations 1.00
757633544 2019-6-25 0:00: CT No Violations 1.00

For data sources see[4]