34-083-24166

Well Details

Well ID: 34-083-24166
Loading map...
Country: United States
State: Ohio
County: Knox
Municipality: Union Township
Operator Name: MARAM ENERGY INC
Well Pad ID:
Farm/Lease Name: SHEW DIANE & STEVEN
License Status: Producing
License Date: 2001-02-05
Spud Date: 2001-09-04
Spud Drilling Contractor: CAMPHIRE DRILLING
Final Drill Date: 2001-10-29
Well Total Depth: 3138.00 ft
Configuration: Vertical
Latitude: 40.400000
Longitude: -82.200000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2001-02-05 476 MARAM ENERGY CO Proposed Formation CLINTON Issued Date 2/5/01 Expired Date 2/5/02 6:00:00 AM
Original Spud 2001-09-04 Combination Job. Surface mudded then 4 1/2 cemented. I left Columbus when notified and arrived tail end of mud job. Mud was staying at surface. Mud was power mixed and gravity fed from top. 5sk gel mixed with 45 sk clay. 4.5 inch casing used a rubber wiper plug , float shoe, 3 centralizers.
Completed 2001-10-29 Combination Job. Surface mudded then 4 1/2 cemented. I left Columbus when notified and arrived tail end of mud job. Mud was staying at surface. Mud was power mixed and gravity fed from top. 5sk gel mixed with 45 sk clay. 4.5 inch casing used a rubber wiper plug , float shoe, 3 centralizers.
Reached Total Depth 2001-10-29 Combination Job. Surface mudded then 4 1/2 cemented. I left Columbus when notified and arrived tail end of mud job. Mud was staying at surface. Mud was power mixed and gravity fed from top. 5sk gel mixed with 45 sk clay. 4.5 inch casing used a rubber wiper plug , float shoe, 3 centralizers.
Completion Report Received 2001-12-10 Combination Job. Surface mudded then 4 1/2 cemented. I left Columbus when notified and arrived tail end of mud job. Mud was staying at surface. Mud was power mixed and gravity fed from top. 5sk gel mixed with 45 sk clay. 4.5 inch casing used a rubber wiper plug , float shoe, 3 centralizers.
Construction Permit Expires 2002-02-05 Combination Job. Surface mudded then 4 1/2 cemented. I left Columbus when notified and arrived tail end of mud job. Mud was staying at surface. Mud was power mixed and gravity fed from top. 5sk gel mixed with 45 sk clay. 4.5 inch casing used a rubber wiper plug , float shoe, 3 centralizers.
Record Last Modified 2017-02-15 Combination Job. Surface mudded then 4 1/2 cemented. I left Columbus when notified and arrived tail end of mud job. Mud was staying at surface. Mud was power mixed and gravity fed from top. 5sk gel mixed with 45 sk clay. 4.5 inch casing used a rubber wiper plug , float shoe, 3 centralizers.

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2002-01-28 3058 3076 38
3058 3076 38
3058 3076 38

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 15 2000 Bbl 20000 420 GALLONS HCL ACID

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2002 MARAM ENERGY INC 3049.00 795.00 260
2003 MARAM ENERGY INC 2849.00 419.00 360
2004 MARAM ENERGY INC 2022.00 340.00 365
2005 MARAM ENERGY INC 1757.00 123.00 365
2006 MARAM ENERGY INC 2328.00 409.00 365
2007 MARAM ENERGY INC 2164.00 205.00 365
2008 MARAM ENERGY INC 2025.00 198.00 365
2010 MARAM ENERGY INC 1762.00 153.00 365
2011 MARAM ENERGY INC 1405.00 66.00 280
2012 MARAM ENERGY INC 1601.00 108.00 366
2013 MARAM ENERGY INC 1471.00 146.00 365
2014 MARAM ENERGY INC 1314.00 101.00 365
2015 MARAM ENERGY INC 1147.00 101.00 365
2016 MARAM ENERGY INC 1058.00 114.00 365
2017 MARAM ENERGY INC 992.00 75.00 365
2018 MARAM ENERGY INC 708.00 79.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2002 MARAM ENERGY INC Brine 2070 260
2003 MARAM ENERGY INC Brine 1216 360
2004 MARAM ENERGY INC Brine 402 365
2005 MARAM ENERGY INC Brine 633 365
2006 MARAM ENERGY INC Brine 357 365
2007 MARAM ENERGY INC Brine 836 365
2008 MARAM ENERGY INC Brine 578 365
2010 MARAM ENERGY INC Brine 395 365
2011 MARAM ENERGY INC Brine 307 280
2012 MARAM ENERGY INC Brine 372 366
2013 MARAM ENERGY INC Brine 392 365
2014 MARAM ENERGY INC Brine 365 365
2015 MARAM ENERGY INC Brine 235 365
2016 MARAM ENERGY INC Brine 415 365
2017 MARAM ENERGY INC Brine 365 365
2018 MARAM ENERGY INC Brine 243 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-606784953 2002-5-10 0:00: PL No Violations
001287i434 2001-10-25 Drill / Deepen / Reopen No Violations drlg at 3095 Clinton sand
001287i740 2002-05-10 Preliminary Restoration Violations Noted pit open , no grading of well site , no seeding . Well in production . Ext. to 6/18/02
0606784953 2002-05-10 Preliminary Restoration Violations Noted FOLLOW UP TO NOV # 1287i740 pit open , no grading of well site , no seeding . Well in production . Ext. to 6/18/02 PITS FILLED, AREA SEEDED. NOV TERMINATED.
0721567343 2006-08-21 Preliminary Restoration No Violations PITS FILLED, EROSION CONTROLLED. NOV TERMINATED. WELL IS CAPABLE OF PRODUCTION.
1210i13571 2002-03-22 Production Wells No Violations Newly drilled well. Well is pumping. ID at well head. Pit still present and not emptied.
1210i1357164 2002-3-22 0:00: PW No Violations
1214237309 2017-08-08 Production Wells No Violations They are still in the process of cleaning up the debris around the well units.
1278808740 2017-08-15 Production Wells No Violations The well has proper identification and the loose debris have been cleaned up and removed.
1287i434 2001-10-25 0:00 DD No Violations
1287i740 2002-5-10 0:00: PL No Violations
1347244486 2017-08-03 Production Wells No Violations The well has identification posted but the area is still in the process of being policed up of debris. I called Shawn Baldridge from Maram Energy and he said the area should be finished being cleaned up by weeks end.
1364212707 2017-07-21 Production Wells Violations Noted This well is in production and the pumping unit was pumping during this inspection. There was debris laying around the pump jack that is a general safety concern. There is no identification posted at the well and this well shares battery tanks with other wells in the area. The law requires that identification be posted at both the well and the tank batteries. This well needs to have identification posted at the well to be compliant with the law, and all the debris need to be picked up and removed.
721567343 2006-8-21 0:00: PL No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
001287i740 US-OH-108108 2002-05-10 Failure to fill pits within 5 mos. (CHANGE) (REPLACE)
0606784953 US-OH-126799 2002-05-10 Failure to fill pits within 5 mos. (CHANGE) (REPLACE)
1364212707 US-OH-110668 2017-08-11 General Safety
1364212707 US-OH-110669 2017-08-11 Failure to legibly identify well

For data sources see[9]