Well Details

Well ID: 34-099-22996
Loading map...
Country: United States
State: Ohio
County: <County>
Municipality:
Operator Name: AM-TEK OIL INC
Well Pad ID:
Farm/Lease Name: TOD HOMESTEAD CEMETERY
License Status: Producing
License Date: 2005-08-31
Spud Date: 2006-03-08
Spud Drilling Contractor: CAPSTAR DRILLING
Final Drill Date: 2006-03-15
Well Total Depth: 5420.00 ft
Configuration: Directional
Latitude: 41.120000
Longitude: -80.670000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2005-08-31 Proposed Formations:ORISKANY/CLINTON, Issued Date:8/31/2005, Expired Date:8/31/2006 6:00:00 AM, Drilling unit acres:161.91, Proposed Well Type:OG, Proposed Well Class:POOL
Correction to Well 2005-09-02 TARGET LOCATION: 2050'NL & 11,100'WL OF TWP.; X= 2,503,825; Y= 537,675; ELEV.= 1095'.
Original Spud 2006-03-08 RBDMS Rec
Completed 2006-03-15 RBDMS Rec
Reached Total Depth 2006-03-15 RBDMS Rec
Completion Report Received 2006-05-01 RBDMS Rec
Correction to Well 2006-05-26 CHANGE IN TARGET INFORMATION: FOOTAGE= 2170'NL & 11,285'WL OF TWP. TARGET X= 2,504,010. TARGET Y= 537,535 (SOURCE OF LOCATION: GPS ).
Construction Permit Expires 2006-08-31 RBDMS Rec
Record Last Modified 2017-02-15 RBDMS Rec

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2006-07-13 5208 5292 78
5208 5292 78
5208 5292 78

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 15 80000 Gal 0 500 GALLONS HCL ACID

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2006 DUCK CREEK ENERGY INC 2020.00 83.00 210
2007 DUCK CREEK ENERGY INC 8755.00 356.00 365
2008 DUCK CREEK ENERGY INC 8306.00 212.00 365
2009 DUCK CREEK ENERGY INC 6414.00 152.00 365
2010 DUCK CREEK ENERGY INC 8976.00 126.00 365
2011 DUCK CREEK ENERGY INC 9425.00 164.00 365
2012 DUCK CREEK ENERGY INC 8090.00 163.00 366
2013 DUCK CREEK ENERGY INC 5562.00 29.00 365
2014 DUCK CREEK ENERGY INC 3736.00 86.00 365
2015 DUCK CREEK ENERGY INC 3436.00 29.00 365
2016 DUCK CREEK ENERGY INC 4604.00 122.00 365
2017 DUCK CREEK ENERGY INC 4018.00 153.00 365
2018 DUCK CREEK ENERGY INC 4615.00 76.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2006 DUCK CREEK ENERGY INC Brine 389 210
2007 DUCK CREEK ENERGY INC Brine 360 365
2008 DUCK CREEK ENERGY INC Brine 138 365
2009 DUCK CREEK ENERGY INC Brine 170 365
2010 DUCK CREEK ENERGY INC Brine 155 365
2011 DUCK CREEK ENERGY INC Brine 124 365
2012 DUCK CREEK ENERGY INC Brine 121 366
2013 DUCK CREEK ENERGY INC Brine 46 365
2014 DUCK CREEK ENERGY INC Brine 19 365
2015 DUCK CREEK ENERGY INC Brine 16 365
2016 DUCK CREEK ENERGY INC Brine 54 365
2017 DUCK CREEK ENERGY INC Brine 52 365
2018 DUCK CREEK ENERGY INC Brine 88 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1154254329 2006-5-8 0:00:0 PL No Violations 0.50
-1611292496 2018-7-12 0:00: PW No Violations
-658232915 2018-7-25 0:00: PW No Violations 1.00
-732796657 2018-6-26 0:00: PW No Violations 0.50
0573358442 2018-07-26 Production Wells No Violations The purpose of my inspection was to follow-up on compliance notice #1611292496. At the time of my inspection Moore Well Services was on location to remove the plunger assembly and begin to convert the well to operate with a pump jack unit. No gas or fluid flow was observed from the well. The location remained stable. I will schedule a follow-up inspection to document the status of the well and installation of screened security fencing for compliance with 1501:9-9 (E). No further action is necessary.
0658232915 2018-07-25 Production Wells No Violations The purpose of my inspection was to follow-up on compliance notice # 732796657 . Inspector John Fleming was present during the inspection. I met with Duck Creek Energy representative Larry Gibler and discussed the scope of work and restoration of the location following the conversion. A workover rig operated by Moore Well Service was on location to remove the plunger lift assembly and replace the assembly with a pump jack unit. At the time of inspection the well had been blown down in preparation for the work and was no longer leaking. I will schedule a follow-up inspection to witness the repairs. No further action is necessary at this time.
0732796657 2018-06-26 Production Wells Violations Noted The purpose of my inspection was to conduct a status check inspection on well #2-2995. Inspector John Fleming was present during the inspection. RBDMS indicated reported production was current. Access to the well and tank battery remained drivable and stable through the Tod Cemetery. The well was located within a locked chain-link enclosure that contained correct identification. The 8.625 well head was above grade and closed to atmosphere. The 4.5 production casing was equipped with a plunger lift assembly. Production valves were in the open position. I witnessed gas leaking from the tubing head assembly. Cloth rags were tied around the assembly. No free fluid was observed on the assembly or ground. A stable earthen dike that was free of fluid was present around the production equipment. A locked and screened chain-link fence enclosure was present on top of the dike. Correct identification was present on the fence. Equipment on location consisted of one (1) horizontal separator and two (2) steel production tanks. The separator remained in good repair. No production chart was present. The production tanks remained in good repair. Valves were closed and plugged. A charcoal filter was present. Hatch lids were closed. While on location I called and spoke with Duck Creek Energy representative Larry Gibler regarding the well leak. Mr. Gibler stated he was aware of the leak and had scheduled a service rig to replace the tubing. I communicated to Mr. Gibler that I was issuing a compliance notice due to the well being insufficiently equipped to prevent the escape of gas. I requested that the surface leak be repaired within 14 days and to be notified of when the service rig was to be on location due to the urban location of the well. I will schedule a follow-up inspection to document the status of repairs.
1141998193 2006-03-02 Drill / Deepen / Reopen No Violations Arrived on site for the surface job. Observed the running inof the surface pipe and the cementing in of the pipe. Good cement returns (14 bbls).
1154254329 2006-05-08 Preliminary Restoration No Violations The tank battery consists of 2-100 bbl storage tanks, 1-separator, a fence and a dike. The dike is not fully closed at this time since the well has no been put into operation as yet. The pits are closed. Partial compliance for preliminary restoration.
1176314238 2007-04-05 Preliminary Restoration No Violations The drilling pits were filled in. Vegetation was growing on the location. No erosion was visible. No drilling equipment on location. Pine trees around tank battery. This well and tank battery have passed the preliminary restoration.
1606227356 2018-12-26 Production Wells No Violations I performed a status check on the above location. A pumping Unit has been installed on this location. The well is in production. The tank battery is equipped with one 140 barrel tank and a horizonal separator. Valves are closed and plugged ID signs are posted No noted violations at this time
1611292496 2018-07-12 Production Wells No Violations The purpose of my inspection was to follow-up on compliance notice # 732796657. At the time of my inspection, the well was still leaking gas to atmosphere. The leak was less pronounced. The tubing was pressure gauge indicated 100 psi. While on location I called and spoke with Duck Creek representative Larry Gibler to regarding the status of the service rig to make repairs. Mr. Gibler stated the rig was scheduled to arrive in a few weeks. Mr. Gibler continued that he had blown the well down and was operating it at a lower pressure until repairs were finished. During the call I requested notification of when the rig arrived due to the urban location. I will schedule a follow-up inspection to document the status of repairs once completed.
573358442 2018-7-26 0:00: PW No Violations 4.00

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
0732796657 US-OH-128334 2018-10-04 Well insufficiently equipped to prevent escape of oil and gas

For data sources see[9]