Well Details

Well ID: 34-111-24552
Loading map...
Country: United States
State: Ohio
County: Monroe
Municipality: Seneca Township
Operator Name: ANTERO RESOURCES CORPORATION
Well Pad ID: US-OH-001145
Farm/Lease Name: KURTZ UNIT
License Status: Producing
License Date: 2015-10-14
Spud Date: 2014-11-29
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2016-03-12
Well Total Depth: 18646.00 ft
Configuration: Horizontal
Latitude: 39.830000
Longitude: -81.250000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-11-25 Proposed Formations:POINT PLEASANT, Issued Date:11/25/2014, Expired Date:11/24/2016 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
APP 2015-03-18 Proposed Formations:POINT PLEASANT, Issued Date:3/18/2015, Expired Date:3/17/2017 12:00:00 PM, Drilling unit acres:536.741, Proposed Well Type:OG, Proposed Well Class:POOL
APP 2015-10-14 Proposed Formations:POINT PLEASANT, Issued Date:10/14/2015, Expired Date:10/13/2017 12:00:00 PM, Drilling unit acres:546.89, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2016-03-12
Completion Report Received 2016-04-25
Construction Permit Expires 2017-10-13
Record Last Modified 2017-10-23

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2016-04-25 8690 18495 0
8690 18495 0
8690 18495 0

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 12/07/2015 12/21/2015 8553 14,835,300.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 FRW-18 Baker Hughes Friction Reducer Listed with other chemicals NA 0 0.0271574 0
Water Operator Carrier Water 7732-18-5 100 89.994 123,694,000.0
Enzyme G-NE Baker Hughes Breaker Listed with other chemicals NA 0 0.00112832 0
Sand, White Baker Hughes Proppant Listed with other chemicals NA 0 9.66239 0
GW-3 Baker Hughes Gelling Agent Listed with other chemicals NA 0 0.0684914 0
Other Chemicals Hemicellulase Enzyme Concentrate 9025-56-3 0 0.00005642 77.5415
Oleamide DEA 93-83-4 0 0.00181049 2488.46
Quaternary Ammonium Compound 68424-85-1 0 0.000438169 602.248
Sodium Chloride 7647-14-5 0 0.004687 6441.76
Ethylene Glycol 107-21-1 0 0.00481467 6617.6
Potassium Chloride 7447-40-7 0 0.000160489 220.587
Polyoxythylene Sorbitan Monooleate 9005-65-6 0 0.000452623 622.115
Petroleum Distillates 64742-47-8 0 0.0271574 37326.9
Glutaraldehyde 111-30-8 0 0.00262901 3613.49
Poly (acrylamide-co-acrylic acid) partial sodium salt 62649-23-4 0 0.0271574 37326.9
Ethanol 64-17-5 0 0.000438169 602.248
Ammonium Chloride 12125-02-9 0 0.00271574 3732.69
Didecyl Dimethyl Ammonium Chloride 7173-51-5 0 0.000876337 1204.5
Guar Gum 9000-30-0 0 0.0684914 94139
Hydrochloric Acid 7647-01-0 0 0.0402565 55331.2
Crystalline Silica (Quartz) 14808-60-7 0 9.66239 13,280,600.0
Ethoxylated Alcohol 68551-12-2 0 0.00181049 2488.46
Calcium Chloride 10043-52-4 0 0.000802446 1102.93
Sorbitan Monooleate 1338-43-8 0 0.000452623 622.115
HCl, 20.1 - 28% Baker Hughes Acidizing Listed with other chemicals NA 0 0.143773 0
Alpha 1427 Baker Hughes Biocide Listed with other chemicals NA 0 0.00438169 0

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2015-12-08 H2O 0 6337 Bbl 234483 BJ Services Company Status check inspection on the well completion process found Baker Hughes pressure pumping service completing stage # 4 with Bass Well Head company's 10,000 psi rated well head assembly set on top of MiSwaco's B section well sub base assembly. Allied Horizontal wireline service has set a solid completion plug at a measured depth of 18,045' and perforated the well with 60 perforations in 6 clusters between the depths of 18,029' and 17,884'. 1000' gallons of 15% HCL was ran ahead of the stimulat

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2016 ANTERO RESOURCES CORPORATION 3476881 563 292
2017 ANTERO RESOURCES CORPORATION 1463960 282 364
2018 ANTERO RESOURCES CORPORATION 708075 288 363
2019 ANTERO RESOURCES CORPORATION 133077 101 90

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2016 ANTERO RESOURCES CORPORATION Brine 33009 292
2017 ANTERO RESOURCES CORPORATION Brine 10973 364
2018 ANTERO RESOURCES CORPORATION Brine 6307 363
2019 ANTERO RESOURCES CORPORATION Brine 1273 90

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1064890679 2017-8-25 0:00: PL No Violations 0.50
-1991793808 2018-3-7 0:00:0 PW No Violations 0.20
-2047996698 2018-3-7 0:00:0 PW No Violations 0.50
-69877607 2015-12-8 0:00: CT No Violations 2.50
-796029 2014-12-30 0:00 CS No Violations 1.50
0000796029 2014-12-30 Casing String Witnessed No Violations 12/30/14 Dallas Morris rig # 24 is now on the hole and has drilled a 24 x 401 surface casing borehole and ran 399 of 18.626 surface casing with Inspector Eric Conrad to witness the surface cement job with Allied cement services to cement the casing using 801 sacks of class A 2% calcium .125 pps flowseal 100% open hole cement excess, 25 bbl 6% gel ran ahead.
0069877607 2015-12-08 Completion Testing No Violations Status check inspection on the well completion process found Baker Hughes pressure pumping service completing stage # 4 with Bass Well Head companys 10,000 psi rated well head assembly set on top of MiSwacos B section well sub base assembly. Allied Horizontal wireline service has set a solid completion plug at a measured depth of 18,045 and perforated the well with 60 perforations in 6 clusters between the depths of 18,029 and 17,884. 1000 gallons of 15% HCL was ran ahead of the stimulation process.
0281061350 2015-11-09 Preliminary Restoration No Violations Preliminary Restoration status check inspection fount the area affected by the well pad construction has been restored with proper erosion and vegetation control in place. Addressing the well status-the drilling process is now complete and the well is awaiting stimulation. A total of 8-400 barrel production tanks are in place inside a poly lined metal containment dike area. A total of 5 gas process separation units are in place to support each of the 5 existing wells on the pad.
0602722632 2019-01-24 Production Wells No Violations On this day, I found the pad gated with signage at the entrance. There are (5) producing wells, (1) additional well that has had only the conductor drilled and set, (5) gas processing units (GPU), (8) 400-barrel steel production tanks within polymer lined steel containment, and an Emergency Shutdown (ESD) button is present at the pad entrance. Additionally, concrete barriers surround the perimeter of the wellheads. Identification and annular pressure monitoring devices are present. The 9.625 inch diameter intermediate casing has a pressure of 0 pounds per square inch (psi), and the 13.375 inch diameter surface casing has a pressure of 100 psi.
1064890679 2017-08-25 Preliminary Restoration No Violations Preliminary Restoration status check inspection found the area affected by the well pad construction meets ORC 1509.072 with vegetation established and erosion control in place. The lease road is gated and identification signs are in place. There is emergency shut down devices at the well pad entry point and tank battery and also at the electrical service point for the gas processing units. The well is equipped with a casing and tubing head with flow lines attached to each well head outlet. A primary master valve is in place on the tubing head with (2) master valves present down stream in the production flow line. The casing head also has (2) master valves present. A gas processing unit is present on the well pad along with units supporting the other 4 wells on the pad. At the production facility a total of (8) steel construction 400 barrel capacity tanks are present inside a polymer lines steel containment dike area. Proper well head identification is posted at each well. Annular pressure monitoring gauges are present showing 1200 psi on the 9.625 diameter casing annulus and 100 psi on the 13.375 . Doug Stebbins with Antero was notified.
1286566636 2020-3-31 0:00: PW No Violations 1.00
1417374387 2014-11-30 Casing String Witnessed No Violations The said well was spudded on 11/29/14 by Express Energys top hole rig with a 100 x 32 conductor borehole being drilled with the fresh water strata encountered at 76. 11/30/14-100 of 26 weld connection conductor was set and cemented by Express Energys cement service using 330 sacks of class A 2% calcium .25pps flake cement with 100% open hole cement excess ran and the cement displaced with 67 barrels of fresh water and good cement returns to surface. The cement mix water was tested for PH & Chlorides.
1419790904 2014-12-28 Drill / Deepen / Reopen No Violations Status check inspection on the drilling process found Dallas Morris rig # 24 skidding onto the well bore with the conductor casing previously set, they shall spud their surface borehole in the next 12 hours.
1419968094 2014-12-30 Casing String Witnessed No Violations I am onsite to witness the surface casing installation and cementing operations. Dallas Morris Rig 24 drilled 401 of 24 diameter hole. The rig crew then installed 400 of J-55 18.625 casing with a Texas shoe and a float collar. I performed a test of the cement mix water with a low range Quantab, the test indicated that the total dissolved chlorides were present at a concentration of 91 parts per million. Allied Oil and Gas Services pumped 801 sacks of class A cement with .125 pounds per sack flowseal and 2% CaCl into the casing with 50 barrels of the cement circulating back to surface. The plug was landed and the casing integrity test passed with no bleed off.
1420422767 2015-01-04 Drill / Deepen / Reopen No Violations Status check inspection of the drilling process found Dallas Morris rig # 24 on the hole with the 13.375 1st intermediate casing being set to a depth of 2,254 and cemented by Allied Cement service with good cement returns documented to surface. The rig is currently installing the Blow Out Preventer.
1441984988 2015-09-11 Drill / Deepen / Reopen No Violations
1455719344 2016-02-17 Completion Testing No Violations
1678745093 2015-09-15 Drill / Deepen / Reopen No Violations Status check inspection on the well drilling process found Patterson drilling rig 342 on location. It was reported by the company man on site that the 8.750 production borehole formation integrity test did not meet their breakdown requirement and they were preparing to spot a 37 barrel -205 sack Class G plug at a depth of 7,619. The plug will be spotted through the 5 drill string.
1991793808 2018-03-07 Production Wells No Violations On this day, I accompanied ODNR Inspector William Stolarik to witness a controlled annular pressure release of permit number 2-4551, into a tank. Please refer to his comments for a detailed report. We spoke with Antero company man Doug Stebbens about the process. The well is equipped with annular pressure monitoring devices. Concrete barriers surround the wellheads. The facility is gated with an electronic shutdown button on the left-hand side, prior to the pad. The front of the pad is equipped with (8) 400 barrel steel tanks within containment. There are (5) gas processing units along the back of the pad, and a midstream facility along the left side.
2047996698 2018-03-07 Production Wells No Violations On site inspection along with ODNR Inspector Tom Thomas and Antero employee Doug Stebbins. The intention of the inspection is to discuss and review annular pressures. The said well was observed to be in production and to have annular pressure gauges present on the 13.375 casing well head section and 9.625 casing well head section. The pressure between the internal of the 13.375 and external of the 9.625 was 125 psi. The pressure between the internal of the 9.625 diameter casing and the external of the 5.5 diameter production casing is 1,500 psi. I have asked the company to address the 1,500 psi on the 9.625 well head section and record the time it takes to blead the pressure off to a static level. The company will monitor and record the pressure every 24 hours in the proceeding days.
281061350 2015-11-9 0:00: PL No Violations
602722632 2019-1-24 0:00: PW No Violations 0.20

For data sources see[10]

References