Well Details

Well ID: 34-121-24536
Loading map...
Country: United States
State: Ohio
County: Noble
Municipality: Seneca Township
Operator Name: ANTERO RESOURCES CORPORATION
Well Pad ID: US-OH-001048
Farm/Lease Name: WALSH UNIT
License Status: Producing
License Date: 2016-12-14
Spud Date: 2014-10-05
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2017-02-20
Well Total Depth: 18980.00 ft
Configuration: Horizontal
Latitude: 39.860000
Longitude: -81.370000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-09-24 Proposed Formations:POINT PLEASANT, Issued Date:9/24/2014, Expired Date:9/23/2016 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
APP 2016-08-31 Proposed Formations:POINT PLEASANT, Issued Date:8/31/2016, Expired Date:8/31/2018 12:00:00 PM, Drilling unit acres:620.667, Proposed Well Type:OG, Proposed Well Class:POOL
APP 2016-12-14 Proposed Formations:POINT PLEASANT, Issued Date:12/14/2016, Expired Date:12/14/2018 12:00:00 PM, Drilling unit acres:499.234, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2017-02-20 CHANGED STATUS TO DRILLED PER COMPLETION, PREV STATUS DATE 10/05/2014-ALE
Correction to Well 2017-04-21 UPDATE TARGET/TAKEPOINT PER AS-DRILLED PLAT RCVD 3-28-17 ALE
Completion Report Received 2018-01-29 CHANGED STATUS TO DRILLED PER COMPLETION, PREV STATUS DATE 10/05/2014-ALE
Record Last Modified 2018-02-09 CHANGED STATUS TO DRILLED PER COMPLETION, PREV STATUS DATE 10/05/2014-ALE
Construction Permit Expires 2018-12-14 CHANGED STATUS TO DRILLED PER COMPLETION, PREV STATUS DATE 10/05/2014-ALE

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2018-02-08 8014 8184 48
2018-02-08 18691 18861 48
18691 18861 48
8014 8184 48
8014 8184 48

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 11/11/2017 12/07/2017 7991 17,131,700.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 WFRA-405 U.S. Well Services, LLC Friction Reducer Hydrated light distillate (petroleum) 64742-47-8 30 0.019115 31603.4
2-Propenoic acid, polymer with 2 propenamide 9003-06-9 30 0.023746 39258.9
HCL Acid (12.6%-17.5%) U.S. Well Services, LLC Bulk Acid Hydrogen Chloride 7647-01-0 17.5 0.030977 51213.9
Water 7732-18-5 87.4 0.133234 220277
Sand U.S. Well Services, LLC Proppant Crystalline Silica, quartz 14808-60-7 100 13.2721 21,942,800.0
Bioclear 2000 U.S. Well Services, LLC Anti-Bacterial Agent 2,2-dibromo-3-nitrilopropionamide 10222-01-2 20 0.003731 6169.2
Deionized Water 7732-18-5 28 0.002131 3523.82
Water Antero Resources Carrier/Base Fluid Water 7732-18-5 100 86.42 142,878,000.0
SI-1200s U.S. Well Services, LLC Scale Inhibitor Proprietary Scale Inhibitor Proprietary 10 0.001228 2030.29
LGC-15 U.S. Well Services, LLC Gelling Agents Suspending agent (solid) 14808-60-7 3 0.006493 10734.2
Petroleum Distillates 64742-47-8 60 0.040204 66469.7
Guar Gum 9000-30-0 50 0.042452 70185.4
Surfactant 68439-51-0 3 0.002547 4211.12
AI-303 U.S. Well Services, LLC Acid Corrosion Inhibitors Acetophenone,thiourea,formaldehyde polymer 68527-49-1 5 0.00000400 6.672
Formic acid 64-18-6 20 0.00001600 26.688
Butyl cellosolve 111-76-2 20 0.00001500 24.0459
Ethylene glycol 107-21-1 40 0.00004600 76.3277
Polyether 60828-78-6 10 0.00000800 13.344
Cinnamaldehyde 104-55-2 20 0.00001700 27.5954
AP One U.S. Well Services, LLC Gel Breakers Ammonium Persulfate 7727-54-0 100 0.001922 3177

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2017-12-07 H2O 15 7212 Bbl 410940 US Well Services Inc STAGE 54/54

STAGES 2-53 SEE IMAGES

2017-11-11 H2O 15 7758 Bbl 407700 US Well Services Inc STAGE 1/54

STAGES 2-53 SEE IMAGES

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 ANTERO RESOURCES CORPORATION 2855204 58939 343
2019 ANTERO RESOURCES CORPORATION 454298 2257 90

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 ANTERO RESOURCES CORPORATION Brine 32867 343
2019 ANTERO RESOURCES CORPORATION Brine 2846 90

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-106639044 2019-9-18 0:00: PW No Violations 0.80
-1235053600 2016-12-29 0:00 DD No Violations 14.00
-1349022465 2019-8-13 0:00: PW No Violations 0.50
-1356008005 2017-6-6 0:00:0 CT No Violations 1.00
-1978801867 2017-1-3 0:00:0 DD No Violations 2.00
-436966355 2018-1-9 0:00:0 CT No Violations 0.50
0219375631 2017-03-23 Preliminary Restoration No Violations The pad is named Bond and it consists of 8 wells. The purpose of my inspection was a preliminary restoration. During my inspection Antero was on location with contractors present to nipple up the wellhead and get it tied into production lines. The area affected by the well pad construction has all been restored. There are no slips or erosion issues on location. The production equipment on the pad consisted of eight gas production units, fifteen 400 barrel tanks, two compressors, and two combustors. Location has met 1509.072 A requirements.
0225054796 2018-03-28 Production Wells No Violations At 3:28 p.m. on 3/27/18 Antero Resources Production Supervisor Doug Stubbins called and reported some electrical issues that they were having with their combustor. Mr. Stubbins stated that the electric cable on the combustor burnt up and caused small flame that was extinguished immediately. The pad is named Bond and it consists of 9 wells. The purpose of my inspection was a status check. During my inspection the well was equipped with a production tree style wellhead with valves in the open position. Pressure monitoring was present on all casing strings. The production equipment consisted of nine gas production units, fifteen 400 barrel tanks, two compressors, and four combustors. Identification was present and production records were current. Antero well tender was on location.
0436966355 2018-01-09 Completion Testing No Violations The pad is named Bond and it consists of 9 wells. The purpose of my inspection was a status check. During my inspection Fortis Energy Services was on location with their service rig drilling out frac plugs on the Iles 2H, 3412124540. This well was equipped with a production tree style wellhead with valves in the closed position. Frac plugs have recently been drilled out and the well is prepared to be flowed back. The production equipment consisted of nine gas production units, fifteen 400 barrel tanks, two compressors, and four combustors.
1235053600 2016-12-29 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed that Patterson UTI Rig #342 had drilled a 24 inch diameter hole to the depth of 367 feet. Wyoming Casing Crew ran 375 feet of 18.625 inch 87.5 pound per foot J-55 casing 10.5 feet above KB which is 25 feet washing down the last 2 joints of casing. Patterson UTI Drilling Rig #342 could not get their landing joint to mate up and replaced it with a full joint of casing. Schlumberger Services was on site loaded their lines with 5 barrels of fresh water, performed a low pressure test at 500 pounds per square inch and performed a high pressure test at 2000 pounds per square inch then gained circulation with 170 barrels of fresh water. Schlumberger cemented the casing with 660 sacks of Class A cement weighing 15.6 pounds per gallon and a yield of 1.2 cubic foot per sack cement. Cement additives included 2% Calcium Chloride and 0.2% B495A. Cement weight was verified by pressurized mud scales. Cement was displaced with 101 barrels of fresh water. Had good cement returns of 34 barrels, plug was landed at 209 pounds per square inch, pressured to 724 pounds per square inch for 5 minutes and the floats held with 1 barrel back. Mix water was tested revealing chlorides of 32 parts per million, pH 7 and 55 degrees. Simultaneous operation was taking place with the drilling of the said well and 4 wells producing on the pad.
1260405218 2017-01-06 Drill / Deepen / Reopen No Violations On the day of my inspection Patterson UTI Drilling Rig #342 had reached total depth on the second intermediate section at 7168 feet and washing down their 9.625 inch diameter 40 pound per foot landing joint of casing. Casing will be landed out at 7153 feet with Schlumberger onsite beginning to rig up and preparing to cement the casing. Upon completion Patterson UTI Rig #342 will walk over and re-spud the 34121245370000 Walsh Unit East 1H.
1356008005 2017-06-06 Completion Testing No Violations The pad is named Bond and it consists of 9 wells. The purpose of my inspection was a status check. During my inspection the well was equipped with a Frac valve. The production equipment on the pad consisted of nine gas production units, fifteen 400 barrel tanks, two compressors, and four combustors. Containment was present on the pad with sound walls surrounding the pad as Antero prepares the location for Hydraulic Fracturing operations on the 5 of wells.
1978801867 2017-01-03 Drill / Deepen / Reopen No Violations
219375631 2017-3-23 0:00: PL No Violations 0.50
225054796 2018-3-28 0:00: PW No Violations 0.20

For data sources see[10]