Well Details

Well ID: 34-155-24048
Loading map...
Country: United States
State: Ohio
County: Trumbull
Municipality: Hubbard Township
Operator Name: PAC DRILLING LLC
Well Pad ID:
Farm/Lease Name: EVANS
License Status: Producing
License Date: 2011-12-29
Spud Date: 2012-01-04
Spud Drilling Contractor: G & H DRLG
Final Drill Date: 2012-01-14
Well Total Depth: 5384.00 ft
Configuration: Vertical
Latitude: 41.190000
Longitude: -80.550000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2011-12-29 Proposed Formations:CLINTON & MEDINA, Issued Date:12/29/2011, Expired Date:12/28/2013 12:00:00 PM, Drilling unit acres:40.82, Proposed Well Type:OG, Proposed Well Class:POOL
Correction to Well 2012-01-13 CORRECTION TO FOOTAGE, SHOULD BE "520'NL & 675'EL OF LOT 14".
Reached Total Depth 2012-01-14
Completion Report Received 2012-06-21
Construction Permit Expires 2012-12-28
Record Last Modified 2017-10-24

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2012-07-19 5134 5140 6
2012-07-19 5107 5110 5
5107 5110 5
5134 5140 6
5143 5151 10
5194 5200 8
5107 5110 5
2012-07-19 5194 5200 8
2012-07-19 5143 5151 10

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2012-01-19 H2O 0 131055 Gal 0 Universal Well Services Inc. 500 sacks of sand

No problems were encountered.

2012-01-19 H2O 20 131055 Gal 50000 Universal Well Services Inc.

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2001 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2002 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2003 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2004 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2006 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2007 OHIO VALLEY ENERGY SYSTEMS COR 0.00 5.00 0
2010 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2011 OHIO VALLEY ENERGY SYSTEMS COR 0.00 0.00 0
2012 PAC DRILLING LLC 10331.00 649.00 231
2013 PAC DRILLING LLC 14057.00 304.00 365
2014 PAC DRILLING LLC 12178.00 256.00 360
2015 PAC DRILLING LLC 10606.00 187.00 360
2016 PAC DRILLING LLC 7751.00 146.00 359
2017 PAC DRILLING LLC 6466.00 141.00 359
2018 PAC DRILLING LLC 6284.00 54.00 359

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2001 OHIO VALLEY ENERGY SYSTEMS COR Brine 0
2002 OHIO VALLEY ENERGY SYSTEMS COR Brine 0 0
2003 OHIO VALLEY ENERGY SYSTEMS COR Brine 0 0
2004 OHIO VALLEY ENERGY SYSTEMS COR Brine 0
2006 OHIO VALLEY ENERGY SYSTEMS COR Brine 0 0
2007 OHIO VALLEY ENERGY SYSTEMS COR Brine 0 0
2010 OHIO VALLEY ENERGY SYSTEMS COR Brine 0 0
2011 OHIO VALLEY ENERGY SYSTEMS COR Brine 0 0
2012 PAC DRILLING LLC Brine 309 231
2013 PAC DRILLING LLC Brine 25 365
2014 PAC DRILLING LLC Brine 43 360
2015 PAC DRILLING LLC Brine 53 360
2016 PAC DRILLING LLC Brine 0 359
2017 PAC DRILLING LLC Brine 0 359
2018 PAC DRILLING LLC Brine 0 359

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1613459289 2013-5-29 0:00: UL No Violations 0.50
-1658138114 2012-1-4 0:00:0 UD No Violations
-1717805094 2012-1-26 0:00: UD No Violations
-1875853359 2018-5-21 0:00: UP No Violations
-943557028 2012-1-12 0:00: UD No Violations
0368684579 2012-01-09 Urban Drill / Deepen / Reopen No Violations The rig was drilling on fluid at 3965 feet. There were no violations.
0943557028 2012-01-12 Urban Drill / Deepen / Reopen No Violations The rig was drilling on fluid at 5157. There were no violations.
1321001453 2012-02-03 Urban Drill / Deepen / Reopen No Violations The pits have been closed. There were no violations at the time of inspection.
1326985970 2012-01-19 Urban Drill / Deepen / Reopen No Violations The well stimulation operation was witnessed. All conditions were acceptable.
1327516945 2012-01-04 Urban Drill / Deepen / Reopen No Violations The drilling contractor was moving on location. All conditions were acceptable.
1610217442 2017-04-10 UrbanProduction Wells No Violations

-up lines have plugs and the ball valve handles have been removed. The 210 bbl. storage tank has the required urban safety equipment. An identification sign is posted at the tank battery. The identification sign is missing the required information per 1501:9-9-05(E)(1)(a--site inspection. The well is located in a clearing surrounded by woodlands. The access road is in good repair with no gate at the entrance. The access road gate was not waived during the pre-site inspection.

The equipment on the pad consists of the following:



1613459289 2013-05-29 UrbanPreliminary Restoration No Violations My inspection found the well in production. The well was equipped with a plunger lift unit and a domestic gas line. The tank battery contained one, 210 barrel production tank, one, 50 barrel brine tank, and a separator. It was surrounded by a locked chain link fence and the proper dike capable of meeting containment requirements. There was a plug on the load line. The proper safety equipment was installed on the production tank. An identification sign was properly posted at the wellhead and tank battery. There was a 7 day production chart at the separator. The site was graded and vegetated. All drainage and erosion controls were in place and working properly. The lease road was in good condition.
1658138114 2012-01-04 Urban Drill / Deepen / Reopen No Violations The rig drilled an 11 borehole to 630 and ran 593 of new 8.675 casing. This casing was cemented with 125 sacks of light cement and 100 sacks of Class A cement which was circulated to surface with 27 barrels of returns. The cement operation and site conditions were acceptable.
1684652807 2019-03-08 UrbanProduction Wells No Violations I conducted a compliance notice follow-up for compliance notice 1875853359, regarding multiple compliance issues related to urban rule requirements. At the time of this inspection, the identification located at the tank battery has been amended with the required information per 1501:9-9-05E(1)(a-e). There was a locked chain link fence surrounding the tank battery without the 3 strand barb wire, which needs to be added to the top of the fence. The production tank was over 3 foot above the top of the fence and needs to meet requirements per 1501:9-9-05E(4)(f). The access road gate was not waived during the pre-site inspection and has not been installed. Install the access gate with a lock and identification.

PAC needs to: 1) Raise the fencing around the tank battery or use low profile tanks as required by 1501:9-9-05E(4)(f). 2) Install the required gate with a lock at the access road entrance per 1501:9-9-05(E)(2)(c). 3) Post the proper identification sign on the access road gate per 1501:9-9-05E(1)(f).

1717805094 2012-01-26 Urban Drill / Deepen / Reopen No Violations Chem Tech delivered two truck loads of dust and the pits were solidified. All conditions were acceptable.
1748149288 2012-01-14 Urban Drill / Deepen / Reopen No Violations The rig installed 5054 of 4.5 production casing and cemented it with 200 sacks of Unitropic cement. Cement operation and well site conditions were acceptable.
1875853359 2018-05-21 UrbanProduction Wells Violations Noted At the time of this inspection, the well was equipped with a plunger lift assembly. The annulus and flow line valves were open. A domestic gas supply comes off of the wellhead with an open 2 inch valve, open 1 inch valve, a gas meter, a drip tank, and regulator. An identification sign was posted at the well. The diked tank battery has two storage tanks and a separator. The pick-up lines have plugs and the valve handles have been removed. The 210 BBL storage tank has the required urban safety equipment. An identification sign was posted at the tank battery. The identification sign was missing the required information per 1501:9-9--e). There was a danger, keep out and no smoking sign(s) posted. There was a locked chain link fence surrounding the tank battery. The 3 strand barb wire needed to be added to the top of the fence. The production tank was over 3 foot above the top of the fence and needs to meet requirements per 1501:9-9--site inspection. The access road was stable with no gate at the entrance. The access road gate was not waived during the pre-site inspection and has not been installed.
368684579 2012-1-9 0:00:0 UD No Violations
734619632 2020-3-27 0:00: UP No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1875853359 US-OH-118815 2018-05-25 9-05E1 ID (a-i)
1875853359 US-OH-118816 2018-05-25 9-05E2 FENCING (a-d)
1875853359 US-OH-118817 2018-05-25 9-05E4 TANKS (a-i)
1875853359 US-OH-118818 2018-05-25 9-9-02 General Safety