34-155-24101

Well Details

Well ID: 34-155-24101
Loading map...
Country: United States
State: Ohio
County: Trumbull
Municipality: Bristol Township
Operator Name: US ENERGY OH LLC
Well Pad ID:
Farm/Lease Name: WILLIAMS UNIT
License Status: Producing
License Date: 2017-08-01
Spud Date: 2017-08-10
Spud Drilling Contractor: US ENERGY DRILLING LLC
Final Drill Date: 2017-08-30
Well Total Depth: 6128.00 ft
Configuration: Horizontal
Latitude: 41.410000
Longitude: -80.880000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2017-08-01 Proposed Formations:CLINTON, Issued Date:8/1/2017, Expired Date:8/1/2019 12:00:00 PM, Drilling unit acres:125.11, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2017-08-30
Completion Report Received 2019-02-05
Record Last Modified 2019-05-23
Construction Permit Expires 2019-08-01

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2019-03-08 5900 5960 0
5900 5960 0
5900 5960 0

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 US ENERGY OH LLC 0.00 4089.00 334

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 US ENERGY OH LLC Brine 7344 334

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1196832487 2018-9-18 0:00: PL No Violations 0.50
-1590553631 2020-1-27 0:00: PW No Violations 0.60
-1688168057 2018-2-26 0:00: PW No Violations
-1935145145 2017-8-9 0:00:0 DD No Violations 2.60
-1963478158 2017-8-30 0:00: DD No Violations 5.00
-599845139 2018-8-7 0:00:0 PL No Violations 0.60
-80135713 2017-8-28 0:00: DD No Violations 1.00
-959919975 2017-8-14 0:00: CS No Violations 2.80
0080135713 2017-08-28 Drill / Deepen / Reopen No Violations
0298326458 2017-08-22 Drill / Deepen / Reopen No Violations U S Energy Rig # 9 was slide drilling a 6.25 borehole at 3637 MD on misted air. A walk around inspection reviewed the pits ( adequate room ) backyard ( no contamination observed ) and the cellar ( slight gas migration was observed between the 13.375 and 9.625 casings ). A gas detector, on the Pason, indicated a show ( 21 units ) below the top of the Lockport Dolomite ( top @ 3312 MD ). There was not any indication of H2S. Erosion controls were in place and effective. No violations identified during this inspection.
0345368989 2017-08-21 Drill / Deepen / Reopen No Violations Peck Leach Rd. west from Rt. 45. Take second road on the left which is Messick Rd. Access road is on the right ~ 0.5 miles.
0599845139 2018-08-07 Preliminary Restoration No Violations I was on location to check the status of Preliminary Restoration of this horizontal, Clinton Sandstone well. My inspection found the lease road and well pad in stable condition. The well is in production and equipped with 2.375 tubing and rods and operating with the aid of an electric powered pumping unit. Gauges indicate pressures of 340psi on the tubing and 570psi on the 4.5 production casing. The stuffing box is equipped with a pumpkin containment system and the containment hood is plumbed to a 55 gallon drum. The casing flow line is equipped with a line heater and the annulus between the 7 intermediate casing and 4.5 production casing is equipped with a 250psi pressure relief valve. The tank battery is diked and contains three (3) 210 barrel tanks and the separator is located in a separate containment area east of the tanks. All of the load lines are locked. There is an electric pump in the northwest corner of the battery that is plumbed to the load lines, the top of the western tank, and to the top of a 500 barrel frac tank that is sitting outside of containment. The fluid level in the frac tank is 4. Vegetation is well established around the perimeter of the pad and the required identification is posted at the wellhead and at the tank battery. I will speak with U.S. Energy about the status of the 500 barrel tank prior to approving Preliminary Restoration. If the tank will be permanent, secondary containment measures will need to be installed around the tank. No violations.
0959919975 2017-08-14 Casing String Witnessed No Violations I was on location to witness the cementing of the 9.625 surface casing. US Energy drilled a 12.25 hole to a depth of 336 measured from the Kelly bushing (KB +10) and set 26lb/ft., ASTM, A500 casing at a depth of 326 KB with a 7 shoe on bottom. Petroset Cementing rigged up and broke circulation with 30 barrels of freshwater and then mixed and pumped 200lbs of bentonite gel with 40lbs of cottonseed hulls to condition the hole. They then mixed and pumped 31.5 barrels (150 sacks) of Class A cement slurry with 3% calcium chloride. The cement was scaled at 15.6lbs/gallon midway through mixing. The plug was released from the head and displaced to 326 with 26.5 barrels of freshwater and landed in the shoe at 500psi. The pressure was released and the cement held at the surface. I witnessed 5-6 barrels of good cement return to the surface. Mix water pH was 7 and the water temperature was 70 degrees. US Energy will wait 8 hours before breaking off and continuing operations. I found no violations at this time.
1070561997 2017-08-11 Drill / Deepen / Reopen No Violations I inspected this location with District Supervisor Steve Ochs. US Energy spudded this well on 8/10/17 and set 56 of 13.375 conductor casing this morning. I retrieved the cement ticket from the doghouse and inspected the casing string below the rig floor. Rig #9 is currently waiting on cement prior to drilling out below the casing shoe. The location was inspected and the pits were found to be lined with minimal fluid in the pits at this time. We met with Cub (US Energy) and he said there were no issues with the conductor casing cement job. He informed me that the rig would be shutting down for the weekend and that they would begin drilling the surface hole early Monday morning (8/14/17). I found no violations at this time.
1196832487 2018-09-18 Preliminary Restoration No Violations Status check inspection for Preliminary Restoration. My inspection found the lease road and pad in stable condition. The wellhead is equipped with 2.375 rods and tubing and operating with the aid of an electric powered pumping unit. The stuffing box is equipped with a pumpkin containment system and the containment hood is plumbed to a 55 gallon drum. The casing flow line is equipped with a line heater and the annulus between the 7 intermediate casing and 4.5 production casing is equipped with a 250psi pressure relief valve. Gauges indicate a pressure of 250psi on the tubing and 500psi on the 4.5 production casing. This well produces to a diked tank battery shared with the Williams Unit 2H (PN#24102) and contains three (3) 210 barrel tanks. There is a heat treating, horizontal separator 50 to the east of the tanks and is surrounded by a secondary containment dike. There is a contract pumper currently on location (Tim) and he is transferring production water to a 500 barrel steel tank. I spoke with the U.S. Energy Field Supervisor (Kerry) about the 500 barrel tank and he said that the tank is not permanent and will be removed when they get ahead of the production water. Valves at the wellhead and on the load lines are equipped with locks. Vegetation is well established around the perimeter of the pad and the required identification is posted at the wellhead and at the tank battery. No violations. Preliminary Restoration is approved.
1503579532 2017-08-23 Drill / Deepen / Reopen No Violations
1503928470 2017-08-28 Drill / Deepen / Reopen No Violations U S Energy Rig # 9 was rotate drilling the lateral section of the wellbore on fluid. Drilling depth was 5647 MD. The curve was landed at 4196 MD. The gas bubbling previously observed in the 9.625 casing to 7 casing annulus have subsided greatly. I observed the pits, mud pump and general drilling operations and did not identify any violations during this inspection.
1504022560 2017-08-15 Drill / Deepen / Reopen No Violations
1509370924 2017-10-30 Drill / Deepen / Reopen No Violations
1516197442 2018-01-17 Preliminary Restoration No Violations The lease road was graveled and allowed access to the well pad. The drilling pits were closed. The top soil remained in a pile on the east side of the pad. Weather permitting the top soil will be spread as soon as possible. The well was equipped to operate as a pumping well. Visible well construction included 7 intermediate casing, 4.5 inch production casing and 2.375 inch tubing with rods. The annular space between the 7 inch and 4.5 casings was open and free of any gas migration indications. I will contact Cary LeShock ( U S Energy ) concerning the installation of the pressure relief valve on the production - intermediate annulus. All the valves on the wellhead were locked. Three 210 barrel stock tanks were on location, but the tank battery construction had not began. No violations were identified during this inspection.
1688168057 2018-02-26 Production Wells No Violations The lease road and location was rocked and offered adequate access to the well and tank battery. The Williams # 1-H well was equipped to produce as an electric pumping well. The well was equipped with a Oilwell Model 114 pumping unit. The I D information was handwritten on the unit. There was a 55 gallon waste barrel to contain any fluids captured from the leak containment pumpkin on the stuffing box. The 7 to 4.5 annulus had a manifold that included a pop off valve and gauge. The gauge read zero psi. The tank battery consisted of three (3) 210 barrel stock tanks and one (1) Gas Production Unit ( GPU ). An earthen dike surrounded the tank battery. The preliminary restoration has not been completed due to weather considerations. No violations identified during this inspection.
1935145145 2017-08-09 Drill / Deepen / Reopen No Violations I was on location to check the rig up of US Energy Rig #9. I met with Jim Stanley (Petrox) and Cub, the tool pusher for US Energy. The rig is spotted and ancillary equipment is currently being moved into position for drilling operations. US Energy is hoping to spud the well some time tomorrow (8/10/17). The drilling pits have been lined and the location is in good condition. I found no violations at this time.
1963478158 2017-08-30 Drill / Deepen / Reopen No Violations
298326458 2017-8-22 0:00: DD No Violations
345368989 2017-8-21 0:00: DD No Violations 0.70

For data sources see[8]

References