34-169-25688

Well Details

Well ID: 34-169-25688
Loading map...
Country: United States
State: Ohio
County: Wayne
Municipality: Paint Township
Operator Name: HG ENERGY LLC
Well Pad ID:
Farm/Lease Name: NUSSBAUM GORDON & MAJORIE
License Status: Plugged and Abandoned
License Date: 2020-03-06
Spud Date: 2017-12-27
Spud Drilling Contractor:
Final Drill Date: 2018-01-24
Well Total Depth: 6474.00 ft
Configuration: Vertical
Latitude: 40.710000
Longitude: -81.720000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2017-09-13 Proposed Formations:ROSE RUN, Issued Date:9/13/2017, Expired Date:9/13/2019 12:00:00 PM, Drilling unit acres:88.932, Proposed Well Type:OG, Proposed Well Class:EOUT
Reached Total Depth 2018-01-24 WELL DRILLED, NOT YET PUT INTO PRODUCTION
Record Last Modified 2019-04-05 WELL DRILLED, NOT YET PUT INTO PRODUCTION
Construction Permit Expires 2019-09-13 WELL DRILLED, NOT YET PUT INTO PRODUCTION

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2018-03-29 6284 6300 64
6284 6300 64
6284 6300 64

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2018-02-13 ACID 15 3435 Gal 0
2018-02-13 ACID 0 3000 Gal 0 Producers Service Corporation Arrived on location on 02/13/2018 to witness completion operations at the Nussbaum #BG-03 well. Hagen Well Service was rigged-up onsite. Thawed-out the rig, and pulled one joint of tubing (due to a tally miscalculation). Rigged up Producers Service Corp., and spotted 3,000 gal of 15% HCl. Formation broke down at ~1,364 psi. No problems were noted during completions operations.

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 HG ENERGY LLC 70481.00 331.00 162

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 HG ENERGY LLC Brine 27 162

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1224642662 2019-7-5 0:00:0 PW No Violations
-1478828905 2020-4-9 0:00:0 PB No Violations
-1534673444 2018-1-19 0:00: DD No Violations
-1538310764 2018-1-12 0:00: DD No Violations
-1724425952 2018-4-2 0:00:0 PL No Violations
-1941127294 2018-1-22 0:00: DD No Violations
-504754481 2018-2-6 0:00:0 CT No Violations
-956654465 2020-3-20 0:00: PB No Violations
0215272127 2018-01-10 Casing String Witnessed No Violations Arrived on location on 01/10/2018 to witness the pressure test on the surface casing. Waited on rig to remove the landing joint and cut-off the conductor casing prior to the test. Pressured the well up to 500#, but the test failed due to leaking connections above-ground. Pressured the well up to 550#, but the test failed again due to leaking around the swedge threads. Tightened up all connections, and pressured the well up to 500# at 2:03PM. At 2:33PM, the pressure had dropped to 450#. As the pressure lost did not exceed 10%, the test passes.
0382842333 2017-12-28 Casing String Witnessed No Violations Arrived on location on 12/28/2017 to witness the spudding and drilling/casing of the well. HAD Rig #618 was rigged-up onsite, and concentrically drilling and casing the conductor hole. 77 of 16 casing was set in a hard gray shale.
0504754481 2018-02-06 Completion Testing No Violations Arrived on location on 02/06/2018 to witness the cement bond log and perforation job on the well. Waited on rig crew to arrive, then rigged up Appalachian Well Surveys and began running downhole with logging tools. The top of the production casing cement was noted at ~5,140, which is more than 1,000 from the top of the planned perforations. Good cement coverage was noted from TD to 5,140. Tripped out and laid down logging tools, prepared the perforation gun (16 hollow-body gun with 4-shots per foot), and ran downhole. The well was perforated from 6,284-6,300 with 4-shots per foot. Slowly pulled the gun from the well to avoid swabbing it, then rigged down and moved out Appalachian Well Surveys. Hagen Well Service will run 2 3/8 upset tubing to 6,319. No problems were noted at the time of the inspection.
0955886889 2018-01-17 Drill / Deepen / Reopen No Violations Visited location on 01/17/2018 to check on the status of drilling operations. Kilbarger Drilling was drilling a 7 7/8 hole at 4,867. No problems were noted at the time of the inspection.
1141831840 2018-04-30 Preliminary Restoration No Violations Visited location on 04/30/2018 to check on the status of reclamation operations. The wellhead has been installed, and the well was shut-in at the time of the inspection. Palmer and Sons Excavating has been working on re-grading the location. No problems were noted at the time of the inspection.
1514296223 2017-12-26 Drill / Deepen / Reopen No Violations Upon arrival on location I found the rig crew has started to move in equipment some of the equipment, the rig is not on location yet.
1516818792 2018-01-24 Drill / Deepen / Reopen No Violations I accompanied Inspector Allie Oprzadek on location for cementing production string. Please refer to her report
1517574748 2018-02-01 Preliminary Restoration No Violations Arrived on location on 02/01/2018 to check on the status of location reclamation. Kilbarger Drilling was rigged down, moved out. S&H is working on emptying pits, and Palmer and Sons Excavating on grading the location in preparation for completion work next week. A night cap has been installed on the well. No problems were noted at the time of the inspection.
1534673444 2018-01-19 Drill / Deepen / Reopen No Violations Visited location on 01/19/2018 to check on the status of drilling operations. The rig was running downhole with drill pipe after a trip to un-clog bit nozzles. No problems were noted at the time of the inspection.
1538310764 2018-01-12 Drill / Deepen / Reopen No Violations Arrived on location on 01/12/2018 to witness the BOP test. Kilbarger Drilling was having problems pressuring the well up past 130#. A problem with the soap pump was discovered. Waited on the rig crew to make repairs. Pressured the well up to 530# at 5:49 AM. At 6:04 AM, the pressure had fallen to 520#. As the pressure lost does not exceed 5%, the test passes.
1539360929 2018-10-09 Preliminary Restoration No Violations Inspected production well on 10/09/2018. The tank battery consists of 1-210 bbl steel tank, located within an earthen dike; 1-horizontal separator with a drip is located within a separate earthen dike nearby. The well is equipped with a threaded wellhead with a flanged master valve, and a flowline; 1-350 gal plastic methanol tank is located nearby. Well identification is clearly displayed at both the tank battery and the wellhead. Pits have been closed, the location restored, and the well placed into production. Preliminary restoration passes.
1568203119 2019-9-9 0:00:0 PW No Violations
1635243521 2018-02-05 Completion Testing No Violations Arrived on location on 02/05/2018 to check on the status of completion operations and discuss the plan forward. Hagen Well Service was rigged-up onsite, and thawing-out the well. They were preparing to swab the freshwater out of the well, and load the hole with saltwater.
1724425952 2018-04-02 Preliminary Restoration No Violations Visited location on 04/02/2018 to check on the status of reclamation. A wellhead has been installed; all valves were noted to be shut-in and locked at the time of the inspection. Pits have been closed and the location rough-graded. Once vegetation has been re-established in the area, the preliminary restoration passes.
1803766717 2018-02-13 Completion Testing No Violations Arrived on location on 02/13/2018 to witness the acid job. Hagen Well Service was on-site and rigged-up. Rigged-up Producers Service Corp. and treated the well with 1,000 gal of 15% HCl. No problems were noted during completion operations.
1941127294 2018-01-22 Drill / Deepen / Reopen No Violations Visited location on 01/22/2018 to check on the status of drilling operations. Kilbarger Drilling was drilling ahead at 6,358.
215272127 2018-1-10 0:00: CS No Violations
382842333 2017-12-28 0:00 CS No Violations
955886889 2018-1-17 0:00: DD No Violations

For data sources see[9]

References