37-005-30888

Well Details

Well ID: 37-005-30888
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: North Buffalo Township
Operator Name: SNYDER BROS INC
Well Pad ID: 146148
Farm/Lease Name: CLEO P CLAYPOOL 3M-277
License Status:
Spud Date:
Permit Date: 2011-11-18
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: Yes
Latitude: 40.786117
Longitude: -79.645578

For data sources see[1][2][3]

Well History

Date Event
2011-11-18 New Permit Application
2012-06-06 Performed Spud Operation
2012-06-12 Drilling Completion
2012-08-13 Perforation
2016-04-29 NEWLY DRILLED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2012-08-15 2012-08-15 6,704 170,292

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Super 100NE Superior Well Services Surfactant/Foamer 2-Butoxyethanol 111-76-2 7.00 0.00679810
Isopropanol 67-63-0 30.00 0.02
SUPER TSC Superior Well Services Scale Control 1,2-Propylene glycol 57-55-6 50.00 0.00170580
1,2,4-Butanetricarboxylic acid, 2-phosphono- 37971-36-1 10.00 0.00034120
ANIONIC COPOLYMER 10.00 0.00034120
ANIONIC POLYMER 10.00 0.00034120
KR-153SL Superior Well Services Biocide Ethylene glycol 107-21-1 1.00 0.00003410
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 20.00 0.00068230
Polyethylene glycol 25322-68-3 50.00 0.00170580
Diethylene glycol 111-46-6 3.50 0.00011940
ICP-1000 Superior Well Services Iron Control Additive 1,2-Propylene glycol 57-55-6 50.00 0.00341160
ANIONIC COPOLYMER 50.00 0.00341160
ACID INHIBITOR 2 Superior Well Services Acid Corrosion Inhibitor Propargyl alcohol 107-19-7 0.00020470
Isopropanol 67-63-0 0.00020470
PROPRIETARY 0.00004780
2-Butoxyethanol 111-76-2 0.00020470
Hydrochloric Acid Superior Well Services Cement/Formation Breakdown Hydrochloric acid 7647-01-0 7.50 0.01
Water 7732-18-5 92.50 0.21
WFR-3B Superior Well Services Friction Reducer Distillates, petroleum, hydrotreated light 64742-47-8 30.00 0.02
Stoddard solvent 8052-41-3 10.00 0.00807410
Ethoxylated C12-16 alcohols 68551-12-2 4.00 0.00322960
1,2-Propylene glycol 57-55-6 25.00 0.02
SUPER TSC Superior Well Services Paraffin & Scale Additive
CLAY TREAT LT Superior Well Services Clay Control Choline chloride 67-48-1 80.00 0.00036390

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2011 SNYDER BROS INC 0.00 0 0.00 0 0.00 0
2012 SNYDER BROS INC 21,636.00 97 0.00 0 0.00 0
2013 SNYDER BROS INC 32,811.00 365 0.00 0 0.00 0
2014 SNYDER BROS INC 21,850.00 365 0.00 0 0.00 0
2015 SNYDER BROS INC 16,585.00 357 0.00 0 0.00 0
2016 SNYDER BROS INC 13,472.00 333 0.00 0 0.00 0
2017 SNYDER BROS INC 10,195.00 356 0.00 0 0.00 0
2018 SNYDER BROS INC 8,248.00 348 0.00 0 0.00 0
2019 SNYDER BROS INC 8,085.00 358 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2012 SNYDER BROS INC Produced Fluid 240.00 Bbl INJECTION DISPOSAL WELL 34-155-21447
2012 SNYDER BROS INC Drill Cuttings 109.00 Tons ON SITE ENCAPSULATION
2012 SNYDER BROS INC Produced Fluid 165.00 Bbl INJECTION DISPOSAL WELL 34-155-21438
2012 SNYDER BROS INC Produced Fluid 83.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2012 SNYDER BROS INC Fracing Fluid Waste 330.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW008
2012 SNYDER BROS INC Fracing Fluid Waste 330.00 Bbl REUSE OTHER THAN ROAD SPREADING
2012 SNYDER BROS INC Fracing Fluid Waste 1,960.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE EPA ID: 748-163
2012 SNYDER BROS INC Drilling Fluid Waste 330.00 Bbl REUSE OTHER THAN ROAD SPREADING
2012 SNYDER BROS INC Drilling Fluid Waste 230.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123SW008
2013 SNYDER BROS INC Produced Fluid 270.00 Bbl INJECTION DISPOSAL WELL 34-155-21438
2014 SNYDER BROS INC Produced Fluid 95.00 Bbl INJECTION DISPOSAL WELL 34-155-23759
2014 SNYDER BROS INC Produced Fluid 93.00 Bbl INJECTION DISPOSAL WELL 34-155-21438
2015 SNYDER BROS INC Produced Fluid 93.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2016 SNYDER BROS INC Produced Fluid 84.00 Bbl REUSE OTHER THAN ROAD SPREADING
2019 SNYDER BROS INC Produced Fluid 90.00 Bbl INJECTION DISPOSAL WELL 34-099-23158

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2048310 Primary Facility 2012-03-06 Routine/Complete Inspection No Violations Noted Site construction had been completed, drilling had not commenced. Erosion controls had been properly as outlined in the E&S plan located onsite. There was no observed acelerated erosion or sedimentation in relation to the access road or well-site.
2061364 Primary Facility 2012-04-20 Routine/Complete Inspection No Violations Noted At the time of inspection the site construction was finished. The drill site and borrow pit were temporarily stabilized with mulch. The BMP's were properly installed as outlined in the E&S plan. The Department suggests the Operator continue to monitor the temporary borrow area to ensure 70% uniform vegetative coverage is achieved. At the time of inspection the site ID sign and drill permit were on site.
2104784 Primary Facility 2012-10-02 Routine/Complete Inspection No Violations Noted Well operating and properly identified.
2174075 Primary Facility 2013-06-11 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tanks located on-site and they appeared to be in sound condition. Site had been properly restored and the vegetation met the 70% uniform coverage criteria. There was no evidence observed of accelerated erosion or sedimentation in relation to the site or access road. It was noted that the field immediately downslope of the well apparatus had been plowed and planeted with corn.
2232599 Primary Facility 2013-12-31 Administrative/File Review Viol(s) Noted & Immediately Corrected No paper inspection report. CACP Enf ID 306998
2262273 Primary Facility 2014-04-14 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. Noted that adjacent to the well apparatus there is a cultivated field. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2487758 Primary Facility 2016-05-26 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production. Brine tanks located onsite and they appeared to be in sound condition. There was no observed accelerated erosion or sedimentation in relation to the site or access road.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2232599 685864 12/31/2013 2013-12-31 OGA 3222(B) - Failure to submit well record / completion report. Administrative

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
685864 306998 CACP - Consent Assessment of Civil Penalty Comply/Closed 2014-01-27 2014-01-27 $500.00 $500.00

For data sources see[8]