37-007-20467

Well Details

Well ID: 37-007-20467
Loading map...
Country: United States
State: Pennsylvania
County: Beaver
Municipality: New Sewickley Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 152367
Farm/Lease Name: PER B11
License Status: Active
Spud Date: 2016-06-30
Permit Date: 2015-03-24
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.734614
Longitude: -80.201377

For data sources see[1][2][3]

Well History

Date Event
2015-03-24 New Permit Application
2015-11-10 New Permit Application
2016-06-29 Performed Spud Operation
2016-07-16 Drilling Completion
2020-01-30 Deviated
2020-01-30 Newly Drilled

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-03-28 2017-04-05 5,167 14,182,500 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 TRS 11800, TRS 3001, EC6111A TightRock Solutions Frac Fluid Additives Sodium Phosphate, Tribasic 7601-54-9 5 0.000371748 515
Glutaraldehyde 111-30-8 30 0.00204209 2829
Amine Triphosphate Proprietary 30 0.00223049 3090
Methanol 67-56-1 1 0.00006857 95
Alkyl Alcohol Proprietary 10 0.00844352 11697.2
Ethylene Glycol 107-21-1 5 0.000371748 515
Inorganic Salt Proprietary 10 0.00844352 11697.2
Oxyalkylated Alcohol Proprietary 5 0.00422176 5848.59
Hydrotreated Light Distillate 64742-47-8 30 0.0253306 35091.6
Hydrochloric Acid (7.5%) Axiall Acidizing Hydrogen Chloride 7647-01-0 40 0.994597 1,377,860.0
Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 86.0471 119,205,000.0
Unihib G GeoSafe Acid Corrosion Inhibitor Glycol Ether 112-34-5 60 0.000668219 925.714
Ethoxylated Alcohol 68002-97-1 35 0.000389795 540
Methanol 67-56-1 5 0.00005568 77.143
Formaldehyde 50-00-0 1 0.00001114 15.429
Acetophenone 98-86-2 1 0.00001114 15.429
Thiourea 62-56-6 1 0.00001114 15.429
Sand (Proppant) Sargent Proppant Silica 14808-60-7 99.9 11.3336 15,700,900.0
Other Chemical(s) Listed Above See Trade Name(s) List Thiourea 62-56-6 1 0.00001114 15.429
Methanol 67-56-1 5 0.00005568 77.143
Ethoxylated Alcohol 68002-97-1 35 0.000389795 540
Formaldehyde 50-00-0 1 0.00001114 15.429
Acetophenone 98-86-2 1 0.00001114 15.429

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2016 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2017 PENNENERGY RESOURCES LLC 568,218.00 190 0.00 0 5,839.00 190
2018 PENNENERGY RESOURCES LLC 924,203.00 355 0.00 0 8,940.00 355
2019 PENNENERGY RESOURCES LLC 751,325.00 305 0.00 0 4,427.00 305

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 2,989.83 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 100.00 Bbl REUSE OTHER THAN ROAD SPREADING
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 2,989.83 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Drill Cuttings 903.50 Tons LANDFILL CID # 28726
2017 PENNENERGY RESOURCES LLC Produced Fluid 55.74 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 21.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC 6.66 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC Produced Fluid 105.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2017 PENNENERGY RESOURCES LLC Drill Cuttings 5.83 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 38.03 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 21.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC Drilling Fluid Waste 137.86 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 9.65 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC Servicing Fluid 19.71 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 105.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2017 PENNENERGY RESOURCES LLC Produced Fluid 21,430.57 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Produced Fluid 6.66 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC 88.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2017 PENNENERGY RESOURCES LLC 11,346.33 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Synthetic Liner Materials 18.63 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 88.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2018 PENNENERGY RESOURCES LLC Produced Fluid 2,958.71 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 10.63 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018 PENNENERGY RESOURCES LLC Produced Fluid 36.33 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 39.71 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 PENNENERGY RESOURCES LLC Produced Fluid 265.61 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 2,971.65 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Produced Fluid 37.49 Bbl INJECTION DISPOSAL WELL 34-155-21893
2019 PENNENERGY RESOURCES LLC Produced Fluid 124.99 Bbl INJECTION DISPOSAL WELL 34-155-23196

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2499825 Primary Facility 2016-07-01 Drilling/Alteration No Violations Noted THE CELLAR AND 40' OF 16" CONDUCTOR ARE IN AND CEMENTED. THE WELL IS COVERED WITH A STEEL PLATE.

THE SITE IS IN GOOD CONDITION.

2504348 Primary Facility 2016-07-25 Routine/Complete Inspection No Violations Noted
2512467 Primary Facility 2016-07-18 Drilling/Alteration No Violations Noted TOP HOLE DRILLING IS COMPLETE. THE RIG HAS MOVED.

THE SITE IS IN GOOD CONDITION.

2514040 Primary Facility 2016-07-15 Drilling/Alteration No Violations Noted A 15" HOLE WAS DRILLED TO 832' AND 822' OF 113/4" CASING WAS CEMENTED. THE RIG IS DOWN FOR CEMENT TIME.

THE SITE IS IN GOOD CONDITION.

2518504 Primary Facility 2016-09-07 Routine/Complete Inspection No Violations Noted
2542675 Primary Facility 2016-11-17 Routine/Complete Inspection No Violations Noted
2547224 Primary Facility 2016-11-30 Drilling/Alteration No Violations Noted THE PRODUCTION CASING IS IN AND CEMENTED TO THE SURFACE.

PATTERSON 259 IS TEARING DOWN AND WILL MOVE FROM THE SITE.

2560043 Primary Facility 2017-02-09 Routine/Complete Inspection No Violations Noted On 2/9/17 WQS Brian MacQuarrie onsite at unconventional well site. Three wells drilled. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad to aid in future well stimulation activities. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. No apparent E/S issues. Light snow covering on ground during inspection.
2570778 Primary Facility 2017-03-13 Routine/Complete Inspection No Violations Noted On 3/13/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells drilled. CUDD Well Services onsite perforating Toe stage. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad to aid in future well stimulation activities. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. No apparent E/S issues. Light snow covering on ground during inspection.
2588514 Primary Facility 2017-05-01 Routine/Complete Inspection No Violations Noted On 5/01/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells fraced. Crew tearing down equipment used in frac. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. Vegetative growth well established in previously disturbed areas. No apparent E/S issues.
2612468 Primary Facility 2017-07-06 Routine/Complete Inspection No Violations Noted On 07/03/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells in production. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. Vegetative growth well established in previously disturbed areas. No apparent E/S issues.
2668361 Primary Facility 2017-12-06 Routine/Complete Inspection No Violations Noted Site had been constructed as outlined in the E&S plan contained within the ESCGP. All site and access road erosion controls had been implemented and properly maintained. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All disturbed areas had been stabilized with vegetation attaining 70% uniform vegetative cover. The well appeared to be equipped for production. There were two brine tanks located onsite within containment. Both the tanks and containment appeared to be in sound condition. There was one Baker tank and four sealed roll-off boxes located on containment on the gravel well pad. Additionally there were four roll off boxes with secondary containment located on the AST pad that appeared to contain pieces of secondary containment. It was also noted that pieces to the AST were located onsite on what had been the AST pad. Finally there was a well development impoundment located onsite and it appeared to contain freshwater.
2698840 Primary Facility 2018-02-27 Routine/Complete Inspection No Violations Noted Site and access road had been constructed in accordance with the ESCGP. All site and access road erosion controls had been implemented and maintained properly. All disturbed slopes and soil stockpiles had been stabilized with vegetation. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that significant precipitation events had recently ceased. Two produced fluids tanks were located onsite within secondary containment. Both the tanks and containment appeared to be in sound condition. Well development impoundment located onsite and it appeared to contain collected precipitation and withdrawn fluids. There was an Act 9 sign located onsite in accordance with 25 Pa Code Chapter 78a.55(i).
2761065 Primary Facility 2018-08-07 Complaint Inspection No Violations Noted At the time of inspection well equipped for production. Brine tank within secondary containment and appears structurally sound. GPUs within containment.
2778417 Primary Facility 2018-09-21 Routine/Complete Inspection No Violations Noted At the time of inspection the well was drilled and equipped for production. The Brine tank and GPU were placed in secondary containment. The well was tagged and the Act 9 site ID sign was installed.

For data sources see[8]

References