37-007-20468

Well Details

Well ID: 37-007-20468
Loading map...
Country: United States
State: Pennsylvania
County: Beaver
Municipality: New Sewickley Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 152367
Farm/Lease Name: PER B11
License Status: Active
Spud Date: 2016-06-29
Permit Date: 2015-03-18
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.734586
Longitude: -80.201439

For data sources see[1][2][3]

Well History

Date Event
2015-03-18 New Permit Application
2015-11-10 New Permit Application
2016-06-29 Performed Spud Operation
2016-07-20 Drilling Completion
2020-02-04 Deviated
2020-02-04 Newly Drilled

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-04-05 2017-04-18 5,305 12,849,900 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Hydrochloric Acid (7.5%) Axiall Acidizing Hydrogen Chloride 7647-01-0 40 0.966951 1,207,840.0
Other Chemical(s) Listed Above See Trade Name(s) List Acetophenone 98-86-2 1 0.00001084 13.543
Thiourea 62-56-6 1 0.00001084 13.543
Ethoxylated Alcohol 68002-97-1 35 0.00037946 473.994
Methanol 67-56-1 5 0.00005421 67.713
Formaldehyde 50-00-0 1 0.00001084 13.543
TRS 11800, TRS 3001, EC6111A TightRock Solutions Frac Fluid Additives Ethylene Glycol 107-21-1 5 0.000412288 515
Alkyl Alcohol Proprietary 10 0.00834495 10423.9
Amine Triphosphate Proprietary 30 0.00247373 3090
Glutaraldehyde 111-30-8 30 0.00226478 2829
Oxyalkylated Alcohol Proprietary 5 0.00417247 5211.94
Hydrotreated Light Distillate 64742-47-8 30 0.0250348 31271.7
Methanol 67-56-1 1 0.00007605 95
Sodium Phosphate, Tribasic 7601-54-9 5 0.000412288 515
Inorganic Salt Proprietary 10 0.00834495 10423.9
Sand (Proppant) Sargent Proppant Silica 14808-60-7 99.9 11.5368 14,411,000.0
Unihib G GeoSafe Acid Corrosion Inhibitor Formaldehyde 50-00-0 1 0.00001084 13.543
Glycol Ether 112-34-5 60 0.000650504 812.561
Acetophenone 98-86-2 1 0.00001084 13.543
Ethoxylated Alcohol 68002-97-1 35 0.00037946 473.994
Methanol 67-56-1 5 0.00005421 67.713
Thiourea 62-56-6 1 0.00001084 13.543
Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 85.9143 107,318,000.0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2016 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2017 PENNENERGY RESOURCES LLC 612,680.00 193 0.00 0 9,192.00 193
2018 PENNENERGY RESOURCES LLC 781,566.00 355 0.00 0 12,159.00 355
2019 PENNENERGY RESOURCES LLC 567,940.00 309 0.00 0 6,414.00 309

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 2,150.55 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 2,150.55 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Drill Cuttings 770.63 Tons LANDFILL CID # 28726
2017 PENNENERGY RESOURCES LLC Produced Fluid 33.43 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 21.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC Produced Fluid 105.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2017 PENNENERGY RESOURCES LLC Drill Cuttings 0.54 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 105.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2017 PENNENERGY RESOURCES LLC 33.97 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 21.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 9.65 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC 88.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2017 PENNENERGY RESOURCES LLC Produced Fluid 18,232.87 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC 10,970.85 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Synthetic Liner Materials 22.96 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 88.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2018 PENNENERGY RESOURCES LLC Produced Fluid 2,673.26 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 10.63 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018 PENNENERGY RESOURCES LLC Produced Fluid 36.33 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 30.70 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 PENNENERGY RESOURCES LLC Produced Fluid 324.79 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 2,317.55 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Produced Fluid 28.89 Bbl INJECTION DISPOSAL WELL 34-155-21893
2019 PENNENERGY RESOURCES LLC Produced Fluid 216.25 Bbl INJECTION DISPOSAL WELL 34-155-23196

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2499826 Primary Facility 2016-07-01 Drilling/Alteration No Violations Noted THE CELLAR AND 40' OF 16" CONDUCTOR ARE IN AND CEMENTED. THE WELL IS COVERED WITH A STEEL PLATE.

THE SITE IS IN GOOD CONDITION.

2504350 Primary Facility 2016-07-25 Routine/Complete Inspection No Violations Noted
2512473 Primary Facility 2016-07-18 Drilling/Alteration No Violations Noted HIGHLANDS RIG 9 IS DRILLING A 15" HOLE AT 688'.

THE SITE IS IN GOOD CONDITION.

2512478 Primary Facility 2016-07-19 Drilling/Alteration No Violations Noted HIGHLANDS RIG 9 DRILLED TO827', THEN SET 804' OF 113/4" CASING.

THE RIG IS DOWN FOR CEMENT TIME.

2512487 Primary Facility 2016-07-21 Drilling/Alteration No Violations Noted TOP HOLE DRILLING IS COMPLETE. HIGHLANDS 9 IS MOVING.

THE SITE IS IN GOOD CONDITION.

2518506 Primary Facility 2016-09-07 Routine/Complete Inspection No Violations Noted
2542676 Primary Facility 2016-11-17 Routine/Complete Inspection No Violations Noted
2547221 Primary Facility 2016-11-18 Drilling/Alteration No Violations Noted PATTERSON 259 HAS DRILLED TO 4,408'. THE RIG IS DOWN FOR A CABLE CHANGE.

THE SITE IS IN GOOD CONDITION.

2560044 Primary Facility 2017-02-09 Routine/Complete Inspection No Violations Noted On 2/9/17 WQS Brian MacQuarrie onsite at unconventional well site. Three wells drilled. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad to aid in future well stimulation activities. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. No apparent E/S issues. Light snow covering on ground during inspection.
2570779 Primary Facility 2017-03-13 Routine/Complete Inspection No Violations Noted On 3/13/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells drilled. CUDD Well Services onsite perforating Toe stage. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad to aid in future well stimulation activities. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. No apparent E/S issues. Light snow covering on ground during inspection.
2588518 Primary Facility 2017-05-01 Routine/Complete Inspection No Violations Noted On 5/01/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells fraced. Crew tearing down equipment used in frac. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. Vegetative growth well established in previously disturbed areas. No apparent E/S issues.
2612470 Primary Facility 2017-07-06 Routine/Complete Inspection No Violations Noted On 07/03/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells in production. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. Vegetative growth well established in previously disturbed areas. No apparent E/S issues.
2668363 Primary Facility 2017-12-06 Routine/Complete Inspection No Violations Noted Site had been constructed as outlined in the E&S plan contained within the ESCGP. All site and access road erosion controls had been implemented and properly maintained. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All disturbed areas had been stabilized with vegetation attaining 70% uniform vegetative cover. The well appeared to be equipped for production. There were two brine tanks located onsite within containment. Both the tanks and containment appeared to be in sound condition. There was one Baker tank and four sealed roll-off boxes located on containment on the gravel well pad. Additionally there were four roll off boxes with secondary containment located on the AST pad that appeared to contain pieces of secondary containment. It was also noted that pieces to the AST were located onsite on what had been the AST pad. Finally there was a well development impoundment located onsite and it appeared to contain freshwater.
2698841 Primary Facility 2018-02-27 Routine/Complete Inspection No Violations Noted Site and access road had been constructed in accordance with the ESCGP. All site and access road erosion controls had been implemented and maintained properly. All disturbed slopes and soil stockpiles had been stabilized with vegetation. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that significant precipitation events had recently ceased. Two produced fluids tanks were located onsite within secondary containment. Both the tanks and containment appeared to be in sound condition. Well development impoundment located onsite and it appeared to contain collected precipitation and withdrawn fluids. There was an Act 9 sign located onsite in accordance with 25 Pa Code Chapter 78a.55(i).
2761069 Primary Facility 2018-08-07 Complaint Inspection No Violations Noted At the time of inspection well equipped for production. Brine tank within secondary containment and appears structurally sound. GPUs within containment.
2778419 Primary Facility 2018-09-21 Routine/Complete Inspection No Violations Noted At the time of inspection the well was drilled and equipped for production. The Brine tank and GPU were placed in secondary containment. The well was tagged and the Act 9 site ID sign was installed.

For data sources see[8]

References