37-007-20469

Well Details

Well ID: 37-007-20469
Loading map...
Country: United States
State: Pennsylvania
County: Beaver
Municipality: New Sewickley Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 152367
Farm/Lease Name: PER B11 4H
License Status: Active
Spud Date: 2016-06-29
Permit Date: 2015-03-18
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.734559
Longitude: -80.201502

For data sources see[1][2][3]

Well History

Date Event
Deviated
2015-03-18 New Permit Application
2015-11-10 New Permit Application
2016-06-29 Performed Spud Operation
2016-07-25 Drilling Completion
2020-02-12 Newly Drilled

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-04-18 2017-04-28 5,391 14,475,200 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 TRS 11800, TRS 3001, EC6111A TightRock Solutions Frac Fluid Additives Inorganic Salt Proprietary 10 0.00865724 12151.7
Hydrotreated Light Distillate 64742-47-8 30 0.0259717 36455
Glutaraldehyde 111-30-8 30 0.00201547 2829
Ethylene Glycol 107-21-1 5 0.000366902 515
Alkyl Alcohol Proprietary 10 0.00865724 12151.7
Sodium Phosphate, Tribasic 7601-54-9 5 0.000366902 515
Amine Triphosphate Proprietary 30 0.00220141 3090
Methanol 67-56-1 1 0.00006768 95
Oxyalkylated Alcohol Proprietary 5 0.00432862 6075.84
Hydrochloric Acid (7.5%) Axiall Acidizing Hydrogen Chloride 7647-01-0 40 1.04207 1,462,700.0
Other Chemical(s) Listed Above See Trade Name(s) List Methanol 67-56-1 5 0.00005830 81.838
Thiourea 62-56-6 1 0.00001166 16.368
Ethoxylated Alcohol 68002-97-1 35 0.000408129 572.867
Formaldehyde 50-00-0 1 0.00001166 16.368
Acetophenone 98-86-2 1 0.00001166 16.368
Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 86.1445 120,916,000.0
Sand (Proppant) Sargent Proppant Silica 14808-60-7 99.9 11.1184 15,606,300.0
Unihib G GeoSafe Acid Corrosion Inhibitor Methanol 67-56-1 5 0.00005830 81.838
Ethoxylated Alcohol 68002-97-1 35 0.000408129 572.867
Formaldehyde 50-00-0 1 0.00001166 16.368
Glycol Ether 112-34-5 60 0.000699649 982.058
Thiourea 62-56-6 1 0.00001166 16.368
Acetophenone 98-86-2 1 0.00001166 16.368

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2016 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2017 PENNENERGY RESOURCES LLC 753,798.00 185 0.00 0 3,834.00 185
2018 PENNENERGY RESOURCES LLC 1,054,991.00 354 0.00 0 4,702.00 354
2019 PENNENERGY RESOURCES LLC 796,617.00 305 0.00 0 2,474.00 305

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 2,154.83 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Drilling Fluid Waste 2,154.83 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Other Oil & Gas Wastes 40.05 Bbl CENT WASTE TRT FAC NPDES DISCHARGE EPA ID: 748-163
2016 PENNENERGY RESOURCES LLC Drill Cuttings 850.61 Tons LANDFILL CID # 28726
2016 PENNENERGY RESOURCES LLC Other Oil & Gas Wastes 40.05 Bbl CENT WASTE TRT FAC NPDES EPA ID: 748-163
2017 PENNENERGY RESOURCES LLC Produced Fluid 33.43 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 33.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC Produced Fluid 165.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2017 PENNENERGY RESOURCES LLC Drill Cuttings 0.54 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC 165.00 Bbl INJECTION DISPOSAL WELL 34-155-22403
2017 PENNENERGY RESOURCES LLC 33.97 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 33.00 Bbl INJECTION DISPOSAL WELL 34-155-21893
2017 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 9.65 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2017 PENNENERGY RESOURCES LLC 139.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2017 PENNENERGY RESOURCES LLC Produced Fluid 24,054.03 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC 17,156.33 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Synthetic Liner Materials 35.54 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2017 PENNENERGY RESOURCES LLC Produced Fluid 139.00 Bbl INJECTION DISPOSAL WELL 34-155-23795
2018 PENNENERGY RESOURCES LLC Produced Fluid 3,375.08 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 10.63 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2018 PENNENERGY RESOURCES LLC Produced Fluid 36.33 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 43.69 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 PENNENERGY RESOURCES LLC Produced Fluid 289.59 Bbl INJECTION DISPOSAL WELL 34-155-23223
2019 PENNENERGY RESOURCES LLC Produced Fluid 3,253.14 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Produced Fluid 40.63 Bbl INJECTION DISPOSAL WELL 34-155-21893
2019 PENNENERGY RESOURCES LLC Produced Fluid 135.76 Bbl INJECTION DISPOSAL WELL 34-155-23196

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2499824 Primary Facility 2016-07-01 Drilling/Alteration No Violations Noted THE CELLAR AND 40' OF 16" CONDUCTOR ARE IN AND CEMENTED. THE WELL IS COVERED WITH A STEEL PLATE.

THE SITE IS IN GOOD CONDITION.

2504354 Primary Facility 2016-07-25 Routine/Complete Inspection No Violations Noted
2512489 Primary Facility 2016-07-21 Drilling/Alteration No Violations Noted HIGHLANDS 9 IS MOVING OVER THE WELL.

THE SITE IS IN GOOD CONDITION.

2518507 Primary Facility 2016-09-07 Routine/Complete Inspection No Violations Noted
2542679 Primary Facility 2016-11-17 Routine/Complete Inspection No Violations Noted
2547217 Primary Facility 2016-11-15 Drilling/Alteration No Violations Noted HALIBURTON IS CEMENTING 13,296' OF PRODUCTION CASING. THE CASING WILL BE CEMENTED TO THE SURFACE.

THE SITE IS IN GOOD CONDITION.

2548203 Primary Facility 2016-11-07 Drilling/Alteration No Violations Noted patterson 259 is up and ready to drill.

the site is in good condition.

2548209 Primary Facility 2016-11-04 Drilling/Alteration No Violations Noted PATTERSON 259 WILL RESUME DRILLING AT 2,335'.

THE SITE IS IN GOOD CONDITION.

2548212 Primary Facility 2016-11-18 Drilling/Alteration No Violations Noted THE PRODUCTION CASING IS SET AT 13,296' AND CEMENTED TO THE SURFACE.

THE RIG HAS MOVED.

2560045 Primary Facility 2017-02-09 Routine/Complete Inspection No Violations Noted On 2/9/17 WQS Brian MacQuarrie onsite at unconventional well site. Three wells drilled. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad to aid in future well stimulation activities. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. No apparent E/S issues. Light snow covering on ground during inspection.
2570782 Primary Facility 2017-03-13 Routine/Complete Inspection No Violations Noted On 3/13/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells drilled. CUDD Well Services onsite perforating Toe stage. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad to aid in future well stimulation activities. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. No apparent E/S issues. Light snow covering on ground during inspection.
2588520 Primary Facility 2017-05-01 Routine/Complete Inspection No Violations Noted On 5/01/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells fraced. Crew tearing down equipment used in frac. Production equipment setup onsite including two 400 bbl production tanks setup within stainless steel containment structure. Temporary AST setup on tank pad. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. Vegetative growth well established in previously disturbed areas. No apparent E/S issues.
2612472 Primary Facility 2017-07-06 Routine/Complete Inspection No Violations Noted On 07/03/2017, WQS Brian MacQuarrie onsite at unconventional well site. Three wells in production. Freshwater impoundment installed and fenced in. Act 9 sign maintained and Erosion and Sedimentation Plan in mailbox. Erosion and Sedimentation Best Management Practices installed and maintained. Vegetative growth well established in previously disturbed areas. No apparent E/S issues.
2668364 Primary Facility 2017-12-06 Routine/Complete Inspection No Violations Noted Site had been constructed as outlined in the E&S plan contained within the ESCGP. All site and access road erosion controls had been implemented and properly maintained. There was no observed accelerated erosion or sedimentation in relation to the site or access road. All disturbed areas had been stabilized with vegetation attaining 70% uniform vegetative cover. The well appeared to be equipped for production. There were two brine tanks located onsite within containment. Both the tanks and containment appeared to be in sound condition. There was one Baker tank and four sealed roll-off boxes located on containment on the gravel well pad. Additionally there were four roll off boxes with secondary containment located on the AST pad that appeared to contain pieces of secondary containment. It was also noted that pieces to the AST were located onsite on what had been the AST pad. Finally there was a well development impoundment located onsite and it appeared to contain freshwater.
2698843 Primary Facility 2018-02-27 Routine/Complete Inspection No Violations Noted Site and access road had been constructed in accordance with the ESCGP. All site and access road erosion controls had been implemented and maintained properly. All disturbed slopes and soil stockpiles had been stabilized with vegetation. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that significant precipitation events had recently ceased. Two produced fluids tanks were located onsite within secondary containment. Both the tanks and containment appeared to be in sound condition. Well development impoundment located onsite and it appeared to contain collected precipitation and withdrawn fluids. There was an Act 9 sign located onsite in accordance with 25 Pa Code Chapter 78a.55(i).
2761071 Primary Facility 2018-08-07 Complaint Inspection No Violations Noted At the time of inspection well equipped for production. Brine tank within secondary containment and appears structurally sound. GPUs within containment.
2778423 Primary Facility 2018-09-21 Routine/Complete Inspection No Violations Noted At the time of inspection the well was drilled and equipped for production. The Brine tank and GPU were placed in secondary containment. The well was tagged and the Act 9 site ID sign was installed.

For data sources see[8]

References