37-019-22617

Well Details

Well ID: 37-019-22617
Loading map...
Country: United States
State: Pennsylvania
County: Butler
Municipality: Winfield Township
Operator Name: PENNENERGY RESOURCES LLC
Well Pad ID: 154148
Farm/Lease Name: PER W34
License Status:
Spud Date:
Permit Date: 2017-06-12
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.797765
Longitude: -79.735765

For data sources see[1][2][3]

Well History

Date Event
2017-06-12 New Permit Application
2017-09-14 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-10-03 2018-10-12 6,286 16,249,200 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Unihib G Geosafe Corrosion Inhibitor Butyl digycol 0000112-34-5 75 0.000727537 1152.49
Alcohols C10-16, ethoxylated 0068002-97-1 50 0.000485024 768.324
Formaldehyde 0000050-00-0 1 0.00000970 15.366
Thiourea 0000062-56-6 1 0.00000970 15.366
Methanol 0000067-56-1 5 0.00004850 76.832
BIOC12031A Nalco Biocide Glutaraldehyde 111-30-8 30 0.00667712 10577.2
TRS 17888 Tight Rock Solutions Friction Reducer Substituted alkylamine Proprietary 1 0.00030852 488.725
Inorganic Salt Proprietary 10 0.0030852 4887.25
Hydrotreated Light Distillate 64742-47-8 30 0.00925561 14661.7
Oxyalkylated alcohol Proprietary 5 0.0015426 2443.63
TRS 3001 Tight Rock Solutions Scale Control Sodium Phosphate, Tribasic 7601-54-9 5 0.000931795 1476.05
Ethylene Glycol 107-21-1 5 0.000931795 1476.05
Amine Triphosphate Proprietary 30 0.00559077 8856.31
AP Breaker Lubrizol Breaker Ammonium persulfate 7727-54-0 100 0.000467144 740
TRS 805X Tight Rock Solutions Friction Reducer Alcohol Alkoxylates Proprietary 5 0.00310447 4917.77
Aliphatic Hydrocarbon Proprietary 30 0.0186268 29506.6
Sand (Proppant) Sargent/Momentive/Prefferred Proppant Silica Substrate 14808-60-7 100 12.0954 19,160,300.0
Water PennEnergy Resources Carrier/Base Fluid Water 7732-18-5 100 85.6006 135,599,000.0
Other Chemical(s) Listed Above See Trade Name(s) List Ethylene Glycol 107-21-1 5 0.000931795 1476.05
Formaldehyde 0000050-00-0 1 0.00000970 15.366
Alcohol Alkoxylates Proprietary 5 0.00310447 4917.77
Methanol 0000067-56-1 5 0.00004850 76.832
Inorganic Salt Proprietary 10 0.0030852 4887.25
Thiourea 0000062-56-6 1 0.00000970 15.366
Oxyalkylated alcohol Proprietary 5 0.0015426 2443.63
Sodium Phosphate, Tribasic 7601-54-9 5 0.000931795 1476.05
Alcohols C10-16, ethoxylated 0068002-97-1 50 0.000485024 768.324
Water 7732-18-5 92.5 2.00608 3,177,820.0
Substituted alkylamine Proprietary 1 0.00030852 488.725
Hydrochloric Acid (7.5%) PVS Acidizing Water 7732-18-5 92.5 2.00608 3,177,820.0
Hydrochloric Acid 7647-01-0 7.5 0.162655 257661

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 PENNENERGY RESOURCES LLC 0.00 0 0.00 0 0.00 0
2019 PENNENERGY RESOURCES LLC 1,364,924.00 337 0.00 0 0.00 31

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 PENNENERGY RESOURCES LLC Other Oil & Gas Wastes 18.33 Bbl INJECTION DISPOSAL WELL 34-155-23223
2017 PENNENERGY RESOURCES LLC Produced Fluid 24.67 Bbl INJECTION DISPOSAL WELL 34-155-23223
2017 PENNENERGY RESOURCES LLC Produced Fluid 328.33 Bbl REUSE (AT WELL PAD)
2017 PENNENERGY RESOURCES LLC Produced Fluid 16.67 Bbl INJECTION DISPOSAL WELL 34-155-23196
2017 PENNENERGY RESOURCES LLC Drill Cuttings 456.70 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018 PENNENERGY RESOURCES LLC Drill Cuttings 819.66 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018 PENNENERGY RESOURCES LLC Other Oil & Gas Wastes 30.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2018 PENNENERGY RESOURCES LLC Produced Fluid 1,315.13 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Drilling Fluid Waste 674.17 Bbl INJECTION DISPOSAL WELL 34-155-23223
2018 PENNENERGY RESOURCES LLC Soil Contaminated by Oil & Gas Related Spills 3.73 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018 PENNENERGY RESOURCES LLC Produced Fluid 10.00 Bbl INJECTION DISPOSAL WELL 34-155-23223
2018 PENNENERGY RESOURCES LLC Drilling Fluid Waste 635.00 Bbl INJECTION DISPOSAL WELL 34-155-23196
2018 PENNENERGY RESOURCES LLC Produced Fluid 17.96 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2018 PENNENERGY RESOURCES LLC Drilling Fluid Waste 389.90 Bbl REUSE (AT WELL PAD)
2018 PENNENERGY RESOURCES LLC Soil Contaminated by Oil 3.73 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2019 PENNENERGY RESOURCES LLC Soil Contaminated by Oil 2.50 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2019 PENNENERGY RESOURCES LLC Produced Fluid 31,560.51 Bbl REUSE (AT WELL PAD)
2019 PENNENERGY RESOURCES LLC Soil Contaminated by Oil & Gas Related Spills 2.50 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2019 PENNENERGY RESOURCES LLC Produced Fluid 18.33 Bbl INJECTION DISPOSAL WELL 34-155-23795
2019 PENNENERGY RESOURCES LLC Filter Socks 0.63 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 PENNENERGY RESOURCES LLC Produced Fluid 7.54 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 PENNENERGY RESOURCES LLC Servicing Fluid 13.36 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592
2019 PENNENERGY RESOURCES LLC Waste Water Treatment Sludge 1.91 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 PENNENERGY RESOURCES LLC Produced Fluid 29.88 Tons RESIDUAL WASTE PROCESSING FACILITY PAD085690592

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2638066 Primary Facility 2017-09-14 Routine/Partial Inspection No Violations Noted At the time of inspection, Soilmec was onsite using an auger on the #2H well. This well has not yet been spud. Notification has been sent in to spud the well today. Location is stoned. Permit (paper form) and Emergency Response sign is posted at the lease entrance.
2639189 Primary Facility 2017-09-19 Routine/Partial Inspection No Violations Noted At the time of inspection, no activity was taking place at the well. Containment is laid out over pad. Cellar is set and conductor is cemented in. Cattle fence is surrounding well. Areas to the side of pad have been seeded and mulched.
2652305 Primary Facility 2017-10-19 Routine/Partial Inspection No Violations Noted At the time of inspection, Highlands 9 Was drilling 12 3/8" hole. Surface casing cemented using 615 sxs (133 bbls) Class H, 2% Gypsum, 15.8 ppg, 1.22 yield. Displaced with 113 bbls freshwater and landed plug. Floats held (1/2 bbl back) and 23 bbls cement returned to surface. A float shoe and float collar (top at 724') were used along with 9 centralizers.

Plan is to cement intermediate casing tomorrow and move to B34 pad. Containment appeared to be in good condition.

There was no water/gas/oil encountered while drilling well.

2653492 Primary Facility 2017-10-26 Routine/Partial Inspection No Violations Noted At the time of inspection, no activity was taking place on the pad. Containment was still laid out with some frac tanks sitting on top. Matting boards have been moved to the side of pad. Well has a steel plate over and cattle gates are surrounding. Well label is attached to the gate. Intermediate casing was cemented using 995 sxs Class H, 2% Gypsum, 15.8 ppg, 1.2 yield. Displaced with 205 bbls and bumped plug. Floats held. 40 bbls cement were returned to surface. A float shoe and float collar were used along with 37 centralizers.
2687783 Primary Facility 2018-01-29 Administrative/File Review No Violations Noted
2692946 Primary Facility 2018-02-08 Drilling/Alteration No Violations Noted At the time of inspection, Patterson 259 was onsite tripping back into well after inspecting BHA. It seems they thought there was a cracked mud motor. Drilling has been very slow due to several issues. Time was lost due to BOP testing would not pass. Several items had to be swapped out before it did pass on 1/31. Also, issues getting flowlines to stop leaking took over a day to repair. They then had to trip out to dial up motor because build rate was very slow.

A dark, rusty looking fluid was seen in containment, which company man stated was in fact rust coming from a blowdown boiler. He said it would be sucked up ASAP. Containment was in good condition. Berms were starting to give out due to weight of snow/ice on top, which would be repaired as well.

2697719 Primary Facility 2018-02-13 Drilling/Alteration No Violations Noted At the time of inspection, Halliburton was onsite cementing production casing. This was done using a lead 1 of 350 sxs HalCem (70 bbls), 14.5 ppg, 1.132 yield, a lead 2 of 1060 sxs ShaleCem (213 bbls), 14.5 ppg, 1.135 yield, and tail of 1170 sxs SoluCem (379 bbls), 15.2 ppg, 1.82 yield. This as displaced with 20 bbls KCl, followed by 301 bbls freshwater. Plug landed and floats held. 60 bbls cement were returned to surface. Plug was down at 8:45 AM. Containment looked good and no issues during cement job.
2708091 Primary Facility 2018-03-21 Administrative/File Review No Violations Noted
2722763 Primary Facility 2018-04-25 Routine/Partial Inspection No Violations Noted On 4/25/2018, WQS Brian MacQuarrie onsite for the purpose of conducting an site inspection. Sign maintained at entrance identifying site and individual signs for wells and permit Nos. . Site mailbox contains Erosion and Sedimentation Plan and E/S inspection reports with most recent conducted on 4/17/2018. Site access road maintained. Patterson Rig # 259 no longer onsite. Soundwall constructed around well pad. Six wells spudded including ; 1H-019-22613, 2H-019-22614, 3H-019-22615, 4H-019-22616, 5H-019-22661 and the 6H-019-22617.
2752878 Primary Facility 2018-07-16 Routine/Partial Inspection No Violations Noted On 7-16-2018, WQS Brian MacQuarrie onsite for the purpose of conducting an site inspection. Sign maintained at entrance identifying site and individual signs for wells and permit Nos.. Site access road maintained. Patterson Rig # 259 no longer onsite. Soundwall constructed around well pad. Six wells drilled including ; 1H-019-22613, 2H-019-22614, 3H-019-22615, 4H-019-22616, 5H-019-22661 and the 6H-019-22617.
2782498 Primary Facility 2018-10-02 Drilling/Alteration No Violations Noted Received stimulation notice for 10/2/18. Spoke with Frank Kosher on site. Stimulation has been delayed until the afternoon. Thirty nine stages are scheduled and should be completed in a week and half. The 6H is the first of six wells on the pad to be stimulated.
2794385 Primary Facility 2018-10-24 Routine/Partial Inspection No Violations Noted On 11/24/2018, WQS Brian MacQuarrie onsite meet with Frank Kocher (PennEnergy). Universal and Renegade onsite. Well stimulation activities underway. Wells 6H-019-22617 and 4H-019-22616 fraced. Four wells left to be fraced, 1H-019-22613, 2H-019-22614, 3H-019-22615 and 5H-019-22661. Secondary containment setup. Large AST onsite to aid in frac. Erosion and Sedimentation BMPs maintained. Vegetative growth well established.
2813982 Primary Facility 2018-12-12 Routine/Partial Inspection No Violations Noted On 12/12/2018, WQS Brian MacQuarrie onsite. Meet with Heath Cunningham-PennEnergy. Deep well services onsite. Snubbing unit #3 is onsite. Currently plugs are being drilled out and production tubing installed in six wells; 1H-019-22613, 2H-019-22614, 3H-019-22615, 4H-019-22616, 5H-019-22617 and 6H-019-22617. Well site secondary containment setup. Large AST onsite and contains approximately 8 inches of impaired water. Erosion and Sedimentation BMPs installed and maintained.
2832641 Primary Facility 2019-01-28 Routine/Partial Inspection No Violations Noted On 1/28/2019, WQS Brian MacQuarrie onsite. Six wells fraced; 1H-019-22613, 2H-019-22614, 3H-019-22615, 4H-019-22616, 5H-019-22661 and 6H-019-22617. Crew onsite flowing back the 2H . The last of six wells. Three 400 bbl production fluid tanks installed within stainless steel containment structure. Large AST onsite containing impaired water. Water from AST is currently being hauled to the B17 well pad in Beaver County. Frac tanks installed within secondary containment. Snow on ground during inspection.
2833602 Primary Facility 2019-01-30 Administrative/File Review No Violations Noted

For data sources see[8]

References