37-033-26961

Well Details

Well ID: 37-033-26961
Loading map...
Country: United States
State: Pennsylvania
County: Clearfield
Municipality: Goshen Township
Operator Name: GREYLOCK PROD LLC
Well Pad ID: 149570
Farm/Lease Name: WHITETAIL 3MH
License Status:
Spud Date:
Permit Date: 2010-11-10
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.126785
Longitude: -78.352970

For data sources see[1][2][3]

Well History

Date Event
2010-11-10 New Permit Application
2011-04-22 Performed Spud Operation
2011-10-27 Drilling Completion
2011-11-29 Perforation
2012-09-28 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2011-11-29 2011-11-29 7,464 4,060,770

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Biocide EC 6116A Universal Well Services Biocide Dibromoacetonitrile 3252-43-5 5.00 0.00091000
Polyethylene glycol 25322-68-3 60.00 0.01
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 30.00 0.00543000
Proppant-40/70 Universal Well Services Proppant Quartz 14808-60-7 100.00 6.12
Proppant-40/70 U.S. Well Services Proppant
15 Hydrochloric Acid (UWS) Universal Well Services Acid Hydrochloric acid 7647-01-0 15.00 0.08
LEB 10X Universal Well Services Breaker Ethylene glycol 107-21-1 60.00 0.00059000
Water ECA Base Fluid 90.80
WGA-3, CMHPG Universal Well Services Dry Gellant Guar gum 9000-30-0 100.00 0.01
Scale Hib 100 Universal Well Services Scale Inhibitor Ethylene glycol 107-21-1 60.00 0.01
Unihib G Universal Well Services Corrosion Inhibitor for Acid 2-Ethylhexanol 104-76-7 75.00 0.00049000
Short chained glycol ether 25.00 0.00016000
Proppant-100 Mesh Universal Well Services Proppant Quartz 14808-60-7 100.00 2.90
Unislik ST 50 Universal Well Services Friction Reducer Distillates, petroleum, hydrotreated light 64742-47-8 30.00 0.02

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 ENERGY CORP OF AMER 0.00 0 0.00 0 0.00 0
2011 ENERGY CORP OF AMER 30,336.00 24 0.00 0 0.00 0
2012 ENERGY CORP OF AMER 376,008.00 335 0.00 0 0.00 0
2013 ENERGY CORP OF AMER 297,085.00 363 0.00 0 0.00 0
2014 ENERGY CORP OF AMER 227,896.00 365 0.00 0 0.00 0
2015 ENERGY CORP OF AMER 137,107.00 349 0.00 0 0.00 0
2016 ENERGY CORP OF AMER 107,666.00 248 0.00 0 0.00 0
2017 ENERGY CORP OF AMER 152,003.00 353 0.00 0 0.00 0
2018 GREYLOCK PROD LLC 128,282.00 356 0.00 0 0.00 0
2019 GREYLOCK PROD LLC 110,122.00 365 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2011 ENERGY CORP OF AMER Produced Fluid 440.00 Bbl REUSE OTHER THAN ROAD SPREADING
2011 ENERGY CORP OF AMER Produced Fluid 2,200.00 Bbl STORAGE PENDING DISPOSAL OR REUSE
2011 ENERGY CORP OF AMER Drill Cuttings 424.28 Tons LANDFILL 100434
2011 ENERGY CORP OF AMER Drilling Fluid Waste 315.00 Bbl LANDFILL 100434
2012 ENERGY CORP OF AMER Produced Fluid 23,569.00 Bbl REUSE OTHER THAN ROAD SPREADING
2012 ENERGY CORP OF AMER Fracturing Fluid Waste 17.62 Tons LANDFILL SWF 1025
2012 ENERGY CORP OF AMER Produced Fluid 1,400.00 Bbl INJECTION DISPOSAL WELL 34-155-23584
2012 ENERGY CORP OF AMER Fracing Fluid Waste 11,345.00 Bbl REUSE OTHER THAN ROAD SPREADING
2013 ENERGY CORP OF AMER Produced Fluid 9,225.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 ENERGY CORP OF AMER Produced Fluid 5,715.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 ENERGY CORP OF AMER Produced Fluid 35.00 Bbl INJECTION DISPOSAL WELL 34-155-24076
2014 ENERGY CORP OF AMER Produced Fluid 35.00 Bbl INJECTION DISPOSAL WELL 34-155-24075
2014 ENERGY CORP OF AMER Produced Fluid 5,328.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW006
2015 ENERGY CORP OF AMER Produced Fluid 8,253.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW005
2015 ENERGY CORP OF AMER Produced Fluid 5,568.00 Bbl REUSE OTHER THAN ROAD SPREADING
2016 ENERGY CORP OF AMER Produced Fluid 140.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2016 ENERGY CORP OF AMER Produced Fluid 630.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW005
2016 ENERGY CORP OF AMER Produced Fluid 136.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW011
2017 ENERGY CORP OF AMER Produced Fluid 21,427.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2017 ENERGY CORP OF AMER Other Oil & Gas Wastes 15.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2018 GREYLOCK PROD LLC Produced Fluid 1,861.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2018 GREYLOCK PROD LLC Produced Fluid 319.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2018 GREYLOCK PROD LLC Produced Fluid 8,340.00 Bbl INJECTION DISPOSAL WELL 34-155-24079
2018 GREYLOCK PROD LLC Produced Fluid 50.00 Bbl INJECTION DISPOSAL WELL 34-133-24189
2018 ENERGY CORP OF AMER Produced Fluid 6,037.00 Bbl REUSE (AT WELL PAD)
2018 GREYLOCK PROD LLC Produced Fluid 1,010.00 Bbl INJECTION DISPOSAL WELL 34-007-21847
2019 GREYLOCK PROD LLC Produced Fluid 1,273.00 Bbl INJECTION DISPOSAL WELL 34-155-24079
2019 GREYLOCK PROD LLC Produced Fluid 352.00 Bbl REUSE (AT WELL PAD)
2019 GREYLOCK PROD LLC Produced Fluid 349.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123SW005
2019 GREYLOCK PROD LLC Produced Fluid 235.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1986421 Primary Facility 2011-07-08 Compliance Evaluation No Violations Noted
1992179 Primary Facility 2011-08-02 Compliance Evaluation No Violations Noted
2006924 Primary Facility 2011-09-29 Compliance Evaluation Violation(s) Noted
2009494 Primary Facility 2011-10-11 Compliance Evaluation No Violations Noted
2017074 Primary Facility 2011-11-07 Compliance Evaluation No Violations Noted
2044810 Primary Facility 2012-02-23 Routine/Complete Inspection No Violations Noted
2050191 Primary Facility 2012-03-13 Routine/Complete Inspection No Violations Noted
2058863 Primary Facility 2012-04-11 Routine/Complete Inspection Viol(s) Noted & Immediately Corrected
2095298 Primary Facility 2012-08-29 Routine/Complete Inspection Violation(s) Noted
2101592 Primary Facility 2012-09-20 Routine/Complete Inspection No Violations Noted
2102696 Primary Facility 2012-09-25 Drilling/Alteration No Violations Noted
2103386 Primary Facility 2012-09-27 Follow-up Inspection No Violations Noted
2107349 Primary Facility 2012-09-27 Follow-up Inspection No Violations Noted
2149180 Primary Facility 2013-03-19 Routine/Complete Inspection No Violations Noted
2179583 Primary Facility 2013-07-01 Routine/Complete Inspection No Violations Noted
2183996 Primary Facility 2013-07-17 Routine/Complete Inspection Viol(s) Noted & Immediately Corrected
2219900 Primary Facility 2013-11-07 Routine/Complete Inspection No Violations Noted
2224934 Primary Facility 2013-11-26 Routine/Complete Inspection No Violations Noted
2236359 Primary Facility 2014-01-15 Routine/Complete Inspection No Violations Noted
2264517 Primary Facility 2014-04-22 Routine/Complete Inspection No Violations Noted
2337438 Primary Facility 2015-01-15 Routine/Complete Inspection No Violations Noted
2362612 Primary Facility 2015-04-20 Routine/Complete Inspection No Violations Noted
2427906 Primary Facility 2015-11-25 Routine/Complete Inspection No Violations Noted
2482709 Primary Facility 2016-05-09 Routine/Complete Inspection No Violations Noted
2515275 Primary Facility 2016-08-30 Routine/Complete Inspection No Violations Noted
2554363 Primary Facility 2017-01-20 Routine/Complete Inspection No Violations Noted
2668308 Primary Facility 2017-12-01 Routine/Complete Inspection No Violations Noted Routine inspection at Energy Corporation of America's (ECA) Whitetail #1 Pad on December 1, 2017. No one was onsite during my inspection. I later spoke with JD Sollon and Travis Wendel via phone on December 4, 2017 regarding some questions I had about this pad and ESCGP. Both gentlemen informed me that ECA was recently bought out by Grey Lock Energy (GLE). GLE is in the processing of having their well permits transferred from ECA to GLE. Both gentlemen are now employed by GLE.

The Whitetail #1 Pad has two producing Marcellus wells located on it (033-26961 and 033-27086). Both well cellars are full of water and no sheen was obsereved. I observed bubbling within the well cellar of 033-26961. I recommend the operator further investigate the bubbling. I will be referring this bubbling to one of the Departments Oil & Gas Inspector's for further investigation.

Each well is connected to (2) 400 bbl produced fluids tanks which are stationed within a clay lined earthen secondary containment. A trace of water w

2668812 Primary Facility 2017-12-08 Follow-up Inspection No Violations Noted The weather is 28 Deg. F and cloudy, windy at time of inspection.

Follow up inspection of Energy Corporation of America, Whitetail 2MH Pad, well number 3MH on December 8, 2017. Annulus 9-5/8" was plumbed to the production line at time of inspection. Digital gauge on the production tubing reads 46 PSI pressure. 0% combustible gas was detected in the area immediately surrounding the well. Used plastic jug to capture bubbling and 4% LEL combustible gas was detected at the time of inspection. This was followed with pumping the water out of the cellar by vacuum truck. Visibly confirmed unknown combustible gas escaping the ground from the outside of the well casing. No violations noted. Discussed follow up inspection with company representative present on site. Energy Corporation of America representative - Roy Ricker - Production Foreman.

2668978 Primary Facility 2017-12-08 Follow-up Inspection No Violations Noted The weather is 28 Deg. F and cloudy, windy at time of inspection.

Follow up inspection of Energy Corporation of America, Whitetail 2MH Pad, well number 3MH on December 7, 2017. There are 2 producing wells on this pad: (Permits: 033-26961; 033-27086). Annulus 9-5/8" was plumbed to the poly tank at time of inspection. Digital gauge on the production tubing reads 44 PSI pressure. 0% combustible gas was detected in the area immediately surrounding the well. Visibly confirmed unknown combustible gas escaping the ground from the outside of the well casing. No violations noted. Discussed follow up inspection with company representative present on site. Energy Corporation of America representative - Roy Ricker - Production foreman and John Sollon - Lead PA Construction and Environmental Foreman. DEP Representative ¿ Ulyana Trynovich, Oil and Gas Inspector.

2711059 Primary Facility 2018-03-27 Follow-up Inspection No Violations Noted The weather is 40 Deg. F and cloudy, windy at time of inspection.

Follow up inspection of Greylock Production LLC., Whitetail Pad, well number 3MH on March 27, 2018. There are 2 active wells on site. This well is producing. Annulus (9-5/8" x 5-1/2¿) was plumbed to the poly tank at time of inspection. Digital gauge on the production tubing reads 42 PSI pressure. 0% combustible gas was detected in the poly tank or the area immediately surrounding the well. Visibly confirmed there is no combustible gas escaping the ground from the outside of the well casing during inspection. No obvious concerns or violations are noted at time of inspection. Wellsite looks neat and well organized. DEP Representative - Ulyana Trynovich, Oil and Gas Inspector.

2764475 Primary Facility 2018-08-14 Routine/Complete Inspection No Violations Noted Department staff Sue Herzing, Sara Metz, and Mike Jurbala conducted a routine site inspection at Greylock Production LLC Whitetail #1 well pad and flowback impoundment on August 14, 2018. The operator is currently in the process of dewatering the flowback impoundment. Water is being hauled offsite via tank trucks. During the inspection we observed two holes within the flowback impoundment liner near the load-out area (photo 4). Another layer of liner was observed underneath the holes.

Greylock is currently in a Consent Order and Agreement (CO&A) with the Department finalized in November 2017. According to the CO&A the operator is required to restore this flowback impoundment and conduct site characterization, consisting of a sub-liner investigation after the liner is removed. If issues are found during that sub-liner investigation, then the operator shall conduct a site remediation in accordance with ACT 2.

There are two producing wells located on the well pad (033-26961 and 033-27086). Each well is prop

2786646 Primary Facility 2018-10-09 Compliance Evaluation No Violations Noted I met with JD Sollon of Greylock on the site. Two skid steers and a 3- man crew were removing the liner and felt from the on-site impoundment. Moody & Associates group on location included Brandon Glowark, Ian Williams, Jona Stoskey, and Brynn Yochim. Moody was there to perform soil screening after the liner removal was completed; screening was to be for specific conductance, petroleum product, and rads. Although it appeared initially that the screening would begin while I was still on location, one of the skid steers threw a track and was being repaired until I departed. I noted several freshwater seeps on the northern slope of the impoundment, which were collecting mostly in the western side. The plan was to dig an interceptor trench across the north and west sides of the impoundment at the bottom to collect these seeps. Then Moody would perform the soil screening and take characterization samples. Once the liner was removed from the bottom of the impoundment, I walked the area taking soil conducta
2811476 Primary Facility 2018-12-06 Routine/Complete Inspection No Violations Noted Department representative Sue Herzing conducted a routine site inspection at Greylock Production LLC Whitetail flowback impoundment and well pad on December 6, 2018. The flowback impoundment has been completely reclaimed, seeded, and mulched. In addition, the well pad has been reduced in size on the S & SE sides. Both restored sides have been seeded and mulched. E&S BMPs and PCSMs remain in place and appear to be functioning as design.

Two Marcellus wells remain in production on the well pad. Well cellars are full of water and are frozen. Each well is connected to (2) 400 bbl produced fluids tanks which are stationed within a clay lined earthen secondary containment. Frozen water ~ 8-10" was observed in the earthen containment. A skid mounted compression and dehydration unit is stationed onsite. Gas leaving this Whitetail #1 pad is being fed to the NRG-Shawville Plant via a modified ECA transmission line.

No violations noted.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2006924 621294 09/29/2011 2011-09-29 102.11 - Failure to design, implement or maintain BMPs to minimize the potential for accelerated erosion and sedimentation. Administrative
2058863 636703 04/11/2012 2012-04-11 6018.301 - Residual Waste is mismanaged. Environmental Health & Safety
2095298 647765 08/29/2012 2012-08-29 91.34A - Failure to take all necessary measures to prevent spill. Inadequate diking, potential pollution Environmental Health & Safety
2183996 672793 07/17/2013 2013-07-17 307CSL - Discharge of industrial waste to waters of Commonwealth without a permit. Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
621294 275738 NOV - Notice of Violation Comply/Closed 2011-10-11
621294 278843 CACP - Consent Assessment of Civil Penalty Comply/Closed 2012-01-03 2012-01-03 $11,128.00 $11,128.00
647765 287928 NOV - Notice of Violation Comply/Closed 2012-10-01

For data sources see[8]