Well Details

Well ID: 37-105-21898
Loading map...
Country: United States
State: Pennsylvania
County: Potter
Municipality: Sweden Township
Operator Name: JKLM ENERGY LLC
Well Pad ID: 154232
Farm/Lease Name: SWEDEN VALLEY 107-4HB
License Status:
Spud Date: 2017-10-10
Permit Date: 2017-08-07
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.739266
Longitude: -77.899886

For data sources see[1][2][3]

Well History

Date Event
Deviated
2017-08-07 New Permit Application
2017-10-09 Performed Spud Operation
2018-04-12 Drilling Completion

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-05-16 2018-06-08 5,839 6,673,970 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Other Chemical(s) Listed Above See Trade Name(s) List Distillates (petroleum), hydrotreated light 64742-47-8 20 0 0
oleic acid diethanolamide 93-83-4 2 0.00126928 849.895
prop-2-yn-1-ol 107-19-7 5 0.000215808 144.502
copolymer of 2-propenamide 69418-26-4 20 0 0
xylene 1330-20-7 5 0.000215808 144.502
isoproyl alcohol 67-63-0 5 0.000215808 144.502
Water 7732-18-5 92.5 0.93386 625300
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00126928 849.895
copolymer of 2-propenamide 69418-26-4 30 0.0190392 12748.4
Alcohols, C12-16, ethoxylated 68551-12-2 2 0 0
Distillates (petroleum), hydrotreated light 64742-47-8 20 0.0126928 8498.95
Fatty imidazoline 61790-69-0 5 0.000215808 144.502
oleic acid diethanolamide 93-83-4 2 0 0
ammonium chloride 12125-02-9 1 0.000634641 424.947
ethylbenzene 100-41-4 1 0.00004316 28.9
Alcohols, C7-9-iso-, C8-rich 68526-83-0 5 0.000215808 144.502
Citric acid 77-92-9 30 0.000620092 415.205
KAI-12 Keane Acid Inhibitor prop-2-yn-1-ol 107-19-7 5 0.000215808 144.502
Alcohols, C7-9-iso-, C8-rich 68526-83-0 5 0.000215808 144.502
isoproyl alcohol 67-63-0 5 0.000215808 144.502
xylene 1330-20-7 5 0.000215808 144.502
Fatty imidazoline 61790-69-0 5 0.000215808 144.502
ethylbenzene 100-41-4 1 0.00004316 28.9
Methanol 67-56-1 90 0.00388454 2601.04
Water JKLM Carrier/Base Fluid Water 7732-18-5 100 83.1771 55,694,300.0
KFR-20 Keane Friction Reducer oleic acid diethanolamide 93-83-4 2 0.00126928 849.895
Water 7732-18-5 45 0.0285589 19122.6
copolymer of 2-propenamide 69418-26-4 30 0.0190392 12748.4
ammonium chloride 12125-02-9 1 0.000634641 424.947
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00126928 849.895
Distillates (petroleum), hydrotreated light 64742-47-8 20 0.0126928 8498.95
Sand (Proppant) Keane Proppant Crystalline silica: Quartz (SiO2) 14808-60-7 100 15.7435 10,541,700.0
KFEAC-30 Keane Iron Control Acetic acid 64-19-7 5 0.000103349 69.201
Citric acid 77-92-9 30 0.000620092 415.205
Hydrochloric Acid (7.5%) Keane Acid Inhibitor Hydrochloric Acid 7647-01-0 7.5 0.0757184 50700
Water 7732-18-5 92.5 0.93386 625300

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 JKLM ENERGY LLC 0.00 0 0.00 0 0.00 0
2018 JKLM ENERGY LLC 191,363.00 93 0.00 0 0.00 0
2019 JKLM ENERGY LLC 373,192.00 311 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 JKLM ENERGY LLC Produced Fluid 292.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2017 JKLM ENERGY LLC Produced Fluid 65.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2017 JKLM ENERGY LLC Drill Cuttings 200.69 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Produced Fluid 147.18 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 JKLM ENERGY LLC Soil Contaminated by Oil & Gas Related Spills 52.31 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Produced Fluid 2,976.25 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2018 JKLM ENERGY LLC Produced Fluid 3,346.13 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2018 JKLM ENERGY LLC Produced Fluid 967.50 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Produced Fluid 38,105.25 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2018 JKLM ENERGY LLC Waste Water Treatment Sludge 32.53 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 8.00 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Drill Cuttings 1,554.05 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 88.98 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 JKLM ENERGY LLC Synthetic Liner Materials 26.48 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Soil Contaminated by Oil 52.31 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 32.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 JKLM ENERGY LLC Produced Fluid 1,927.82 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2019 JKLM ENERGY LLC Produced Fluid 5,390.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 JKLM ENERGY LLC Produced Fluid 926.25 Bbl INJECTION DISPOSAL WELL 34-133-24096
2019 JKLM ENERGY LLC Other Oil & Gas Wastes 32.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 JKLM ENERGY LLC Produced Fluid 1,713.75 Bbl REUSE (AT WELL PAD)
2019 JKLM ENERGY LLC Produced Fluid 445.83 Bbl STORAGE PENDING DISPOSAL OR REUSE WMGR123NC038
2019 JKLM ENERGY LLC Produced Fluid 1,427.29 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 JKLM ENERGY LLC Produced Fluid 360.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2019 JKLM ENERGY LLC Soil Contaminated by Oil & Gas Related Spills 24.56 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Produced Fluid 142.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2019 JKLM ENERGY LLC Soil Contaminated by Oil 24.56 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Other Oil & Gas Wastes 665.00 Bbl REUSE (AT WELL PAD)
2019 JKLM ENERGY LLC Produced Fluid 1,963.75 Bbl INJECTION DISPOSAL WELL 34-133-24189
2019 JKLM ENERGY LLC Waste Water Treatment Sludge 10.55 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Produced Fluid 1.80 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Synthetic Liner Materials 12.81 Tons LANDFILL 301358

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2617054 Primary Facility 2017-07-18 Routine/Partial Inspection No Violations Noted On 7/18/17 at 1323 hrs I attended a preconstruction meeting for the Sweden Valley 107 well site. JKLM representatives, Jeff Long and John Manuel, and J.L. Watts representative, John Watts, were present. CB&I developed the Erosion and Sediment (E&S) control plan and J.L. Watts is the construction contractor.

We reviewed the E&S drawing. Site drainage is to an unnamed tributary to Nelson Run, which is designated as a High Quality stream. A majority of the access road was constructed under the Sweden Valley 106 ESCGP. The access road for the 107 pad will come off the existing access road and is 200 feet in length. The site will consist of a well pad (350 feet x 500 feet) and a sediment basin located off the northwest corner of the pad. The pad will be soil cemented for stability. The E&S drawing shows that a wash rack is to be installed on the access road. JKLM would prefer to install an additional 50 feet of rock constructed entrance in lieu of the wash rack; this is an acceptable alternative when a sediment

2633733 Primary Facility 2017-09-06 Preoperation Inspection No Violations Noted On 9/6/17 at 0938 hrs I conducted a preoperational inspection at the Sweden Valley 107 well site. It was mostly cloudy and 61 degrees F.

I observed the site and the routine Erosion and Sediment (E&S) control inspection log. Earth disturbance is complete. The pad surface and access road will be soil cemented and rocked within the next week or so. E&S controls are installed and disturbed areas have been stabilized with seed and mulch or erosion control blanket; seed has germinated in some areas.

Cellars have not yet been installed. Well permits for the Sweden Valley 107 1HU, 2HU, 3HM and 4HB have been issued.

The last routine E&S inspection was conducted on 8/30/17. No violations are cited during this inspection. I concluded the inspection at 1052 hrs. TLT

2650286 Primary Facility 2017-10-19 Routine/Complete Inspection No Violations Noted Well is conductor only. Well was drilled and cemented on 10-10-17.
2695960 Primary Facility 2018-02-15 Routine/Complete Inspection No Violations Noted The Department of Environmental Protection (DEP) inspected the JKLM Sweden Valley 107 well pad located in Sweden Twp., Potter Co. on 2/15/2018 @1300 hours. The weather was 48 degrees and sunny causing accumulated snow to melt and the pad surface and access road to be very wet/muddy. JKLM representatives Jon Manuel and Ron Hall were present for my inspection. The H&P 500 flex rig is onsite and is currently drilling the 1HU well. The rig was at a depth of 11,474’ feet at the time of my inspection. Mr. Hall stated no issues have been encountered. The rig will be drilling 4 wells while onsite the 1HU, 2HU, 3HM and 4HB. Fluid was observed accumulating along the eastern side of the pad-wide containment. Fluid in containment had a field measured conductivity of between 6.82 mS/cm and 8.28 mS/cm. A puddle on the ground surface approximately 1-2 feet off the edge of containment had an elevated conductivity of 7.23 mS/cm. Additional screening of the surrounding area showed the elevated area to be isolated. A vac truck
2719492 Primary Facility 2018-04-17 Routine/Complete Inspection No Violations Noted At the time of this inspection the drilling of this well was complete and the drilling rig was rigging down and being moved.
2730080 Primary Facility 2018-05-15 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM-Sweden Valley 107 well pad located in Sweden Township, Potter County. The weather was 77° mostly cloudy with severe thunderstorms in the area, winds W 12 mph, 61% humidity. Chris Wiley, JKLM was present onsite.

JKLM was preparing to frack the 1HU, 2HU, 3HU and 4 HB with contractor Keane Frack. Mr. Wiley stated they were hoping to begin fracking later this afternoon. The onsite AST, containment and E&S controls were observed. No puddles or staining was observed around the AST. All duckponds observed appeared dry. All observed puddles, on the pads surface, were measured for field conductivity and found to be within normal range. Rain water was accumulating inside the northern edge of the primary containment. Mr. Wiley was informed of the finding. Due to severe thunderstorms and the potential for heavy precipitation, storage capacity of primary containment should be monitored.

A sheen and bubbles/foam were observed in water standing in the E&S channels in th

2735320 Primary Facility 2018-05-30 Routine/Complete Inspection No Violations Noted This well was being fractured at the time of this inspection
2738173 Primary Facility 2018-06-06 Routine/Complete Inspection No Violations Noted At the time of this inspection there was 9 of the24 total stages completed. Additional information on averages of all other pressures and rates was not available at this time.
2740716 Primary Facility 2018-06-06 Routine/Complete Inspection No Violations Noted The DEP conducted an INCDENT inspection of the JKLM – Sweden Valley 107 well pad located in Sweden Twp., Potter Co. @ 1045 hours on 6/6/2018 in response to spill#334721 reported to the DEP on 6/5/2018 @1534 hours. The weather was 58 degrees and overcast.

A representative from JKLM contractor Whipper Hill Consulting was onsite conducting a grid screening of the impacted area. The following information was provided.

On 6/5/2018, sometime between 1000 – 1330 hours, a contractor punctured the pad-wide containment beneath the sand boxes located along the northern edge of containment. An unknown volume of fluid exhibiting an elevated conductivity flowed to the northern edge of containment, thought to be the “low spot”, where it exited the puncture causing a puddle to form outside of containment. The representative stated the puddle had a field measured conductivity of >20mS/cm. A vacuum truck was dispatched to remove the standing liquid from the pad surface.

The initial soil conductivity of the saturated pad s

2745361 Primary Facility 2018-06-25 Routine/Complete Inspection No Violations Noted At the time of this inspection the hydraulic fracturing of this well was complete.
2783182 Primary Facility 2018-10-01 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM - Sweden Valley 107 well pad located in Sweden Twp., Potter Co. on 10/1/2018 @1240 hours. DEP Env Trainee, was present onsite for the inspection. The weather was 73 degrees, partly sunny.

Company personnel onsite appeared to be repairing a dehydration unit that had sprayed glycol onto the pad surface on 9/28/2018. The glycol release was below the reportable limit (but had been reported to the DEP), and appeared remediated by the time of this inspection.

The pad surface appeared very wet and muddy around the well heads, AST and main traffic areas. Puddles on the pad surface, near the production tanks, tested for field conductivity with an Oakton Multi-Parameter PCTestr and a Groline soil conductivity meter measured ~1000 uS/cm.

A number of flowback tanks were arranged, on secondary containment, along the eastern side of the pad. Standing fluid in the secondary containment had a field measured conductivity of "Over Range" or >20.00mS/cm. A large wet/damp

2820225 Primary Facility 2018-12-20 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM Sweden Valley 107 well pad located in Sweden Twp, Potter Co on 12/20/2018 @1230 hours. The weather was overcast, 34 degrees.

The well pad is currently setup for flowback/production. Personnel were present onsite to monitor transfers from/to the Aboveground Storage Tank (AST). A temporary fluid line was observed connecting the production tanks to the AST, but did not appear to be in use. Fluid with a field measured conductivity of "Over Range" or >19.99 mS/cm was observed in the production tank containment. Puddles screened on the pad surface measured <1000uS/cm.

Violations from an inspection dated 10/29/2018, remain outstanding at this site from a previous release. Site remediation has been performed and a Remediation Action Completion Report has been submitted to DEP’s Environmental Cleanups and Brownfields program for review. The outstanding violations will be closed once attainment with Act 2 standards has be confirmed.

2846831 Primary Facility 2019-02-28 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM - Sweden Valley 107 Well Pad located in Sweden Twp, Potter Co. on 2/282019 @1230 hours. The weather was 23 degrees, sunny, winds N 4mph,63% humidity, 2-3" of snow deposited over the previous 24 hrs. The well pad appears to be setup for flowback/production. 4 wells were observed connected to sand traps and a gas buster. 17 orange roll-off tanks were observed on containment on the along the south side of the well pad.
2848098 Primary Facility 2019-03-05 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was in production. There are three (3) annulus vents that are vented to surface. These annulus vents were checked for combustible gas on each annulus vent. Results of this testing were 0 LEL ( lower explosion limit) and 0 Methane on vent 18 x 13 and 100% LEL and 5% Methane on vent 13 x 9 and 0% LEL and 0% Methane on the 9 x 5. A gauge on the well showed a pressure of 1900 psi ( pounds per square inch ) . No violations were noted at this inspection.