If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 37-115-21668 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.831967,"lon":-75.582017,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Susquehanna | |
Municipality: Jackson Township | |
Operator Name: CABOT OIL & GAS CORP | |
Well Pad ID: 150898 | |
Farm/Lease Name: SLOCUM S 5 | |
License Status: | |
Spud Date: | |
Permit Date: 2014-02-21 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 41.831967 | |
Longitude: -75.582017 |
Date | Event |
---|---|
2014-02-21 | New Permit Application |
2014-04-30 | Performed Spud Operation |
2014-05-30 | Drilling Completion |
2014-07-18 | Perforation |
2016-07-29 | DEVIATED |
For data sources see[4]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 2014-07-17 | 2014-08-06 | 6,839 | 13,410,300 | 0 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | Plexslick 957 | Chemplex | Friction Reducer | Poly (acrylamide-co-acrylic acid), partial sodium salt | 62649-23-4 | 35 | 0.0309776 | 39480.7 |
Paraffinic, Naphtehenic Solvent | 64742-47-8 | 30 | 0.0265522 | 33840.6 | ||||
Nonionic Surfactants | Proprietary | 1.5 | 0.00132761 | 1692.03 | ||||
Ammonium Chloride | 12125-02-9 | 5 | 0.00442537 | 5640.1 | ||||
Plexhib 256 | Chemplex | Acid Inhibitor | Methyl Alcohol | 67-56-1 | 60 | 0.000500036 | 637.291 | |
Polyethoxylated Alcohol Surfactant | 68951-67-7 | 30 | 0.000250018 | 318.645 | ||||
C-14 to C-16 Alpha Olefins | 64743-02-8 | 5 | 0.00004167 | 53.108 | ||||
Propargyl Alcohol | 107-19-7 | 10 | 0.00008334 | 106.215 | ||||
Thiourea/Formaldehyde Copolymer | 68527-49-1 | 30 | 0.000250018 | 318.645 | ||||
Greenhib 679 | Chemplex | Friction Reducer | Proprietary | Proprietary | 35 | 0.00862925 | 10997.9 | |
Glycerine | 56-81-5 | 20 | 0.004931 | 6284.52 | ||||
Ferriplex 40 | Chemplex | Iron Control | Trisodium Nitrilotriacetate | 5064-31-3 | 40 | 0.00125978 | 1605.58 | |
Sodium Hydroxide | 1310-73-2 | 1 | 0.00003149 | 40.139 | ||||
Sodium Sulfate Anhydrous | 7757-82-6 | 2 | 0.00006299 | 80.279 | ||||
Sand (Proppant) | TSS | Proppant | Silica Substrate | 14808-60-7 | 100 | 11.0398 | 14,070,100.0 | |
Plexbreak 145 | Chemplex | Non-Emulsifier | Cocamide Based Surfactant | Proprietary | 10 | 0.00009303 | 118.566 | |
Methyl Alcohol | 67-56-1 | 15 | 0.000139545 | 177.849 | ||||
Diethanolamine | 111-42-2 | 3 | 0.00002791 | 35.57 | ||||
2-Butoxyethanol | 111-76-2 | 15 | 0.000139545 | 177.849 | ||||
Plexcide 15G | Chemplex | Biocide | Didecyl Dimethyl Ammonium Chloride | 7173-51-5 | 3 | 0.000676097 | 861.68 | |
Alkyl Dimethyl Benzyl Ammonium Chloride | 68424-85-1 | 3 | 0.000676097 | 861.68 | ||||
Glutaraldehyde | 111-30-8 | 14 | 0.00315512 | 4021.17 | ||||
Ethanol | 64-17-5 | 3 | 0.000676097 | 861.68 | ||||
Water | Baker | Carrier/Base Fluid | Water | 7732-18-5 | 100 | 88.3012 | 112,539,000.0 | |
Hydrochloric Acid (15%) | Reagent | Acidizing | Hydrochloric Acid | 7647-01-0 | 15 | 0.0777672 | 99113.6 |
For data sources see[5]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2014 | CABOT OIL & GAS CORP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2015 | CABOT OIL & GAS CORP | 1,387,879.06 | 219 | 0.00 | 0 | 0.00 | 0 |
2016 | CABOT OIL & GAS CORP | 1,377,837.82 | 366 | 0.00 | 0 | 0.00 | 0 |
2017 | CABOT OIL & GAS CORP | 786,359.25 | 359 | 0.00 | 0 | 0.00 | 0 |
2018 | CABOT OIL & GAS CORP | 696,341.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2019 | CABOT OIL & GAS CORP | 572,641.00 | 365 | 0.00 | 0 | 0.00 | 0 |
For data sources see[6]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2014 | CABOT OIL & GAS CORP | Fracing Fluid Waste | 1,658.50 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE001 |
2014 | CABOT OIL & GAS CORP | Drill Cuttings | 1,117.07 Tons | LANDFILL | 101247 |
2014 | CABOT OIL & GAS CORP | Fracing Fluid Waste | 12,255.05 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2015 | CABOT OIL & GAS CORP | Fracing Fluid Waste | 7,974.72 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2015 | CABOT OIL & GAS CORP | Produced Fluid | 10,793.91 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2015 | CABOT OIL & GAS CORP | Produced Fluid | 30.70 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE001 |
2016 | CABOT OIL & GAS CORP | Produced Fluid | 59.06 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123NE004 |
2016 | CABOT OIL & GAS CORP | Produced Fluid | 1,362.84 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2016 | CABOT OIL & GAS CORP | Waste Water Treatment Sludge | 4.38 Tons | LANDFILL | 301358 |
2016 | CABOT OIL & GAS CORP | Produced Fluid | 3,677.35 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2017 | CABOT OIL & GAS CORP | Synthetic Liner Materials | 0.89 Tons | LANDFILL | 101247 |
2017 | CABOT OIL & GAS CORP | Produced Fluid | 980.88 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC018 |
2017 | CABOT OIL & GAS CORP | Produced Fluid | 1,135.28 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE004 |
2017 | CABOT OIL & GAS CORP | Produced Fluid | 319.95 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2018 | CABOT OIL & GAS CORP | Produced Fluid | 1,761.41 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2018 | CABOT OIL & GAS CORP | Produced Fluid | 188.36 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE004 |
2018 | CABOT OIL & GAS CORP | Produced Fluid | 950.15 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC018 |
2019 | CABOT OIL & GAS CORP | Produced Fluid | 344.74 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2019 | CABOT OIL & GAS CORP | Produced Fluid | 1,513.32 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE004 |
For data sources see[7]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2264735 | Primary Facility | 2014-04-21 | Routine/Complete Inspection | No Violations Noted | . With all of the above mentioned changes that have occurred on the site, the Department requires that Cabot have the design engineer review conditions on the ground and submit a new revised site plan reflecting the site changes along with BMP changes that may be required. This inspection does not qualify as a preoperational inspection. A preoperational inspection will be conducted after the Department reviews the updated site plan. |
2266524 | Primary Facility | 2014-04-29 | Preoperation Inspection | No Violations Noted | The Department was on site on 4/29/14 at the Cabot Slocum S. Well Site to conduct a Preoperational Inspection. Well permits that have been issued for this pad are the 1H (115-21666), 3H (115-21667), and the 5H (115-21668). |
2269189 | Primary Facility | 2014-05-07 | Routine/Complete Inspection | No Violations Noted | The 1H (115-21666), 3H (115-21667), and the 5H (115-21668) wells have been spud and associated conductors set. Contractors are installing newly designed steel rectangular cellars. The cellars, when complete, will be welded to the conductor pipe creating a tight seal. This NOV will be associated with the 1H well permit. |
2269678 | Primary Facility | 2014-05-12 | Drilling/Alteration | No Violations Noted | |
2272011 | Primary Facility | 2014-04-17 | Routine/Complete Inspection | No Violations Noted | The Department was on site on 4/17/14 at the Cabot Slocum S. Well Site to conduct an inspection. Inspection is a follow-up inspection to evaluate how the pad construction is progressing. Well permits that have been issued for this pad are the 1H (115-21666), 3H (115-21667), and the 5H (115-21668). The tank pad is approximately 95% complete. The perimeter BMP’s are in place for this pad. The top soil stock pile and a timber pile that have been installed above the cut slope of the tank pad have not been red lined onto the site plans. The well pad has been cleared and grubbed. Large pools of standing water are present on the well pad location. The site has still not evolved to the point where a pre-operational inspection would be warranted. This inspection does not qualify as a pre-operational inspection. Will re-inspect in near future |
2272017 | Primary Facility | 2014-04-10 | Routine/Complete Inspection | No Violations Noted | The Department was on site on 4/10/14 at the Cabot Slocum S. Well Site to conduct an inspection. Inspection based on Cabot notification that well spudding of this pad is to occur in the very near future, but that site conditions exist which are impeding construction. Well permits that have been issued for this pad are the 1H (115-21666), 3H (115-21667), and the 5H (115-21668). The tank pad is approximately 90% complete. The perimeter BMP’s are in place for this pad. A top soil stock pile and a timber pile have been installed on above the cut slope of the tank pad. Pointed out to George Bishop, GDS foreman, that these features were not on the E&S plans and that they needed to be red lined onto the site plans. The well pad has been cleared, and is currently being grubbed. This inspection does not qualify as a pre-operational inspection. Will re-inspect in near future |
2272148 | Primary Facility | 2014-05-21 | Administrative/File Review | No Violations Noted | This administrative inspection has been created to document Cabot’s response letter related to violations noted in the 4/29/14 NOV/inspection record # 2266507 and the associated enforcement record # 310543. Attached is a copy of the response letter. |
2273693 | Primary Facility | 2014-05-21 | Follow-up Inspection | No Violations Noted | The Department was on site on 5//14 at the Cabot Slocum S. Well Site to conduct a follow up inspection. Well permits that have been issued for this pad are the 1H (115-21666), 3H (115-21667), and the 5H (115-21668). |
2285945 | Primary Facility | 2014-05-21 | Drilling/Alteration | No Violations Noted | H&P Drilling Rig #371 is the active rig on location, currently drilling the S Slocum 5H well. The current drilling depth is (4,743.21) feet. Cabot is drilling the lateral section of the well below the intermediate string through the process of water based mud drilling. A white powdery susbstance, was observed spilled to the drilling rig containment. A light tower did not have properly secured containment. The secondary containment berm in the backyard next to the drill cuttings containers was not secured properly. Mr. Wyant contacted rig hands just before the Department left the site to request the white powdery substance spilled to containment be cleaned up immediately and all insecure areas of secondary containment on the location be compleltely secured immediately as well. |
2477063 | Primary Facility | 2016-04-21 | Routine/Complete Inspection | No Violations Noted | |
2484895 | Primary Facility | 2016-05-17 | Routine/Complete Inspection | No Violations Noted | On 5/17/16, the Department conducted an inspection of the COG Slocum, S. Pad located in Jackson Township, Susquehanna County. The inspection was in response to Cabot’s self-reporting of a spill of 12 gallons of antifreeze on the access road of the pad. According to Steve Watson, COG EH&S Specialist at around 7:00 PM, 5/16/16, the previous evening the driver of a low boy who was delivering a piece of machinery noticed that his truck was leaking antifreeze, a line had sprung a leak. J.P. Reilly is the contractor and began the clean-up of the spill. Not sure exactly how much material spilled on the access road as opposed to how much was lost in travel, but after the line was fixed, 12 gallons of antifreeze was added to the reservoir, hence the 12 gallon reporting. Today’s inspection revealed that approximately 3 tons of material has been excavated and placed in a lined roll-off container. According to Jose Fernandez of J.P. Reilly, Resource Environmental had just left, and that they had collected soil sam |
2493190 | Primary Facility | 2016-06-15 | Routine/Complete Inspection | No Violations Noted | |
2531817 | Primary Facility | 2016-10-24 | Routine/Complete Inspection | No Violations Noted | |
2563597 | Primary Facility | 2017-02-21 | Routine/Complete Inspection | No Violations Noted | At time of inspection, arrived on site at 13:45p.m., the cellar was about a quarter full of ice. The (13x9) annulus vent pipe was open and venting into a small plastic tank, the (9x5) annulus vent pipe was open and venting into a small plastic tank. There was 624psi on the production casing. I took a walk around the location and there were no obvious concerns noticed.
I left the site at 14:15p.m. |
2684060 | Primary Facility | 2018-01-08 | Routine/Complete Inspection | No Violations Noted | At time of inspection.
The cellar had snow 5' below grade and there was no gas detected. The (13x9) and (9x5) annuli vent pipes were connected together and venting to the same tank. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted. |
2708533 | Primary Facility | 2018-03-21 | Routine/Complete Inspection | No Violations Noted | Today's inspection was conducted as a routine inspection. No E&S issues were identified. No violations noted. |
2779283 | Primary Facility | 2018-09-25 | Routine/Complete Inspection | No Violations Noted | At time of inspection.
The well was in production. There was water 3' below grade in the cellar with no bubbling noticed and there was no gas detected in the remainder of the cellar. The (13x9) and (9x5) annuli vent pipes were connected together and going to the same poly vent tank. There was gas detected at the poly vent tank. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted. |
2844389 | Primary Facility | 2019-02-25 | Routine/Complete Inspection | No Violations Noted | Today's inspection was conducted as a routine inspection. Overall the site appears to have good stabilization. No E&S issues identified. No violations noted. |
For data sources see[8]