37-115-22238

Well Details

Well ID: 37-115-22238
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Great Bend Township
Operator Name: SWN PROD CO LLC
Well Pad ID: 146865
Farm/Lease Name: TONYA EAST 3H
License Status:
Spud Date: 2016-11-06
Permit Date: 2016-10-26
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.909993
Longitude: -75.656052

For data sources see[1][2][3]

Well History

Date Event
Deviated
2016-10-26 New Permit Application
2016-11-04 Performed Spud Operation
2017-01-06 Drilling Completion

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-03-30 2017-04-07 6,170 10,256,200 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 LP-65-MC Halliburton Scale Inhibitor Listed Below Listed Below 0 0 0
Ingredients Listed Above Listed Above Water 7732-18-5 100 1.21651 1,228,870.0
Fresh Water Operator Base Fluid Water 7732-18-5 100 84.5748 85,434,100.0
FR-76 Halliburton Friction Reducer Listed Below Listed Below 0 0 0
HAI-OS ACID INHIBITOR Halliburton Corrosion Inhibitor Listed Below Listed Below 0 0 0
SAND-PREMIUM WHITE-30/50, BULK Halliburton Proppant Listed Below Listed Below 0 0 0
SAND-COMMON WHITE-100 MESH, SSA-2, BULK (100003676) Halliburton Proppant Listed Below Listed Below 0 0 0
HCL >10% Halliburton Solvent Listed Below Listed Below 0 0 0
Acrylamide acrylate copolymer Proprietary 30 0.0244771 24726
Propargyl alcohol 107-19-7 10 0.00009243 94
Ammonium chloride 12125-02-9 10 0.00239125 2416
Crystalline silica, quartz 14808-60-7 100 14.1656 14,309,500.0
Propylene glycol 57-55-6 60 0.0228615 23094
Tributyl tetradecyl phosphonium chloride 81741-28-8 10 0.00381025 3849
Methanol 67-56-1 60 0.000554561 561
Fatty acids, tall oil Proprietary 30 0.000277281 281
Hydrochloric acid 7647-01-0 30 0.334532 337931
Ethoxylated alcohols Proprietary 30 0.000277281 281
Organic phosphonate Proprietary 60 0.0143475 14494
Inorganic salt Proprietary 30 0.0244771 24726
Hydrotreated light petroleum distillate 64742-47-8 30 0.0244771 24726
Olefins Proprietary 5 0.000110912 114
Reaction product of acetophenone,
formaldehyde, thiourea
and oleic acid in dimethyl formamide
68527-49-1 30 0.000277281 281
BE-9W Halliburton Biocide Listed Below Listed Below 0 0 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2016 SWN PROD CO LLC 0.00 0 0.00 0 0.00 0
2017 SWN PROD CO LLC 2,616,675.00 248 0.00 0 0.00 0
2018 SWN PROD CO LLC 1,562,127.00 345 0.00 0 0.00 0
2019 SWN PROD CO LLC 930,340.00 361 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2016 SWN PROD CO LLC Drilling Fluid Waste 1,318.00 Bbl REUSE OTHER THAN ROAD SPREADING
2016 SWN PROD CO LLC Other Oil & Gas Wastes 50.25 Bbl REUSE OTHER THAN ROAD SPREADING
2016 SWN PROD CO LLC Drill Cuttings 709.80 Tons LANDFILL 101247
2016 SWN PROD CO LLC Fracturing Fluid Waste 554.00 Bbl REUSE OTHER THAN ROAD SPREADING
2016 SWN PROD CO LLC Produced Fluid 56.00 Bbl REUSE OTHER THAN ROAD SPREADING
2017 SWN PROD CO LLC Other Oil & Gas Wastes 27.50 Bbl REUSE (AT WELL PAD)
2017 SWN PROD CO LLC Drilling Fluid Waste 1,030.00 Bbl REUSE (AT WELL PAD)
2017 SWN PROD CO LLC Other Oil & Gas Wastes 225.75 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2017 SWN PROD CO LLC Synthetic Liner Materials 3.17 Tons LANDFILL 100933
2017 SWN PROD CO LLC Produced Fluid 320.00 Bbl REUSE OTHER THAN ROAD SPREADING
2017 SWN PROD CO LLC Produced Fluid 320.00 Bbl SURFACE IMPOUNDMENT 826342
2017 SWN PROD CO LLC Synthetic Liner Materials 5.00 Tons LANDFILL 101247
2017 SWN PROD CO LLC Produced Fluid 18,842.25 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2017 SWN PROD CO LLC Unused Fracturing Fluid Waste 13.75 Tons LANDFILL THR029
2017 SWN PROD CO LLC Other Oil & Gas Wastes 110.00 Bbl REUSE OTHER THAN ROAD SPREADING
2018 SWN PROD CO LLC Other Oil & Gas Wastes 28.50 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Produced Fluid 4,802.25 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2018 SWN PROD CO LLC Produced Fluid 907.25 Bbl REUSE (AT WELL PAD)
2018 SWN PROD CO LLC Produced Fluid 516.25 Bbl SURFACE IMPOUNDMENT 826342
2018 SWN PROD CO LLC Other Oil & Gas Wastes 46.73 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Produced Fluid 92.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC035
2019 SWN PROD CO LLC Produced Fluid 1,232.00 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Produced Fluid 394.00 Bbl SURFACE IMPOUNDMENT 826342
2019 SWN PROD CO LLC Other Oil & Gas Wastes 67.32 Bbl SURFACE IMPOUNDMENT 95-16-65420-013
2019 SWN PROD CO LLC Soil Contaminated by Oil 0.10 Tons RESIDUAL WASTE PROCESSING FACILITY 301333
2019 SWN PROD CO LLC Soil Contaminated by Oil & Gas Related Spills 0.10 Tons RESIDUAL WASTE PROCESSING FACILITY 301333

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2535073 Primary Facility 2016-11-08 Drilling/Alteration No Violations Noted At time of inspection, arrived on site at 10:45a.m. for a new spud inspection. The conductor pipe is drilled and set. A cement truck was on site to put cement in the mouse holes. The conductor pipe was drilled and set by Minichi. I spoke with Marvin Gilpin of Minichi, the conductor pipe was set at 218' on the 5H and 225' on the 3H. I took a walk around the location and there were no obvious concerns noticed.

I left the site at 10:55a.m.

2540498 Primary Facility 2016-11-29 Drilling/Alteration No Violations Noted At time of inspection, arrived on site at 9:45a.m., met with company man Robert Gray, Falcon Rig 23 was on site and rigging up on the 5H well. The top hole section of the 3H was drilled to a depth of 5260'. I took a walk around the location and there were no obvious concerns noticed.

I left the site at 11:20a.m.

2549637 Primary Facility 2017-01-04 Drilling/Alteration No Violations Noted At time of inspection, arrived on site at 9:20a.m., met with company man Dan Hessdorfer, SDC 45 was on site and drilling the lateral section of the well. The top hole section of the well was drilled and completed by Falcon Rig 23 on 11/29/16. I took a walk around the location and there were no obvious concerns noticed.

Depth at time of inspection was 8306'. Projected TD of the well is 13,914' I left the site at 10:15a.m.

2574274 Primary Facility 2017-03-21 Routine/Complete Inspection No Violations Noted The Department was on site to conduct an inspection. The E&S Inspection Log Site Checklist indicated that Ryan Klemish conducted the most recent inspection on 3/17/17. Upon my arrival I spoke to the gate guard but explained that I would only be inspecting the area along the access road where a crew was working. The site is currently being hydraulically fractured.

I spoke with Ed Stone and "Smoke" (Linde) who explained that they were repairing an area where a snow plow impacted the E&S controls. No obvious issues were discovered. The site was covered in approximately 2' of snow during the inspection.

2578180 Primary Facility 2017-03-23 Follow-up Inspection No Violations Noted The Department was on site to follow up on the Department's 3/21/17 inspection. The Department only inspected the area adjacent to the access road where the E&S controls were damaged.
2585082 Primary Facility 2017-04-18 Drilling/Alteration No Violations Noted At time of inspection, arrived on site at 11:35a.m.

I met with company man Ed Blystone. The 1H, 3H, and 5H wells were recently stimulated CWS (Consolidated Well Service) Rig was on site drilling out the plugs and cleaning the wells out to TD. The plugs were drilled out of the 5H and cleaned out to TD. The rig was running drill pipe into the 3H and started drilling out the plugs. There were 33 stages on the 1H, 35 stages on the 3H, and 31 stages on the 5H. I took a walk around the location and there were no obvious concerns noticed. I left the site at 12:10p.m.

2598964 Primary Facility 2017-05-16 Routine/Complete Inspection No Violations Noted I initially met with Bob Lamberton, who is part of the SWN Production Company LLC Water Team around 12:15 on the Range Unit 74, Tretter Pad. Mr. Lamberton conducts inspections of secondary containment at various SWN well sites per Department regulations. I had inquired with Mr. Lamberton as to what type of site operations where in progress at the Range Unit 13 (Tonya East) Pad as my intent was to conduct an inspection at that pad, not the Tretter Pad. Mr. Lamberton stated that flowback of the wells was in progress on the Tonya East Pad. The Tretter pad is located near the Tonya East, Range Unit 13 Pad. The pads share the same entrance road off East Lake Road. I arrived at the Tonya East Pad at 12:30. There was no SWN personnel at the site during the inspection. Flowback of the Tonya East 1H, 3H and 5H wells is in progress. The Tonya East 4H well is in production. It is apparent that natural gas is being sent to sales through the gathering pipeline as the gas production units for the 1H, 3H and 5H wells are
2604226 Primary Facility 2017-06-13 Routine/Complete Inspection No Violations Noted At time of inspection, arrived on site at 10:50a.m.

The well was recently completed and is in production. The well tag was on the well and correct. The cellar was set up with a plastic corrugated pipe around the well for inspection access; there was water above the surface casing with no bubbling noticed. The (9x5) annulus vent pipe was open and set up with a Taylor plug to check for pressure with a Crystal pressure gauge, the valve going to the production tank was closed. There was 587psi on the production casing. There were 500bbl tanks still on site from the recent stimulations of the 1H, 3H and 5H wells, the tanks were empty and on containment, the containment appeared to be in good condition. I took a walk around the location and there were no obvious concerns noticed. I left the site at 11:35a.m.

2709592 Primary Facility 2018-03-21 Routine/Complete Inspection No Violations Noted At time of inspection.

The well was in production. The cellar was set up with a corrugated pipe around the well for inspection access. The (20x13) and (13x9) annuli were below the water level and there was no bubbling noticed. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2812745 Primary Facility 2018-12-10 Routine/Complete Inspection No Violations Noted At time of inspection.

The well was in production. The cellar was set up with a plastic corrugated pipe around the well for inspection access. There was water .5' below grade in the cellar and there was no bubbling noticed. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

For data sources see[8]

References